EX
|
|
|
627,006.80
|
₽ 68.36
|
₽ 42,863,400.00
|
|
EX
|
Benua Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Benua Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Benua Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Tihoretskiy Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Tihoretskiy Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Tihoretskiy Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Kurchatov Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Kurchatov Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Kurchatov Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Politekh Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Politekh Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Politekh Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Atom Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Atom Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Atom Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
RTK Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
RTK Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
RTK Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P101
|
|
18,104.80
|
₽ 68.40
|
₽ 1,238,400.00
|
|
EX
|
P101
|
Hand Soil Excavation (cum)
|
296.80
|
₽ 3,566.04
|
₽ 1,058,400.00
|
|
EX
|
P101
|
Mechanised Soil Excavation (cum)
|
17,808.00
|
₽ 10.11
|
₽ 180,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P102
|
|
23,436.20
|
₽ 68.37
|
₽ 1,602,300.00
|
|
EX
|
P102
|
Hand Soil Excavation (cum)
|
384.20
|
₽ 3,561.43
|
₽ 1,368,300.00
|
|
EX
|
P102
|
Mechanised Soil Excavation (cum)
|
23,052.00
|
₽ 10.15
|
₽ 234,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P103
|
|
27,925.80
|
₽ 68.25
|
₽ 1,905,900.00
|
|
EX
|
P103
|
Hand Soil Excavation (cum)
|
457.80
|
₽ 3,560.29
|
₽ 1,629,900.00
|
|
EX
|
P103
|
Mechanised Soil Excavation (cum)
|
27,468.00
|
₽ 10.05
|
₽ 276,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P104
|
|
22,252.80
|
₽ 68.35
|
₽ 1,521,000.00
|
|
EX
|
P104
|
Hand Soil Excavation (cum)
|
364.80
|
₽ 3,560.86
|
₽ 1,299,000.00
|
|
EX
|
P104
|
Mechanised Soil Excavation (cum)
|
21,888.00
|
₽ 10.14
|
₽ 222,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P105
|
|
18,104.80
|
₽ 68.40
|
₽ 1,238,400.00
|
|
EX
|
P105
|
Hand Soil Excavation (cum)
|
296.80
|
₽ 3,566.04
|
₽ 1,058,400.00
|
|
EX
|
P105
|
Mechanised Soil Excavation (cum)
|
17,808.00
|
₽ 10.11
|
₽ 180,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P106
|
|
20,691.20
|
₽ 68.19
|
₽ 1,410,900.00
|
|
EX
|
P106
|
Hand Soil Excavation (cum)
|
339.20
|
₽ 3,558.08
|
₽ 1,206,900.00
|
|
EX
|
P106
|
Mechanised Soil Excavation (cum)
|
20,352.00
|
₽ 10.02
|
₽ 204,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P107
|
|
19,422.40
|
₽ 68.27
|
₽ 1,326,000.00
|
|
EX
|
P107
|
Hand Soil Excavation (cum)
|
318.40
|
₽ 3,561.56
|
₽ 1,134,000.00
|
|
EX
|
P107
|
Mechanised Soil Excavation (cum)
|
19,104.00
|
₽ 10.05
|
₽ 192,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P108
|
|
23,899.80
|
₽ 68.40
|
₽ 1,634,700.00
|
|
EX
|
P108
|
Hand Soil Excavation (cum)
|
391.80
|
₽ 3,559.72
|
₽ 1,394,700.00
|
|
EX
|
P108
|
Mechanised Soil Excavation (cum)
|
23,508.00
|
₽ 10.21
|
₽ 240,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P109
|
|
23,277.60
|
₽ 68.40
|
₽ 1,592,250.00
|
|
EX
|
P109
|
Hand Soil Excavation (cum)
|
381.60
|
₽ 3,559.36
|
₽ 1,358,250.00
|
|
EX
|
P109
|
Mechanised Soil Excavation (cum)
|
22,896.00
|
₽ 10.22
|
₽ 234,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P110
|
|
25,790.80
|
₽ 68.32
|
₽ 1,762,050.00
|
|
EX
|
P110
|
Hand Soil Excavation (cum)
|
422.80
|
₽ 3,557.36
|
₽ 1,504,050.00
|
|
EX
|
P110
|
Mechanised Soil Excavation (cum)
|
25,368.00
|
₽ 10.17
|
₽ 258,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P111
|
|
22,606.60
|
₽ 68.48
|
₽ 1,548,000.00
|
|
EX
|
P111
|
Hand Soil Excavation (cum)
|
370.60
|
₽ 3,561.79
|
₽ 1,320,000.00
|
|
EX
|
P111
|
Mechanised Soil Excavation (cum)
|
22,236.00
|
₽ 10.25
|
₽ 228,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Akadem Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Akadem Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Akadem Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Nauki Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Nauki Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Nauki Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P201
|
|
29,097.00
|
₽ 68.26
|
₽ 1,986,300.00
|
|
EX
|
P201
|
Hand Soil Excavation (cum)
|
477.00
|
₽ 3,560.38
|
₽ 1,698,300.00
|
|
EX
|
P201
|
Mechanised Soil Excavation (cum)
|
28,620.00
|
₽ 10.06
|
₽ 288,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P202
|
|
29,097.00
|
₽ 68.26
|
₽ 1,986,300.00
|
|
EX
|
P202
|
Hand Soil Excavation (cum)
|
477.00
|
₽ 3,560.38
|
₽ 1,698,300.00
|
|
EX
|
P202
|
Mechanised Soil Excavation (cum)
|
28,620.00
|
₽ 10.06
|
₽ 288,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P203
|
|
27,803.80
|
₽ 68.25
|
₽ 1,897,650.00
|
|
EX
|
P203
|
Hand Soil Excavation (cum)
|
455.80
|
₽ 3,557.81
|
₽ 1,621,650.00
|
|
EX
|
P203
|
Mechanised Soil Excavation (cum)
|
27,348.00
|
₽ 10.09
|
₽ 276,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P204
|
|
30,390.20
|
₽ 68.21
|
₽ 2,073,000.00
|
|
EX
|
P204
|
Hand Soil Excavation (cum)
|
498.20
|
₽ 3,558.81
|
₽ 1,773,000.00
|
|
EX
|
P204
|
Mechanised Soil Excavation (cum)
|
29,892.00
|
₽ 10.04
|
₽ 300,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
CHapaev Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
CHapaev Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
CHapaev Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
Budenniy Tower
|
|
14,871.80
|
₽ 68.57
|
₽ 1,019,700.00
|
|
EX
|
Budenniy Tower
|
Hand Soil Excavation (cum)
|
243.80
|
₽ 3,567.27
|
₽ 869,700.00
|
|
EX
|
Budenniy Tower
|
Mechanised Soil Excavation (cum)
|
14,628.00
|
₽ 10.25
|
₽ 150,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P301
|
|
29,097.00
|
₽ 68.26
|
₽ 1,986,300.00
|
|
EX
|
P301
|
Hand Soil Excavation (cum)
|
477.00
|
₽ 3,560.38
|
₽ 1,698,300.00
|
|
EX
|
P301
|
Mechanised Soil Excavation (cum)
|
28,620.00
|
₽ 10.06
|
₽ 288,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P302
|
|
29,097.00
|
₽ 68.26
|
₽ 1,986,300.00
|
|
EX
|
P302
|
Hand Soil Excavation (cum)
|
477.00
|
₽ 3,560.38
|
₽ 1,698,300.00
|
|
EX
|
P302
|
Mechanised Soil Excavation (cum)
|
28,620.00
|
₽ 10.06
|
₽ 288,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P303
|
|
27,803.80
|
₽ 68.25
|
₽ 1,897,650.00
|
|
EX
|
P303
|
Hand Soil Excavation (cum)
|
455.80
|
₽ 3,557.81
|
₽ 1,621,650.00
|
|
EX
|
P303
|
Mechanised Soil Excavation (cum)
|
27,348.00
|
₽ 10.09
|
₽ 276,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EX
|
P304
|
|
30,390.20
|
₽ 68.21
|
₽ 2,073,000.00
|
|
EX
|
P304
|
Hand Soil Excavation (cum)
|
498.20
|
₽ 3,558.81
|
₽ 1,773,000.00
|
|
EX
|
P304
|
Mechanised Soil Excavation (cum)
|
29,892.00
|
₽ 10.04
|
₽ 300,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
|
|
6,095.00
|
₽ 129,283.35
|
₽ 787,982,000.00
|
|
PL
|
Benua Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Benua Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Benua Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Tihoretskiy Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Tihoretskiy Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Tihoretskiy Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Kurchatov Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Kurchatov Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Kurchatov Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Politekh Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Politekh Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Politekh Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Atom Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Atom Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Atom Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
RTK Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
RTK Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
RTK Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Akadem Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Akadem Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Akadem Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Nauki Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Nauki Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Nauki Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
CHapaev Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
CHapaev Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
CHapaev Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PL
|
Budenniy Tower
|
|
609.50
|
₽ 129,283.35
|
₽ 78,798,200.00
|
|
PL
|
Budenniy Tower
|
Pile caps of the foundation (pcs)
|
304.75
|
₽ 3,562.59
|
₽ 1,085,700.00
|
|
PL
|
Budenniy Tower
|
Piles of the foundation (pcs)
|
304.75
|
₽ 255,004.10
|
₽ 77,712,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
|
|
7,660,719.42
|
₽ 606.48
|
₽ 4,646,063,500.00
|
|
FD
|
Benua Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Benua Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Benua Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Benua Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Benua Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Benua Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Benua Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Benua Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Benua Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Benua Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Tihoretskiy Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Tihoretskiy Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Tihoretskiy Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Tihoretskiy Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Tihoretskiy Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Tihoretskiy Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Tihoretskiy Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Tihoretskiy Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Tihoretskiy Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Tihoretskiy Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Kurchatov Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Kurchatov Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Kurchatov Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Kurchatov Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Kurchatov Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Kurchatov Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Kurchatov Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Kurchatov Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Kurchatov Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Kurchatov Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Politekh Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Politekh Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Politekh Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Politekh Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Politekh Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Politekh Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Politekh Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Politekh Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Politekh Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Politekh Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Atom Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Atom Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Atom Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Atom Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Atom Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Atom Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Atom Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Atom Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Atom Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Atom Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
RTK Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
RTK Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
RTK Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
RTK Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
RTK Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
RTK Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
RTK Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
RTK Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
RTK Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
RTK Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P101
|
|
114,164.12
|
₽ 615.33
|
₽ 70,248,200.00
|
|
FD
|
P101
|
Concrete of the foundation (cum)
|
593.60
|
₽ 6,950.64
|
₽ 4,125,900.00
|
|
FD
|
P101
|
Formwork of the foundation (sqm)
|
148.40
|
₽ 1,441.71
|
₽ 213,950.00
|
|
FD
|
P101
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,968.00
|
₽ 219.17
|
₽ 650,500.00
|
|
FD
|
P101
|
Gravel fill of the foundation (cum)
|
222.60
|
₽ 1,631.40
|
₽ 363,150.00
|
|
FD
|
P101
|
Logicbase V-SL of the foundation (sqm)
|
1,484.00
|
₽ 1,869.17
|
₽ 2,773,850.00
|
|
FD
|
P101
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,484.00
|
₽ 149.17
|
₽ 221,370.00
|
|
FD
|
P101
|
Rebar of the foundation (kg)
|
106,848.00
|
₽ 574.01
|
₽ 61,331,700.00
|
|
FD
|
P101
|
Sand fill of the foundation (cum)
|
222.60
|
₽ 1,131.40
|
₽ 251,850.00
|
|
FD
|
P101
|
Screed of the foundation (cum)
|
192.92
|
₽ 1,637.62
|
₽ 315,930.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P102
|
|
147,782.53
|
₽ 615.33
|
₽ 90,934,675.00
|
|
FD
|
P102
|
Concrete of the foundation (cum)
|
768.40
|
₽ 6,950.29
|
₽ 5,340,600.00
|
|
FD
|
P102
|
Formwork of the foundation (sqm)
|
192.10
|
₽ 1,450.94
|
₽ 278,725.00
|
|
FD
|
P102
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,842.00
|
₽ 220.09
|
₽ 845,600.00
|
|
FD
|
P102
|
Gravel fill of the foundation (cum)
|
288.15
|
₽ 1,620.25
|
₽ 466,875.00
|
|
FD
|
P102
|
Logicbase V-SL of the foundation (sqm)
|
1,921.00
|
₽ 1,870.09
|
₽ 3,592,450.00
|
|
FD
|
P102
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,921.00
|
₽ 150.09
|
₽ 288,330.00
|
|
FD
|
P102
|
Rebar of the foundation (kg)
|
138,312.00
|
₽ 574.01
|
₽ 79,392,750.00
|
|
FD
|
P102
|
Sand fill of the foundation (cum)
|
288.15
|
₽ 1,120.25
|
₽ 322,800.00
|
|
FD
|
P102
|
Screed of the foundation (cum)
|
249.73
|
₽ 1,627.94
|
₽ 406,545.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P103
|
|
176,092.77
|
₽ 615.26
|
₽ 108,343,275.00
|
|
FD
|
P103
|
Concrete of the foundation (cum)
|
915.60
|
₽ 6,950.85
|
₽ 6,364,200.00
|
|
FD
|
P103
|
Formwork of the foundation (sqm)
|
228.90
|
₽ 1,436.76
|
₽ 328,875.00
|
|
FD
|
P103
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,578.00
|
₽ 218.68
|
₽ 1,001,100.00
|
|
FD
|
P103
|
Gravel fill of the foundation (cum)
|
343.35
|
₽ 1,624.95
|
₽ 557,925.00
|
|
FD
|
P103
|
Logicbase V-SL of the foundation (sqm)
|
2,289.00
|
₽ 1,868.68
|
₽ 4,277,400.00
|
|
FD
|
P103
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,289.00
|
₽ 148.68
|
₽ 340,320.00
|
|
FD
|
P103
|
Rebar of the foundation (kg)
|
164,808.00
|
₽ 574.02
|
₽ 94,602,450.00
|
|
FD
|
P103
|
Sand fill of the foundation (cum)
|
343.35
|
₽ 1,124.95
|
₽ 386,250.00
|
|
FD
|
P103
|
Screed of the foundation (cum)
|
297.57
|
₽ 1,629.05
|
₽ 484,755.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P104
|
|
140,320.32
|
₽ 615.35
|
₽ 86,346,450.00
|
|
FD
|
P104
|
Concrete of the foundation (cum)
|
729.60
|
₽ 6,950.86
|
₽ 5,071,350.00
|
|
FD
|
P104
|
Formwork of the foundation (sqm)
|
182.40
|
₽ 1,449.84
|
₽ 264,450.00
|
|
FD
|
P104
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,648.00
|
₽ 219.98
|
₽ 802,500.00
|
|
FD
|
P104
|
Gravel fill of the foundation (cum)
|
273.60
|
₽ 1,623.36
|
₽ 444,150.00
|
|
FD
|
P104
|
Logicbase V-SL of the foundation (sqm)
|
1,824.00
|
₽ 1,869.98
|
₽ 3,410,850.00
|
|
FD
|
P104
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,824.00
|
₽ 149.98
|
₽ 273,570.00
|
|
FD
|
P104
|
Rebar of the foundation (kg)
|
131,328.00
|
₽ 574.02
|
₽ 75,385,500.00
|
|
FD
|
P104
|
Sand fill of the foundation (cum)
|
273.60
|
₽ 1,123.36
|
₽ 307,350.00
|
|
FD
|
P104
|
Screed of the foundation (cum)
|
237.12
|
₽ 1,630.95
|
₽ 386,730.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P105
|
|
114,164.12
|
₽ 615.33
|
₽ 70,248,200.00
|
|
FD
|
P105
|
Concrete of the foundation (cum)
|
593.60
|
₽ 6,950.64
|
₽ 4,125,900.00
|
|
FD
|
P105
|
Formwork of the foundation (sqm)
|
148.40
|
₽ 1,441.71
|
₽ 213,950.00
|
|
FD
|
P105
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,968.00
|
₽ 219.17
|
₽ 650,500.00
|
|
FD
|
P105
|
Gravel fill of the foundation (cum)
|
222.60
|
₽ 1,631.40
|
₽ 363,150.00
|
|
FD
|
P105
|
Logicbase V-SL of the foundation (sqm)
|
1,484.00
|
₽ 1,869.17
|
₽ 2,773,850.00
|
|
FD
|
P105
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,484.00
|
₽ 149.17
|
₽ 221,370.00
|
|
FD
|
P105
|
Rebar of the foundation (kg)
|
106,848.00
|
₽ 574.01
|
₽ 61,331,700.00
|
|
FD
|
P105
|
Sand fill of the foundation (cum)
|
222.60
|
₽ 1,131.40
|
₽ 251,850.00
|
|
FD
|
P105
|
Screed of the foundation (cum)
|
192.92
|
₽ 1,637.62
|
₽ 315,930.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P106
|
|
130,473.28
|
₽ 615.28
|
₽ 80,277,400.00
|
|
FD
|
P106
|
Concrete of the foundation (cum)
|
678.40
|
₽ 6,951.43
|
₽ 4,715,850.00
|
|
FD
|
P106
|
Formwork of the foundation (sqm)
|
169.60
|
₽ 1,437.79
|
₽ 243,850.00
|
|
FD
|
P106
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,392.00
|
₽ 218.78
|
₽ 742,100.00
|
|
FD
|
P106
|
Gravel fill of the foundation (cum)
|
254.40
|
₽ 1,625.59
|
₽ 413,550.00
|
|
FD
|
P106
|
Logicbase V-SL of the foundation (sqm)
|
1,696.00
|
₽ 1,868.78
|
₽ 3,169,450.00
|
|
FD
|
P106
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,696.00
|
₽ 148.78
|
₽ 252,330.00
|
|
FD
|
P106
|
Rebar of the foundation (kg)
|
122,112.00
|
₽ 574.01
|
₽ 70,093,950.00
|
|
FD
|
P106
|
Sand fill of the foundation (cum)
|
254.40
|
₽ 1,125.59
|
₽ 286,350.00
|
|
FD
|
P106
|
Screed of the foundation (cum)
|
220.48
|
₽ 1,632.67
|
₽ 359,970.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P107
|
|
122,472.56
|
₽ 615.28
|
₽ 75,354,950.00
|
|
FD
|
P107
|
Concrete of the foundation (cum)
|
636.80
|
₽ 6,949.04
|
₽ 4,425,150.00
|
|
FD
|
P107
|
Formwork of the foundation (sqm)
|
159.20
|
₽ 1,440.95
|
₽ 229,400.00
|
|
FD
|
P107
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,184.00
|
₽ 219.10
|
₽ 697,600.00
|
|
FD
|
P107
|
Gravel fill of the foundation (cum)
|
238.80
|
₽ 1,626.26
|
₽ 388,350.00
|
|
FD
|
P107
|
Logicbase V-SL of the foundation (sqm)
|
1,592.00
|
₽ 1,869.10
|
₽ 2,975,600.00
|
|
FD
|
P107
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,592.00
|
₽ 149.10
|
₽ 237,360.00
|
|
FD
|
P107
|
Rebar of the foundation (kg)
|
114,624.00
|
₽ 574.00
|
₽ 65,794,650.00
|
|
FD
|
P107
|
Sand fill of the foundation (cum)
|
238.80
|
₽ 1,126.26
|
₽ 268,950.00
|
|
FD
|
P107
|
Screed of the foundation (cum)
|
206.96
|
₽ 1,632.63
|
₽ 337,890.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P108
|
|
150,705.87
|
₽ 615.25
|
₽ 92,722,425.00
|
|
FD
|
P108
|
Concrete of the foundation (cum)
|
783.60
|
₽ 6,949.27
|
₽ 5,445,450.00
|
|
FD
|
P108
|
Formwork of the foundation (sqm)
|
195.90
|
₽ 1,441.42
|
₽ 282,375.00
|
|
FD
|
P108
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,918.00
|
₽ 219.14
|
₽ 858,600.00
|
|
FD
|
P108
|
Gravel fill of the foundation (cum)
|
293.85
|
₽ 1,620.98
|
₽ 476,325.00
|
|
FD
|
P108
|
Logicbase V-SL of the foundation (sqm)
|
1,959.00
|
₽ 1,869.14
|
₽ 3,661,650.00
|
|
FD
|
P108
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,959.00
|
₽ 149.14
|
₽ 292,170.00
|
|
FD
|
P108
|
Rebar of the foundation (kg)
|
141,048.00
|
₽ 574.01
|
₽ 80,962,500.00
|
|
FD
|
P108
|
Sand fill of the foundation (cum)
|
293.85
|
₽ 1,120.98
|
₽ 329,400.00
|
|
FD
|
P108
|
Screed of the foundation (cum)
|
254.67
|
₽ 1,625.46
|
₽ 413,955.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P109
|
|
146,782.44
|
₽ 615.34
|
₽ 90,321,750.00
|
|
FD
|
P109
|
Concrete of the foundation (cum)
|
763.20
|
₽ 6,952.04
|
₽ 5,305,800.00
|
|
FD
|
P109
|
Formwork of the foundation (sqm)
|
190.80
|
₽ 1,449.69
|
₽ 276,600.00
|
|
FD
|
P109
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,816.00
|
₽ 219.97
|
₽ 839,400.00
|
|
FD
|
P109
|
Gravel fill of the foundation (cum)
|
286.20
|
₽ 1,621.07
|
₽ 463,950.00
|
|
FD
|
P109
|
Logicbase V-SL of the foundation (sqm)
|
1,908.00
|
₽ 1,869.97
|
₽ 3,567,900.00
|
|
FD
|
P109
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,908.00
|
₽ 149.97
|
₽ 286,140.00
|
|
FD
|
P109
|
Rebar of the foundation (kg)
|
137,376.00
|
₽ 574.02
|
₽ 78,857,100.00
|
|
FD
|
P109
|
Sand fill of the foundation (cum)
|
286.20
|
₽ 1,121.07
|
₽ 320,850.00
|
|
FD
|
P109
|
Screed of the foundation (cum)
|
248.04
|
₽ 1,628.81
|
₽ 404,010.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P110
|
|
162,630.02
|
₽ 615.36
|
₽ 100,075,700.00
|
|
FD
|
P110
|
Concrete of the foundation (cum)
|
845.60
|
₽ 6,949.74
|
₽ 5,876,700.00
|
|
FD
|
P110
|
Formwork of the foundation (sqm)
|
211.40
|
₽ 1,449.15
|
₽ 306,350.00
|
|
FD
|
P110
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,228.00
|
₽ 219.91
|
₽ 929,800.00
|
|
FD
|
P110
|
Gravel fill of the foundation (cum)
|
317.10
|
₽ 1,626.77
|
₽ 515,850.00
|
|
FD
|
P110
|
Logicbase V-SL of the foundation (sqm)
|
2,114.00
|
₽ 1,869.91
|
₽ 3,953,000.00
|
|
FD
|
P110
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,114.00
|
₽ 149.91
|
₽ 316,920.00
|
|
FD
|
P110
|
Rebar of the foundation (kg)
|
152,208.00
|
₽ 574.02
|
₽ 87,370,050.00
|
|
FD
|
P110
|
Sand fill of the foundation (cum)
|
317.10
|
₽ 1,126.77
|
₽ 357,300.00
|
|
FD
|
P110
|
Screed of the foundation (cum)
|
274.82
|
₽ 1,636.45
|
₽ 449,730.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P111
|
|
142,551.29
|
₽ 615.30
|
₽ 87,712,025.00
|
|
FD
|
P111
|
Concrete of the foundation (cum)
|
741.20
|
₽ 6,950.76
|
₽ 5,151,900.00
|
|
FD
|
P111
|
Formwork of the foundation (sqm)
|
185.30
|
₽ 1,445.63
|
₽ 267,875.00
|
|
FD
|
P111
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
3,706.00
|
₽ 219.56
|
₽ 813,700.00
|
|
FD
|
P111
|
Gravel fill of the foundation (cum)
|
277.95
|
₽ 1,621.42
|
₽ 450,675.00
|
|
FD
|
P111
|
Logicbase V-SL of the foundation (sqm)
|
1,853.00
|
₽ 1,869.56
|
₽ 3,464,300.00
|
|
FD
|
P111
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,853.00
|
₽ 149.56
|
₽ 277,140.00
|
|
FD
|
P111
|
Rebar of the foundation (kg)
|
133,416.00
|
₽ 574.01
|
₽ 76,582,350.00
|
|
FD
|
P111
|
Sand fill of the foundation (cum)
|
277.95
|
₽ 1,121.42
|
₽ 311,700.00
|
|
FD
|
P111
|
Screed of the foundation (cum)
|
240.89
|
₽ 1,628.90
|
₽ 392,385.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Akadem Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Akadem Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Akadem Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Akadem Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Akadem Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Akadem Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Akadem Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Akadem Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Akadem Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Akadem Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Nauki Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Nauki Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Nauki Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Nauki Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Nauki Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Nauki Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Nauki Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Nauki Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Nauki Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Nauki Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P201
|
|
183,478.05
|
₽ 615.25
|
₽ 112,885,575.00
|
|
FD
|
P201
|
Concrete of the foundation (cum)
|
954.00
|
₽ 6,950.79
|
₽ 6,631,050.00
|
|
FD
|
P201
|
Formwork of the foundation (sqm)
|
238.50
|
₽ 1,438.68
|
₽ 343,125.00
|
|
FD
|
P201
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,770.00
|
₽ 218.87
|
₽ 1,044,000.00
|
|
FD
|
P201
|
Gravel fill of the foundation (cum)
|
357.75
|
₽ 1,622.43
|
₽ 580,425.00
|
|
FD
|
P201
|
Logicbase V-SL of the foundation (sqm)
|
2,385.00
|
₽ 1,868.87
|
₽ 4,457,250.00
|
|
FD
|
P201
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,385.00
|
₽ 148.87
|
₽ 355,050.00
|
|
FD
|
P201
|
Rebar of the foundation (kg)
|
171,720.00
|
₽ 574.00
|
₽ 98,567,850.00
|
|
FD
|
P201
|
Sand fill of the foundation (cum)
|
357.75
|
₽ 1,122.43
|
₽ 401,550.00
|
|
FD
|
P201
|
Screed of the foundation (cum)
|
310.05
|
₽ 1,629.66
|
₽ 505,275.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P202
|
|
183,478.05
|
₽ 615.25
|
₽ 112,885,575.00
|
|
FD
|
P202
|
Concrete of the foundation (cum)
|
954.00
|
₽ 6,950.79
|
₽ 6,631,050.00
|
|
FD
|
P202
|
Formwork of the foundation (sqm)
|
238.50
|
₽ 1,438.68
|
₽ 343,125.00
|
|
FD
|
P202
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,770.00
|
₽ 218.87
|
₽ 1,044,000.00
|
|
FD
|
P202
|
Gravel fill of the foundation (cum)
|
357.75
|
₽ 1,622.43
|
₽ 580,425.00
|
|
FD
|
P202
|
Logicbase V-SL of the foundation (sqm)
|
2,385.00
|
₽ 1,868.87
|
₽ 4,457,250.00
|
|
FD
|
P202
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,385.00
|
₽ 148.87
|
₽ 355,050.00
|
|
FD
|
P202
|
Rebar of the foundation (kg)
|
171,720.00
|
₽ 574.00
|
₽ 98,567,850.00
|
|
FD
|
P202
|
Sand fill of the foundation (cum)
|
357.75
|
₽ 1,122.43
|
₽ 401,550.00
|
|
FD
|
P202
|
Screed of the foundation (cum)
|
310.05
|
₽ 1,629.66
|
₽ 505,275.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P203
|
|
175,323.47
|
₽ 615.26
|
₽ 107,869,625.00
|
|
FD
|
P203
|
Concrete of the foundation (cum)
|
911.60
|
₽ 6,948.94
|
₽ 6,334,650.00
|
|
FD
|
P203
|
Formwork of the foundation (sqm)
|
227.90
|
₽ 1,438.02
|
₽ 327,725.00
|
|
FD
|
P203
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,558.00
|
₽ 218.80
|
₽ 997,300.00
|
|
FD
|
P203
|
Gravel fill of the foundation (cum)
|
341.85
|
₽ 1,625.49
|
₽ 555,675.00
|
|
FD
|
P203
|
Logicbase V-SL of the foundation (sqm)
|
2,279.00
|
₽ 1,868.80
|
₽ 4,259,000.00
|
|
FD
|
P203
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,279.00
|
₽ 148.80
|
₽ 339,120.00
|
|
FD
|
P203
|
Rebar of the foundation (kg)
|
164,088.00
|
₽ 574.01
|
₽ 94,188,600.00
|
|
FD
|
P203
|
Sand fill of the foundation (cum)
|
341.85
|
₽ 1,125.49
|
₽ 384,750.00
|
|
FD
|
P203
|
Screed of the foundation (cum)
|
296.27
|
₽ 1,629.61
|
₽ 482,805.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P204
|
|
191,632.63
|
₽ 615.26
|
₽ 117,903,325.00
|
|
FD
|
P204
|
Concrete of the foundation (cum)
|
996.40
|
₽ 6,949.62
|
₽ 6,924,600.00
|
|
FD
|
P204
|
Formwork of the foundation (sqm)
|
249.10
|
₽ 1,439.28
|
₽ 358,525.00
|
|
FD
|
P204
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,982.00
|
₽ 218.93
|
₽ 1,090,700.00
|
|
FD
|
P204
|
Gravel fill of the foundation (cum)
|
373.65
|
₽ 1,622.04
|
₽ 606,075.00
|
|
FD
|
P204
|
Logicbase V-SL of the foundation (sqm)
|
2,491.00
|
₽ 1,868.93
|
₽ 4,655,500.00
|
|
FD
|
P204
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,491.00
|
₽ 148.93
|
₽ 370,980.00
|
|
FD
|
P204
|
Rebar of the foundation (kg)
|
179,352.00
|
₽ 574.02
|
₽ 102,950,850.00
|
|
FD
|
P204
|
Sand fill of the foundation (cum)
|
373.65
|
₽ 1,122.04
|
₽ 419,250.00
|
|
FD
|
P204
|
Screed of the foundation (cum)
|
323.83
|
₽ 1,626.92
|
₽ 526,845.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
CHapaev Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
CHapaev Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
CHapaev Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
CHapaev Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
CHapaev Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
CHapaev Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
CHapaev Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
CHapaev Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
CHapaev Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
CHapaev Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
Budenniy Tower
|
|
464,475.57
|
₽ 600.76
|
₽ 279,039,025.00
|
|
FD
|
Budenniy Tower
|
Concrete of the foundation (cum)
|
1,828.50
|
₽ 6,949.22
|
₽ 12,706,650.00
|
|
FD
|
Budenniy Tower
|
Formwork of the foundation (sqm)
|
121.90
|
₽ 1,454.68
|
₽ 177,325.00
|
|
FD
|
Budenniy Tower
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
2,438.00
|
₽ 220.47
|
₽ 537,500.00
|
|
FD
|
Budenniy Tower
|
Gravel fill of the foundation (cum)
|
182.85
|
₽ 1,624.69
|
₽ 297,075.00
|
|
FD
|
Budenniy Tower
|
Logicbase V-SL of the foundation (sqm)
|
1,219.00
|
₽ 1,870.47
|
₽ 2,280,100.00
|
|
FD
|
Budenniy Tower
|
Polyethylene 200 mkm of the foundation (sqm)
|
1,219.00
|
₽ 150.47
|
₽ 183,420.00
|
|
FD
|
Budenniy Tower
|
Rebar of the foundation (kg)
|
457,125.00
|
₽ 574.00
|
₽ 262,389,750.00
|
|
FD
|
Budenniy Tower
|
Sand fill of the foundation (cum)
|
182.85
|
₽ 1,124.69
|
₽ 205,650.00
|
|
FD
|
Budenniy Tower
|
Screed of the foundation (cum)
|
158.47
|
₽ 1,650.50
|
₽ 261,555.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P301
|
|
183,478.05
|
₽ 615.25
|
₽ 112,885,575.00
|
|
FD
|
P301
|
Concrete of the foundation (cum)
|
954.00
|
₽ 6,950.79
|
₽ 6,631,050.00
|
|
FD
|
P301
|
Formwork of the foundation (sqm)
|
238.50
|
₽ 1,438.68
|
₽ 343,125.00
|
|
FD
|
P301
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,770.00
|
₽ 218.87
|
₽ 1,044,000.00
|
|
FD
|
P301
|
Gravel fill of the foundation (cum)
|
357.75
|
₽ 1,622.43
|
₽ 580,425.00
|
|
FD
|
P301
|
Logicbase V-SL of the foundation (sqm)
|
2,385.00
|
₽ 1,868.87
|
₽ 4,457,250.00
|
|
FD
|
P301
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,385.00
|
₽ 148.87
|
₽ 355,050.00
|
|
FD
|
P301
|
Rebar of the foundation (kg)
|
171,720.00
|
₽ 574.00
|
₽ 98,567,850.00
|
|
FD
|
P301
|
Sand fill of the foundation (cum)
|
357.75
|
₽ 1,122.43
|
₽ 401,550.00
|
|
FD
|
P301
|
Screed of the foundation (cum)
|
310.05
|
₽ 1,629.66
|
₽ 505,275.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P302
|
|
183,478.05
|
₽ 615.25
|
₽ 112,885,575.00
|
|
FD
|
P302
|
Concrete of the foundation (cum)
|
954.00
|
₽ 6,950.79
|
₽ 6,631,050.00
|
|
FD
|
P302
|
Formwork of the foundation (sqm)
|
238.50
|
₽ 1,438.68
|
₽ 343,125.00
|
|
FD
|
P302
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,770.00
|
₽ 218.87
|
₽ 1,044,000.00
|
|
FD
|
P302
|
Gravel fill of the foundation (cum)
|
357.75
|
₽ 1,622.43
|
₽ 580,425.00
|
|
FD
|
P302
|
Logicbase V-SL of the foundation (sqm)
|
2,385.00
|
₽ 1,868.87
|
₽ 4,457,250.00
|
|
FD
|
P302
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,385.00
|
₽ 148.87
|
₽ 355,050.00
|
|
FD
|
P302
|
Rebar of the foundation (kg)
|
171,720.00
|
₽ 574.00
|
₽ 98,567,850.00
|
|
FD
|
P302
|
Sand fill of the foundation (cum)
|
357.75
|
₽ 1,122.43
|
₽ 401,550.00
|
|
FD
|
P302
|
Screed of the foundation (cum)
|
310.05
|
₽ 1,629.66
|
₽ 505,275.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P303
|
|
175,323.47
|
₽ 615.26
|
₽ 107,869,625.00
|
|
FD
|
P303
|
Concrete of the foundation (cum)
|
911.60
|
₽ 6,948.94
|
₽ 6,334,650.00
|
|
FD
|
P303
|
Formwork of the foundation (sqm)
|
227.90
|
₽ 1,438.02
|
₽ 327,725.00
|
|
FD
|
P303
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,558.00
|
₽ 218.80
|
₽ 997,300.00
|
|
FD
|
P303
|
Gravel fill of the foundation (cum)
|
341.85
|
₽ 1,625.49
|
₽ 555,675.00
|
|
FD
|
P303
|
Logicbase V-SL of the foundation (sqm)
|
2,279.00
|
₽ 1,868.80
|
₽ 4,259,000.00
|
|
FD
|
P303
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,279.00
|
₽ 148.80
|
₽ 339,120.00
|
|
FD
|
P303
|
Rebar of the foundation (kg)
|
164,088.00
|
₽ 574.01
|
₽ 94,188,600.00
|
|
FD
|
P303
|
Sand fill of the foundation (cum)
|
341.85
|
₽ 1,125.49
|
₽ 384,750.00
|
|
FD
|
P303
|
Screed of the foundation (cum)
|
296.27
|
₽ 1,629.61
|
₽ 482,805.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FD
|
P304
|
|
191,632.63
|
₽ 615.26
|
₽ 117,903,325.00
|
|
FD
|
P304
|
Concrete of the foundation (cum)
|
996.40
|
₽ 6,949.62
|
₽ 6,924,600.00
|
|
FD
|
P304
|
Formwork of the foundation (sqm)
|
249.10
|
₽ 1,439.28
|
₽ 358,525.00
|
|
FD
|
P304
|
Geotextile (500 g/sqm) of the foundation (sqm)
|
4,982.00
|
₽ 218.93
|
₽ 1,090,700.00
|
|
FD
|
P304
|
Gravel fill of the foundation (cum)
|
373.65
|
₽ 1,622.04
|
₽ 606,075.00
|
|
FD
|
P304
|
Logicbase V-SL of the foundation (sqm)
|
2,491.00
|
₽ 1,868.93
|
₽ 4,655,500.00
|
|
FD
|
P304
|
Polyethylene 200 mkm of the foundation (sqm)
|
2,491.00
|
₽ 148.93
|
₽ 370,980.00
|
|
FD
|
P304
|
Rebar of the foundation (kg)
|
179,352.00
|
₽ 574.02
|
₽ 102,950,850.00
|
|
FD
|
P304
|
Sand fill of the foundation (cum)
|
373.65
|
₽ 1,122.04
|
₽ 419,250.00
|
|
FD
|
P304
|
Screed of the foundation (cum)
|
323.83
|
₽ 1,626.92
|
₽ 526,845.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
|
|
45,982,905.00
|
₽ 632.22
|
₽ 29,071,410,490.00
|
|
SR
|
Benua Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Benua Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Benua Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Benua Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Benua Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Benua Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Benua Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Tihoretskiy Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Tihoretskiy Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Tihoretskiy Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Tihoretskiy Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Tihoretskiy Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Tihoretskiy Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Tihoretskiy Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Kurchatov Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Kurchatov Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Kurchatov Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Kurchatov Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Kurchatov Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Kurchatov Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Kurchatov Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Politekh Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Politekh Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Politekh Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Politekh Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Politekh Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Politekh Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Politekh Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Atom Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Atom Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Atom Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Atom Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Atom Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Atom Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Atom Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
RTK Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
RTK Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
RTK Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
RTK Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
RTK Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
RTK Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
RTK Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P101
|
|
258,661.20
|
₽ 632.40
|
₽ 163,576,430.00
|
|
SR
|
P101
|
Concrete of the slabs (cum)
|
296.80
|
₽ 6,952.16
|
₽ 2,063,400.00
|
|
SR
|
P101
|
Concrete of the walls, columns (cum)
|
979.44
|
₽ 6,954.12
|
₽ 6,811,140.00
|
|
SR
|
P101
|
Formwork of the slabs (sqm)
|
1,484.00
|
₽ 1,436.15
|
₽ 2,131,250.00
|
|
SR
|
P101
|
Formwork of the walls, columns (sqm)
|
6,588.96
|
₽ 1,435.62
|
₽ 9,459,240.00
|
|
SR
|
P101
|
Rebar of the slabs (kg)
|
53,424.00
|
₽ 574.01
|
₽ 30,665,850.00
|
|
SR
|
P101
|
Rebar of the walls, columns (kg)
|
195,888.00
|
₽ 574.03
|
₽ 112,445,550.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P102
|
|
334,830.30
|
₽ 632.37
|
₽ 211,737,370.00
|
|
SR
|
P102
|
Concrete of the slabs (cum)
|
384.20
|
₽ 6,951.46
|
₽ 2,670,750.00
|
|
SR
|
P102
|
Concrete of the walls, columns (cum)
|
1,267.86
|
₽ 6,949.79
|
₽ 8,811,360.00
|
|
SR
|
P102
|
Formwork of the slabs (sqm)
|
1,921.00
|
₽ 1,436.34
|
₽ 2,759,200.00
|
|
SR
|
P102
|
Formwork of the walls, columns (sqm)
|
8,529.24
|
₽ 1,435.44
|
₽ 12,243,210.00
|
|
SR
|
P102
|
Rebar of the slabs (kg)
|
69,156.00
|
₽ 574.04
|
₽ 39,698,250.00
|
|
SR
|
P102
|
Rebar of the walls, columns (kg)
|
253,572.00
|
₽ 574.02
|
₽ 145,554,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P103
|
|
398,972.70
|
₽ 632.36
|
₽ 252,294,930.00
|
|
SR
|
P103
|
Concrete of the slabs (cum)
|
457.80
|
₽ 6,951.83
|
₽ 3,182,550.00
|
|
SR
|
P103
|
Concrete of the walls, columns (cum)
|
1,510.74
|
₽ 6,950.99
|
₽ 10,501,140.00
|
|
SR
|
P103
|
Formwork of the slabs (sqm)
|
2,289.00
|
₽ 1,435.12
|
₽ 3,285,000.00
|
|
SR
|
P103
|
Formwork of the walls, columns (sqm)
|
10,163.16
|
₽ 1,435.27
|
₽ 14,586,840.00
|
|
SR
|
P103
|
Rebar of the slabs (kg)
|
82,404.00
|
₽ 574.03
|
₽ 47,302,650.00
|
|
SR
|
P103
|
Rebar of the walls, columns (kg)
|
302,148.00
|
₽ 574.01
|
₽ 173,436,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P104
|
|
317,923.20
|
₽ 632.37
|
₽ 201,044,430.00
|
|
SR
|
P104
|
Concrete of the slabs (cum)
|
364.80
|
₽ 6,954.77
|
₽ 2,537,100.00
|
|
SR
|
P104
|
Concrete of the walls, columns (cum)
|
1,203.84
|
₽ 6,950.33
|
₽ 8,367,090.00
|
|
SR
|
P104
|
Formwork of the slabs (sqm)
|
1,824.00
|
₽ 1,435.94
|
₽ 2,619,150.00
|
|
SR
|
P104
|
Formwork of the walls, columns (sqm)
|
8,098.56
|
₽ 1,435.21
|
₽ 11,623,140.00
|
|
SR
|
P104
|
Rebar of the slabs (kg)
|
65,664.00
|
₽ 574.02
|
₽ 37,692,750.00
|
|
SR
|
P104
|
Rebar of the walls, columns (kg)
|
240,768.00
|
₽ 574.02
|
₽ 138,205,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P105
|
|
258,661.20
|
₽ 632.40
|
₽ 163,576,430.00
|
|
SR
|
P105
|
Concrete of the slabs (cum)
|
296.80
|
₽ 6,952.16
|
₽ 2,063,400.00
|
|
SR
|
P105
|
Concrete of the walls, columns (cum)
|
979.44
|
₽ 6,954.12
|
₽ 6,811,140.00
|
|
SR
|
P105
|
Formwork of the slabs (sqm)
|
1,484.00
|
₽ 1,436.15
|
₽ 2,131,250.00
|
|
SR
|
P105
|
Formwork of the walls, columns (sqm)
|
6,588.96
|
₽ 1,435.62
|
₽ 9,459,240.00
|
|
SR
|
P105
|
Rebar of the slabs (kg)
|
53,424.00
|
₽ 574.01
|
₽ 30,665,850.00
|
|
SR
|
P105
|
Rebar of the walls, columns (kg)
|
195,888.00
|
₽ 574.03
|
₽ 112,445,550.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P106
|
|
295,612.80
|
₽ 632.37
|
₽ 186,937,720.00
|
|
SR
|
P106
|
Concrete of the slabs (cum)
|
339.20
|
₽ 6,956.96
|
₽ 2,359,800.00
|
|
SR
|
P106
|
Concrete of the walls, columns (cum)
|
1,119.36
|
₽ 6,950.36
|
₽ 7,779,960.00
|
|
SR
|
P106
|
Formwork of the slabs (sqm)
|
1,696.00
|
₽ 1,435.67
|
₽ 2,434,900.00
|
|
SR
|
P106
|
Formwork of the walls, columns (sqm)
|
7,530.24
|
₽ 1,435.58
|
₽ 10,810,260.00
|
|
SR
|
P106
|
Rebar of the slabs (kg)
|
61,056.00
|
₽ 574.04
|
₽ 35,048,850.00
|
|
SR
|
P106
|
Rebar of the walls, columns (kg)
|
223,872.00
|
₽ 574.01
|
₽ 128,503,950.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P107
|
|
277,485.60
|
₽ 632.39
|
₽ 175,479,290.00
|
|
SR
|
P107
|
Concrete of the slabs (cum)
|
318.40
|
₽ 6,953.52
|
₽ 2,214,000.00
|
|
SR
|
P107
|
Concrete of the walls, columns (cum)
|
1,050.72
|
₽ 6,951.78
|
₽ 7,304,370.00
|
|
SR
|
P107
|
Formwork of the slabs (sqm)
|
1,592.00
|
₽ 1,436.43
|
₽ 2,286,800.00
|
|
SR
|
P107
|
Formwork of the walls, columns (sqm)
|
7,068.48
|
₽ 1,435.66
|
₽ 10,147,920.00
|
|
SR
|
P107
|
Rebar of the slabs (kg)
|
57,312.00
|
₽ 574.03
|
₽ 32,898,750.00
|
|
SR
|
P107
|
Rebar of the walls, columns (kg)
|
210,144.00
|
₽ 574.02
|
₽ 120,627,450.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P108
|
|
341,453.70
|
₽ 632.37
|
₽ 215,924,130.00
|
|
SR
|
P108
|
Concrete of the slabs (cum)
|
391.80
|
₽ 6,954.06
|
₽ 2,724,600.00
|
|
SR
|
P108
|
Concrete of the walls, columns (cum)
|
1,292.94
|
₽ 6,951.90
|
₽ 8,988,390.00
|
|
SR
|
P108
|
Formwork of the slabs (sqm)
|
1,959.00
|
₽ 1,435.15
|
₽ 2,811,450.00
|
|
SR
|
P108
|
Formwork of the walls, columns (sqm)
|
8,697.96
|
₽ 1,435.17
|
₽ 12,483,090.00
|
|
SR
|
P108
|
Rebar of the slabs (kg)
|
70,524.00
|
₽ 574.01
|
₽ 40,481,250.00
|
|
SR
|
P108
|
Rebar of the walls, columns (kg)
|
258,588.00
|
₽ 574.02
|
₽ 148,435,350.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P109
|
|
332,564.40
|
₽ 632.36
|
₽ 210,302,010.00
|
|
SR
|
P109
|
Concrete of the slabs (cum)
|
381.60
|
₽ 6,953.22
|
₽ 2,653,350.00
|
|
SR
|
P109
|
Concrete of the walls, columns (cum)
|
1,259.28
|
₽ 6,951.26
|
₽ 8,753,580.00
|
|
SR
|
P109
|
Formwork of the slabs (sqm)
|
1,908.00
|
₽ 1,435.30
|
₽ 2,738,550.00
|
|
SR
|
P109
|
Formwork of the walls, columns (sqm)
|
8,471.52
|
₽ 1,435.34
|
₽ 12,159,480.00
|
|
SR
|
P109
|
Rebar of the slabs (kg)
|
68,688.00
|
₽ 574.03
|
₽ 39,429,000.00
|
|
SR
|
P109
|
Rebar of the walls, columns (kg)
|
251,856.00
|
₽ 574.01
|
₽ 144,568,050.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P110
|
|
368,470.20
|
₽ 632.37
|
₽ 233,007,680.00
|
|
SR
|
P110
|
Concrete of the slabs (cum)
|
422.80
|
₽ 6,950.80
|
₽ 2,938,800.00
|
|
SR
|
P110
|
Concrete of the walls, columns (cum)
|
1,395.24
|
₽ 6,949.30
|
₽ 9,695,940.00
|
|
SR
|
P110
|
Formwork of the slabs (sqm)
|
2,114.00
|
₽ 1,435.81
|
₽ 3,035,300.00
|
|
SR
|
P110
|
Formwork of the walls, columns (sqm)
|
9,386.16
|
₽ 1,435.50
|
₽ 13,473,840.00
|
|
SR
|
P110
|
Rebar of the slabs (kg)
|
76,104.00
|
₽ 574.04
|
₽ 43,686,450.00
|
|
SR
|
P110
|
Rebar of the walls, columns (kg)
|
279,048.00
|
₽ 574.01
|
₽ 160,177,350.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P111
|
|
322,977.90
|
₽ 632.38
|
₽ 204,245,810.00
|
|
SR
|
P111
|
Concrete of the slabs (cum)
|
370.60
|
₽ 6,951.97
|
₽ 2,576,400.00
|
|
SR
|
P111
|
Concrete of the walls, columns (cum)
|
1,222.98
|
₽ 6,951.90
|
₽ 8,502,030.00
|
|
SR
|
P111
|
Formwork of the slabs (sqm)
|
1,853.00
|
₽ 1,436.08
|
₽ 2,661,050.00
|
|
SR
|
P111
|
Formwork of the walls, columns (sqm)
|
8,227.32
|
₽ 1,435.51
|
₽ 11,810,430.00
|
|
SR
|
P111
|
Rebar of the slabs (kg)
|
66,708.00
|
₽ 574.04
|
₽ 38,293,050.00
|
|
SR
|
P111
|
Rebar of the walls, columns (kg)
|
244,596.00
|
₽ 574.02
|
₽ 140,402,850.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Akadem Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Akadem Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Akadem Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Akadem Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Akadem Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Akadem Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Akadem Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Nauki Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Nauki Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Nauki Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Nauki Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Nauki Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Nauki Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Nauki Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P201
|
|
415,705.50
|
₽ 632.36
|
₽ 262,877,100.00
|
|
SR
|
P201
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
SR
|
P201
|
Concrete of the walls, columns (cum)
|
1,574.10
|
₽ 6,950.35
|
₽ 10,940,550.00
|
|
SR
|
P201
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
SR
|
P201
|
Formwork of the walls, columns (sqm)
|
10,589.40
|
₽ 1,435.34
|
₽ 15,199,350.00
|
|
SR
|
P201
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
SR
|
P201
|
Rebar of the walls, columns (kg)
|
314,820.00
|
₽ 574.01
|
₽ 180,711,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P202
|
|
415,705.50
|
₽ 632.36
|
₽ 262,877,100.00
|
|
SR
|
P202
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
SR
|
P202
|
Concrete of the walls, columns (cum)
|
1,574.10
|
₽ 6,950.35
|
₽ 10,940,550.00
|
|
SR
|
P202
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
SR
|
P202
|
Formwork of the walls, columns (sqm)
|
10,589.40
|
₽ 1,435.34
|
₽ 15,199,350.00
|
|
SR
|
P202
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
SR
|
P202
|
Rebar of the walls, columns (kg)
|
314,820.00
|
₽ 574.01
|
₽ 180,711,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P203
|
|
397,229.70
|
₽ 632.36
|
₽ 251,193,080.00
|
|
SR
|
P203
|
Concrete of the slabs (cum)
|
455.80
|
₽ 6,952.06
|
₽ 3,168,750.00
|
|
SR
|
P203
|
Concrete of the walls, columns (cum)
|
1,504.14
|
₽ 6,951.57
|
₽ 10,456,140.00
|
|
SR
|
P203
|
Formwork of the slabs (sqm)
|
2,279.00
|
₽ 1,435.13
|
₽ 3,270,650.00
|
|
SR
|
P203
|
Formwork of the walls, columns (sqm)
|
10,118.76
|
₽ 1,435.43
|
₽ 14,524,740.00
|
|
SR
|
P203
|
Rebar of the slabs (kg)
|
82,044.00
|
₽ 574.01
|
₽ 47,094,300.00
|
|
SR
|
P203
|
Rebar of the walls, columns (kg)
|
300,828.00
|
₽ 574.01
|
₽ 172,678,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P204
|
|
434,181.30
|
₽ 632.36
|
₽ 274,558,120.00
|
|
SR
|
P204
|
Concrete of the slabs (cum)
|
498.20
|
₽ 6,949.62
|
₽ 3,462,300.00
|
|
SR
|
P204
|
Concrete of the walls, columns (cum)
|
1,644.06
|
₽ 6,949.78
|
₽ 11,425,860.00
|
|
SR
|
P204
|
Formwork of the slabs (sqm)
|
2,491.00
|
₽ 1,436.03
|
₽ 3,577,150.00
|
|
SR
|
P204
|
Formwork of the walls, columns (sqm)
|
11,060.04
|
₽ 1,435.42
|
₽ 15,875,760.00
|
|
SR
|
P204
|
Rebar of the slabs (kg)
|
89,676.00
|
₽ 574.04
|
₽ 51,477,300.00
|
|
SR
|
P204
|
Rebar of the walls, columns (kg)
|
328,812.00
|
₽ 574.01
|
₽ 188,739,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
CHapaev Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
CHapaev Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
CHapaev Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
CHapaev Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
CHapaev Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
CHapaev Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
CHapaev Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
Budenniy Tower
|
|
3,914,964.78
|
₽ 632.20
|
₽ 2,475,027,346.00
|
|
SR
|
Budenniy Tower
|
Concrete of the slabs (cum)
|
8,289.20
|
₽ 6,957.34
|
₽ 57,670,800.00
|
|
SR
|
Budenniy Tower
|
Concrete of the walls, columns (cum)
|
11,424.47
|
₽ 6,951.79
|
₽ 79,420,458.00
|
|
SR
|
Budenniy Tower
|
Formwork of the slabs (sqm)
|
41,446.00
|
₽ 1,435.23
|
₽ 59,484,700.00
|
|
SR
|
Budenniy Tower
|
Formwork of the walls, columns (sqm)
|
76,855.51
|
₽ 1,435.68
|
₽ 110,339,628.00
|
|
SR
|
Budenniy Tower
|
Rebar of the slabs (kg)
|
1,492,056.00
|
₽ 574.05
|
₽ 856,514,400.00
|
|
SR
|
Budenniy Tower
|
Rebar of the walls, columns (kg)
|
2,284,893.60
|
₽ 574.03
|
₽ 1,311,597,360.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P301
|
|
415,705.50
|
₽ 632.36
|
₽ 262,877,100.00
|
|
SR
|
P301
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
SR
|
P301
|
Concrete of the walls, columns (cum)
|
1,574.10
|
₽ 6,950.35
|
₽ 10,940,550.00
|
|
SR
|
P301
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
SR
|
P301
|
Formwork of the walls, columns (sqm)
|
10,589.40
|
₽ 1,435.34
|
₽ 15,199,350.00
|
|
SR
|
P301
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
SR
|
P301
|
Rebar of the walls, columns (kg)
|
314,820.00
|
₽ 574.01
|
₽ 180,711,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P302
|
|
415,705.50
|
₽ 632.36
|
₽ 262,877,100.00
|
|
SR
|
P302
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
SR
|
P302
|
Concrete of the walls, columns (cum)
|
1,574.10
|
₽ 6,950.35
|
₽ 10,940,550.00
|
|
SR
|
P302
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
SR
|
P302
|
Formwork of the walls, columns (sqm)
|
10,589.40
|
₽ 1,435.34
|
₽ 15,199,350.00
|
|
SR
|
P302
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
SR
|
P302
|
Rebar of the walls, columns (kg)
|
314,820.00
|
₽ 574.01
|
₽ 180,711,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P303
|
|
397,229.70
|
₽ 632.36
|
₽ 251,193,080.00
|
|
SR
|
P303
|
Concrete of the slabs (cum)
|
455.80
|
₽ 6,952.06
|
₽ 3,168,750.00
|
|
SR
|
P303
|
Concrete of the walls, columns (cum)
|
1,504.14
|
₽ 6,951.57
|
₽ 10,456,140.00
|
|
SR
|
P303
|
Formwork of the slabs (sqm)
|
2,279.00
|
₽ 1,435.13
|
₽ 3,270,650.00
|
|
SR
|
P303
|
Formwork of the walls, columns (sqm)
|
10,118.76
|
₽ 1,435.43
|
₽ 14,524,740.00
|
|
SR
|
P303
|
Rebar of the slabs (kg)
|
82,044.00
|
₽ 574.01
|
₽ 47,094,300.00
|
|
SR
|
P303
|
Rebar of the walls, columns (kg)
|
300,828.00
|
₽ 574.01
|
₽ 172,678,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
SR
|
P304
|
|
434,181.30
|
₽ 632.36
|
₽ 274,558,120.00
|
|
SR
|
P304
|
Concrete of the slabs (cum)
|
498.20
|
₽ 6,949.62
|
₽ 3,462,300.00
|
|
SR
|
P304
|
Concrete of the walls, columns (cum)
|
1,644.06
|
₽ 6,949.78
|
₽ 11,425,860.00
|
|
SR
|
P304
|
Formwork of the slabs (sqm)
|
2,491.00
|
₽ 1,436.03
|
₽ 3,577,150.00
|
|
SR
|
P304
|
Formwork of the walls, columns (sqm)
|
11,060.04
|
₽ 1,435.42
|
₽ 15,875,760.00
|
|
SR
|
P304
|
Rebar of the slabs (kg)
|
89,676.00
|
₽ 574.04
|
₽ 51,477,300.00
|
|
SR
|
P304
|
Rebar of the walls, columns (kg)
|
328,812.00
|
₽ 574.01
|
₽ 188,739,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
|
|
37,745.22
|
₽ 1,549.98
|
₽ 58,504,210.40
|
|
IS
|
Benua Tower
|
|
1,000.92
|
₽ 1,547.36
|
₽ 1,548,784.40
|
|
IS
|
Benua Tower
|
Backfiling (cum)
|
9.12
|
₽ 328.95
|
₽ 3,000.00
|
|
IS
|
Benua Tower
|
CARBON PROF 300 of the basement (cum)
|
22.80
|
₽ 1,855.89
|
₽ 42,314.40
|
|
IS
|
Benua Tower
|
PLANTER Geo of the basement (sqm)
|
228.00
|
₽ 1,605.17
|
₽ 365,978.00
|
|
IS
|
Benua Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
57.00
|
₽ 1,466.00
|
₽ 83,562.00
|
|
IS
|
Benua Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
228.00
|
₽ 1,401.50
|
₽ 319,542.00
|
|
IS
|
Benua Tower
|
Техноэласт ЭПП of the basement (sqm)
|
456.00
|
₽ 1,610.50
|
₽ 734,388.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Tihoretskiy Tower
|
|
1,000.92
|
₽ 1,547.36
|
₽ 1,548,784.40
|
|
IS
|
Tihoretskiy Tower
|
Backfiling (cum)
|
9.12
|
₽ 328.95
|
₽ 3,000.00
|
|
IS
|
Tihoretskiy Tower
|
CARBON PROF 300 of the basement (cum)
|
22.80
|
₽ 1,855.89
|
₽ 42,314.40
|
|
IS
|
Tihoretskiy Tower
|
PLANTER Geo of the basement (sqm)
|
228.00
|
₽ 1,605.17
|
₽ 365,978.00
|
|
IS
|
Tihoretskiy Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
57.00
|
₽ 1,466.00
|
₽ 83,562.00
|
|
IS
|
Tihoretskiy Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
228.00
|
₽ 1,401.50
|
₽ 319,542.00
|
|
IS
|
Tihoretskiy Tower
|
Техноэласт ЭПП of the basement (sqm)
|
456.00
|
₽ 1,610.50
|
₽ 734,388.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Kurchatov Tower
|
|
698.01
|
₽ 1,547.16
|
₽ 1,079,933.20
|
|
IS
|
Kurchatov Tower
|
Backfiling (cum)
|
6.36
|
₽ 471.70
|
₽ 3,000.00
|
|
IS
|
Kurchatov Tower
|
CARBON PROF 300 of the basement (cum)
|
15.90
|
₽ 1,837.15
|
₽ 29,210.70
|
|
IS
|
Kurchatov Tower
|
PLANTER Geo of the basement (sqm)
|
159.00
|
₽ 1,604.46
|
₽ 255,109.00
|
|
IS
|
Kurchatov Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
39.75
|
₽ 1,458.45
|
₽ 57,973.50
|
|
IS
|
Kurchatov Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
159.00
|
₽ 1,400.79
|
₽ 222,726.00
|
|
IS
|
Kurchatov Tower
|
Техноэласт ЭПП of the basement (sqm)
|
318.00
|
₽ 1,609.79
|
₽ 511,914.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Politekh Tower
|
|
1,106.28
|
₽ 1,551.07
|
₽ 1,715,919.60
|
|
IS
|
Politekh Tower
|
Backfiling (cum)
|
10.08
|
₽ 297.62
|
₽ 3,000.00
|
|
IS
|
Politekh Tower
|
CARBON PROF 300 of the basement (cum)
|
25.20
|
₽ 1,840.86
|
₽ 46,389.60
|
|
IS
|
Politekh Tower
|
PLANTER Geo of the basement (sqm)
|
252.00
|
₽ 1,611.71
|
₽ 406,152.00
|
|
IS
|
Politekh Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
63.00
|
₽ 1,482.67
|
₽ 93,408.00
|
|
IS
|
Politekh Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
252.00
|
₽ 1,408.05
|
₽ 354,828.00
|
|
IS
|
Politekh Tower
|
Техноэласт ЭПП of the basement (sqm)
|
504.00
|
₽ 1,611.39
|
₽ 812,142.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Atom Tower
|
|
1,396.02
|
₽ 1,545.01
|
₽ 2,156,866.40
|
|
IS
|
Atom Tower
|
Backfiling (cum)
|
12.72
|
₽ 235.85
|
₽ 3,000.00
|
|
IS
|
Atom Tower
|
CARBON PROF 300 of the basement (cum)
|
31.80
|
₽ 1,837.15
|
₽ 58,421.40
|
|
IS
|
Atom Tower
|
PLANTER Geo of the basement (sqm)
|
318.00
|
₽ 1,604.46
|
₽ 510,218.00
|
|
IS
|
Atom Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
79.50
|
₽ 1,458.45
|
₽ 115,947.00
|
|
IS
|
Atom Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
318.00
|
₽ 1,400.79
|
₽ 445,452.00
|
|
IS
|
Atom Tower
|
Техноэласт ЭПП of the basement (sqm)
|
636.00
|
₽ 1,609.79
|
₽ 1,023,828.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
RTK Tower
|
|
1,303.83
|
₽ 1,545.97
|
₽ 2,015,685.60
|
|
IS
|
RTK Tower
|
Backfiling (cum)
|
11.88
|
₽ 252.53
|
₽ 3,000.00
|
|
IS
|
RTK Tower
|
CARBON PROF 300 of the basement (cum)
|
29.70
|
₽ 1,769.97
|
₽ 52,568.10
|
|
IS
|
RTK Tower
|
PLANTER Geo of the basement (sqm)
|
297.00
|
₽ 1,605.55
|
₽ 476,847.00
|
|
IS
|
RTK Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
74.25
|
₽ 1,482.16
|
₽ 110,050.50
|
|
IS
|
RTK Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
297.00
|
₽ 1,401.88
|
₽ 416,358.00
|
|
IS
|
RTK Tower
|
Техноэласт ЭПП of the basement (sqm)
|
594.00
|
₽ 1,610.88
|
₽ 956,862.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P101
|
|
737.52
|
₽ 1,567.61
|
₽ 1,156,146.40
|
|
IS
|
P101
|
Backfiling (cum)
|
6.72
|
₽ 892.86
|
₽ 6,000.00
|
|
IS
|
P101
|
CARBON PROF 300 of the basement (cum)
|
16.80
|
₽ 1,876.57
|
₽ 31,526.40
|
|
IS
|
P101
|
PLANTER Geo of the basement (sqm)
|
168.00
|
₽ 1,623.02
|
₽ 272,668.00
|
|
IS
|
P101
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
42.00
|
₽ 1,573.14
|
₽ 66,072.00
|
|
IS
|
P101
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
168.00
|
₽ 1,419.36
|
₽ 238,452.00
|
|
IS
|
P101
|
Техноэласт ЭПП of the basement (sqm)
|
336.00
|
₽ 1,611.39
|
₽ 541,428.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P102
|
|
2,344.26
|
₽ 1,546.49
|
₽ 3,625,383.20
|
|
IS
|
P102
|
Backfiling (cum)
|
21.36
|
₽ 280.90
|
₽ 6,000.00
|
|
IS
|
P102
|
CARBON PROF 300 of the basement (cum)
|
53.40
|
₽ 1,803.34
|
₽ 96,298.20
|
|
IS
|
P102
|
PLANTER Geo of the basement (sqm)
|
534.00
|
₽ 1,605.87
|
₽ 857,534.00
|
|
IS
|
P102
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
133.50
|
₽ 1,468.25
|
₽ 196,011.00
|
|
IS
|
P102
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
534.00
|
₽ 1,402.20
|
₽ 748,776.00
|
|
IS
|
P102
|
Техноэласт ЭПП of the basement (sqm)
|
1,068.00
|
₽ 1,611.20
|
₽ 1,720,764.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P103
|
|
1,764.78
|
₽ 1,558.83
|
₽ 2,750,989.60
|
|
IS
|
P103
|
Backfiling (cum)
|
16.08
|
₽ 373.13
|
₽ 6,000.00
|
|
IS
|
P103
|
CARBON PROF 300 of the basement (cum)
|
40.20
|
₽ 1,938.67
|
₽ 77,934.60
|
|
IS
|
P103
|
PLANTER Geo of the basement (sqm)
|
402.00
|
₽ 1,615.43
|
₽ 649,402.00
|
|
IS
|
P103
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
100.50
|
₽ 1,519.73
|
₽ 152,733.00
|
|
IS
|
P103
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
402.00
|
₽ 1,411.76
|
₽ 567,528.00
|
|
IS
|
P103
|
Техноэласт ЭПП of the basement (sqm)
|
804.00
|
₽ 1,613.67
|
₽ 1,297,392.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P105
|
|
605.82
|
₽ 1,560.70
|
₽ 945,502.40
|
|
IS
|
P105
|
Backfiling (cum)
|
5.52
|
₽ 1,086.96
|
₽ 6,000.00
|
|
IS
|
P105
|
CARBON PROF 300 of the basement (cum)
|
13.80
|
₽ 1,899.09
|
₽ 26,207.40
|
|
IS
|
P105
|
PLANTER Geo of the basement (sqm)
|
138.00
|
₽ 1,606.80
|
₽ 221,738.00
|
|
IS
|
P105
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
34.50
|
₽ 1,535.57
|
₽ 52,977.00
|
|
IS
|
P105
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
138.00
|
₽ 1,403.13
|
₽ 193,632.00
|
|
IS
|
P105
|
Техноэласт ЭПП of the basement (sqm)
|
276.00
|
₽ 1,612.13
|
₽ 444,948.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P106
|
|
105.36
|
₽ 1,814.12
|
₽ 191,135.20
|
|
IS
|
P106
|
Backfiling (cum)
|
0.96
|
₽ 6,250.00
|
₽ 6,000.00
|
|
IS
|
P106
|
CARBON PROF 300 of the basement (cum)
|
2.40
|
₽ 4,448.00
|
₽ 10,675.20
|
|
IS
|
P106
|
PLANTER Geo of the basement (sqm)
|
24.00
|
₽ 1,792.67
|
₽ 43,024.00
|
|
IS
|
P106
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
6.00
|
₽ 2,116.00
|
₽ 12,696.00
|
|
IS
|
P106
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
24.00
|
₽ 1,589.00
|
₽ 38,136.00
|
|
IS
|
P106
|
Техноэласт ЭПП of the basement (sqm)
|
48.00
|
₽ 1,679.25
|
₽ 80,604.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P107
|
|
1,554.06
|
₽ 1,551.43
|
₽ 2,411,019.20
|
|
IS
|
P107
|
Backfiling (cum)
|
14.16
|
₽ 423.73
|
₽ 6,000.00
|
|
IS
|
P107
|
CARBON PROF 300 of the basement (cum)
|
35.40
|
₽ 1,810.29
|
₽ 64,084.20
|
|
IS
|
P107
|
PLANTER Geo of the basement (sqm)
|
354.00
|
₽ 1,607.50
|
₽ 569,054.00
|
|
IS
|
P107
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
88.50
|
₽ 1,503.29
|
₽ 133,041.00
|
|
IS
|
P107
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
354.00
|
₽ 1,403.83
|
₽ 496,956.00
|
|
IS
|
P107
|
Техноэласт ЭПП of the basement (sqm)
|
708.00
|
₽ 1,612.83
|
₽ 1,141,884.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P108
|
|
790.20
|
₽ 1,553.86
|
₽ 1,227,864.00
|
|
IS
|
P108
|
Backfiling (cum)
|
7.20
|
₽ 833.33
|
₽ 6,000.00
|
|
IS
|
P108
|
CARBON PROF 300 of the basement (cum)
|
18.00
|
₽ 1,789.67
|
₽ 32,214.00
|
|
IS
|
P108
|
PLANTER Geo of the basement (sqm)
|
180.00
|
₽ 1,602.67
|
₽ 288,480.00
|
|
IS
|
P108
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
45.00
|
₽ 1,566.00
|
₽ 70,470.00
|
|
IS
|
P108
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
180.00
|
₽ 1,399.00
|
₽ 251,820.00
|
|
IS
|
P108
|
Техноэласт ЭПП of the basement (sqm)
|
360.00
|
₽ 1,608.00
|
₽ 578,880.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P109
|
|
948.24
|
₽ 1,557.85
|
₽ 1,477,216.80
|
|
IS
|
P109
|
Backfiling (cum)
|
8.64
|
₽ 694.44
|
₽ 6,000.00
|
|
IS
|
P109
|
CARBON PROF 300 of the basement (cum)
|
21.60
|
₽ 2,017.44
|
₽ 43,576.80
|
|
IS
|
P109
|
PLANTER Geo of the basement (sqm)
|
216.00
|
₽ 1,607.94
|
₽ 347,316.00
|
|
IS
|
P109
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
54.00
|
₽ 1,482.67
|
₽ 80,064.00
|
|
IS
|
P109
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
216.00
|
₽ 1,404.28
|
₽ 303,324.00
|
|
IS
|
P109
|
Техноэласт ЭПП of the basement (sqm)
|
432.00
|
₽ 1,613.28
|
₽ 696,936.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P110
|
|
1,290.66
|
₽ 1,553.49
|
₽ 2,005,031.20
|
|
IS
|
P110
|
Backfiling (cum)
|
11.76
|
₽ 510.20
|
₽ 6,000.00
|
|
IS
|
P110
|
CARBON PROF 300 of the basement (cum)
|
29.40
|
₽ 1,879.12
|
₽ 55,246.20
|
|
IS
|
P110
|
PLANTER Geo of the basement (sqm)
|
294.00
|
₽ 1,608.48
|
₽ 472,894.00
|
|
IS
|
P110
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
73.50
|
₽ 1,482.33
|
₽ 108,951.00
|
|
IS
|
P110
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
294.00
|
₽ 1,404.82
|
₽ 413,016.00
|
|
IS
|
P110
|
Техноэласт ЭПП of the basement (sqm)
|
588.00
|
₽ 1,613.82
|
₽ 948,924.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P111
|
|
1,843.80
|
₽ 1,547.84
|
₽ 2,853,916.00
|
|
IS
|
P111
|
Backfiling (cum)
|
16.80
|
₽ 357.14
|
₽ 6,000.00
|
|
IS
|
P111
|
CARBON PROF 300 of the basement (cum)
|
42.00
|
₽ 1,880.14
|
₽ 78,966.00
|
|
IS
|
P111
|
PLANTER Geo of the basement (sqm)
|
420.00
|
₽ 1,602.67
|
₽ 673,120.00
|
|
IS
|
P111
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
105.00
|
₽ 1,500.29
|
₽ 157,530.00
|
|
IS
|
P111
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
420.00
|
₽ 1,399.00
|
₽ 587,580.00
|
|
IS
|
P111
|
Техноэласт ЭПП of the basement (sqm)
|
840.00
|
₽ 1,608.00
|
₽ 1,350,720.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Akadem Tower
|
|
1,000.92
|
₽ 1,547.36
|
₽ 1,548,784.40
|
|
IS
|
Akadem Tower
|
Backfiling (cum)
|
9.12
|
₽ 328.95
|
₽ 3,000.00
|
|
IS
|
Akadem Tower
|
CARBON PROF 300 of the basement (cum)
|
22.80
|
₽ 1,855.89
|
₽ 42,314.40
|
|
IS
|
Akadem Tower
|
PLANTER Geo of the basement (sqm)
|
228.00
|
₽ 1,605.17
|
₽ 365,978.00
|
|
IS
|
Akadem Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
57.00
|
₽ 1,466.00
|
₽ 83,562.00
|
|
IS
|
Akadem Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
228.00
|
₽ 1,401.50
|
₽ 319,542.00
|
|
IS
|
Akadem Tower
|
Техноэласт ЭПП of the basement (sqm)
|
456.00
|
₽ 1,610.50
|
₽ 734,388.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Nauki Tower
|
|
1,000.92
|
₽ 1,547.36
|
₽ 1,548,784.40
|
|
IS
|
Nauki Tower
|
Backfiling (cum)
|
9.12
|
₽ 328.95
|
₽ 3,000.00
|
|
IS
|
Nauki Tower
|
CARBON PROF 300 of the basement (cum)
|
22.80
|
₽ 1,855.89
|
₽ 42,314.40
|
|
IS
|
Nauki Tower
|
PLANTER Geo of the basement (sqm)
|
228.00
|
₽ 1,605.17
|
₽ 365,978.00
|
|
IS
|
Nauki Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
57.00
|
₽ 1,466.00
|
₽ 83,562.00
|
|
IS
|
Nauki Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
228.00
|
₽ 1,401.50
|
₽ 319,542.00
|
|
IS
|
Nauki Tower
|
Техноэласт ЭПП of the basement (sqm)
|
456.00
|
₽ 1,610.50
|
₽ 734,388.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P201
|
|
2,581.32
|
₽ 1,546.75
|
₽ 3,992,662.40
|
|
IS
|
P201
|
Backfiling (cum)
|
23.52
|
₽ 255.10
|
₽ 6,000.00
|
|
IS
|
P201
|
CARBON PROF 300 of the basement (cum)
|
58.80
|
₽ 1,782.18
|
₽ 104,792.40
|
|
IS
|
P201
|
PLANTER Geo of the basement (sqm)
|
588.00
|
₽ 1,608.48
|
₽ 945,788.00
|
|
IS
|
P201
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
147.00
|
₽ 1,482.33
|
₽ 217,902.00
|
|
IS
|
P201
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
588.00
|
₽ 1,404.82
|
₽ 826,032.00
|
|
IS
|
P201
|
Техноэласт ЭПП of the basement (sqm)
|
1,176.00
|
₽ 1,608.97
|
₽ 1,892,148.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P202
|
|
1,185.30
|
₽ 1,556.14
|
₽ 1,844,496.00
|
|
IS
|
P202
|
Backfiling (cum)
|
10.80
|
₽ 555.56
|
₽ 6,000.00
|
|
IS
|
P202
|
CARBON PROF 300 of the basement (cum)
|
27.00
|
₽ 1,928.56
|
₽ 52,071.00
|
|
IS
|
P202
|
PLANTER Geo of the basement (sqm)
|
270.00
|
₽ 1,613.22
|
₽ 435,570.00
|
|
IS
|
P202
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
67.50
|
₽ 1,510.44
|
₽ 101,955.00
|
|
IS
|
P202
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
270.00
|
₽ 1,409.56
|
₽ 380,580.00
|
|
IS
|
P202
|
Техноэласт ЭПП of the basement (sqm)
|
540.00
|
₽ 1,608.00
|
₽ 868,320.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P203
|
|
1,396.02
|
₽ 1,547.16
|
₽ 2,159,866.40
|
|
IS
|
P203
|
Backfiling (cum)
|
12.72
|
₽ 471.70
|
₽ 6,000.00
|
|
IS
|
P203
|
CARBON PROF 300 of the basement (cum)
|
31.80
|
₽ 1,837.15
|
₽ 58,421.40
|
|
IS
|
P203
|
PLANTER Geo of the basement (sqm)
|
318.00
|
₽ 1,604.46
|
₽ 510,218.00
|
|
IS
|
P203
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
79.50
|
₽ 1,458.45
|
₽ 115,947.00
|
|
IS
|
P203
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
318.00
|
₽ 1,400.79
|
₽ 445,452.00
|
|
IS
|
P203
|
Техноэласт ЭПП of the basement (sqm)
|
636.00
|
₽ 1,609.79
|
₽ 1,023,828.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P204
|
|
2,634.00
|
₽ 1,542.36
|
₽ 4,062,580.00
|
|
IS
|
P204
|
Backfiling (cum)
|
24.00
|
₽ 250.00
|
₽ 6,000.00
|
|
IS
|
P204
|
CARBON PROF 300 of the basement (cum)
|
60.00
|
₽ 1,758.00
|
₽ 105,480.00
|
|
IS
|
P204
|
PLANTER Geo of the basement (sqm)
|
600.00
|
₽ 1,602.67
|
₽ 961,600.00
|
|
IS
|
P204
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
150.00
|
₽ 1,470.00
|
₽ 220,500.00
|
|
IS
|
P204
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
600.00
|
₽ 1,399.00
|
₽ 839,400.00
|
|
IS
|
P204
|
Техноэласт ЭПП of the basement (sqm)
|
1,200.00
|
₽ 1,608.00
|
₽ 1,929,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
CHapaev Tower
|
|
1,000.92
|
₽ 1,547.36
|
₽ 1,548,784.40
|
|
IS
|
CHapaev Tower
|
Backfiling (cum)
|
9.12
|
₽ 328.95
|
₽ 3,000.00
|
|
IS
|
CHapaev Tower
|
CARBON PROF 300 of the basement (cum)
|
22.80
|
₽ 1,855.89
|
₽ 42,314.40
|
|
IS
|
CHapaev Tower
|
PLANTER Geo of the basement (sqm)
|
228.00
|
₽ 1,605.17
|
₽ 365,978.00
|
|
IS
|
CHapaev Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
57.00
|
₽ 1,466.00
|
₽ 83,562.00
|
|
IS
|
CHapaev Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
228.00
|
₽ 1,401.50
|
₽ 319,542.00
|
|
IS
|
CHapaev Tower
|
Техноэласт ЭПП of the basement (sqm)
|
456.00
|
₽ 1,610.50
|
₽ 734,388.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
Budenniy Tower
|
|
1,000.92
|
₽ 1,547.36
|
₽ 1,548,784.40
|
|
IS
|
Budenniy Tower
|
Backfiling (cum)
|
9.12
|
₽ 328.95
|
₽ 3,000.00
|
|
IS
|
Budenniy Tower
|
CARBON PROF 300 of the basement (cum)
|
22.80
|
₽ 1,855.89
|
₽ 42,314.40
|
|
IS
|
Budenniy Tower
|
PLANTER Geo of the basement (sqm)
|
228.00
|
₽ 1,605.17
|
₽ 365,978.00
|
|
IS
|
Budenniy Tower
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
57.00
|
₽ 1,466.00
|
₽ 83,562.00
|
|
IS
|
Budenniy Tower
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
228.00
|
₽ 1,401.50
|
₽ 319,542.00
|
|
IS
|
Budenniy Tower
|
Техноэласт ЭПП of the basement (sqm)
|
456.00
|
₽ 1,610.50
|
₽ 734,388.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P301
|
|
1,185.30
|
₽ 1,556.14
|
₽ 1,844,496.00
|
|
IS
|
P301
|
Backfiling (cum)
|
10.80
|
₽ 555.56
|
₽ 6,000.00
|
|
IS
|
P301
|
CARBON PROF 300 of the basement (cum)
|
27.00
|
₽ 1,928.56
|
₽ 52,071.00
|
|
IS
|
P301
|
PLANTER Geo of the basement (sqm)
|
270.00
|
₽ 1,613.22
|
₽ 435,570.00
|
|
IS
|
P301
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
67.50
|
₽ 1,510.44
|
₽ 101,955.00
|
|
IS
|
P301
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
270.00
|
₽ 1,409.56
|
₽ 380,580.00
|
|
IS
|
P301
|
Техноэласт ЭПП of the basement (sqm)
|
540.00
|
₽ 1,608.00
|
₽ 868,320.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P302
|
|
2,502.30
|
₽ 1,546.91
|
₽ 3,870,836.00
|
|
IS
|
P302
|
Backfiling (cum)
|
22.80
|
₽ 263.16
|
₽ 6,000.00
|
|
IS
|
P302
|
CARBON PROF 300 of the basement (cum)
|
57.00
|
₽ 1,788.79
|
₽ 101,961.00
|
|
IS
|
P302
|
PLANTER Geo of the basement (sqm)
|
570.00
|
₽ 1,607.67
|
₽ 916,370.00
|
|
IS
|
P302
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
142.50
|
₽ 1,495.47
|
₽ 213,105.00
|
|
IS
|
P302
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
570.00
|
₽ 1,404.00
|
₽ 800,280.00
|
|
IS
|
P302
|
Техноэласт ЭПП of the basement (sqm)
|
1,140.00
|
₽ 1,608.00
|
₽ 1,833,120.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P303
|
|
1,132.62
|
₽ 1,555.14
|
₽ 1,761,378.40
|
|
IS
|
P303
|
Backfiling (cum)
|
10.32
|
₽ 581.40
|
₽ 6,000.00
|
|
IS
|
P303
|
CARBON PROF 300 of the basement (cum)
|
25.80
|
₽ 1,921.84
|
₽ 49,583.40
|
|
IS
|
P303
|
PLANTER Geo of the basement (sqm)
|
258.00
|
₽ 1,604.88
|
₽ 414,058.00
|
|
IS
|
P303
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
64.50
|
₽ 1,540.42
|
₽ 99,357.00
|
|
IS
|
P303
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
258.00
|
₽ 1,401.21
|
₽ 361,512.00
|
|
IS
|
P303
|
Техноэласт ЭПП of the basement (sqm)
|
516.00
|
₽ 1,610.21
|
₽ 830,868.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IS
|
P304
|
|
2,634.00
|
₽ 1,542.36
|
₽ 4,062,580.00
|
|
IS
|
P304
|
Backfiling (cum)
|
24.00
|
₽ 250.00
|
₽ 6,000.00
|
|
IS
|
P304
|
CARBON PROF 300 of the basement (cum)
|
60.00
|
₽ 1,758.00
|
₽ 105,480.00
|
|
IS
|
P304
|
PLANTER Geo of the basement (sqm)
|
600.00
|
₽ 1,602.67
|
₽ 961,600.00
|
|
IS
|
P304
|
ТехноНИКОЛЬ №01 of the basement (kg)
|
150.00
|
₽ 1,470.00
|
₽ 220,500.00
|
|
IS
|
P304
|
ТехноНИКОЛЬ №27 of the basement (kg)
|
600.00
|
₽ 1,399.00
|
₽ 839,400.00
|
|
IS
|
P304
|
Техноэласт ЭПП of the basement (sqm)
|
1,200.00
|
₽ 1,608.00
|
₽ 1,929,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
|
|
1,943,303.08
|
₽ 972.02
|
₽ 1,888,929,259.20
|
|
GRF
|
P101
|
|
73,560.40
|
₽ 972.16
|
₽ 71,512,319.87
|
|
GRF
|
P101
|
Asphalt concrete finishing of the greenroof (cum)
|
74.20
|
₽ 11,216.98
|
₽ 832,300.00
|
|
GRF
|
P101
|
Asphalt concrete of the greenroof (cum)
|
192.92
|
₽ 11,200.50
|
₽ 2,160,800.00
|
|
GRF
|
P101
|
CARBON SOLID 500 of the greenroof (cum)
|
148.40
|
₽ 1,791.71
|
₽ 265,890.00
|
|
GRF
|
P101
|
Clay pebbles of the greenroof (cum)
|
37.10
|
₽ 2,173.85
|
₽ 80,650.00
|
|
GRF
|
P101
|
Concrete of greenroof (cum)
|
237.44
|
₽ 6,948.24
|
₽ 1,649,790.00
|
|
GRF
|
P101
|
Concrete of the slabs (cum)
|
296.80
|
₽ 6,952.16
|
₽ 2,063,400.00
|
|
GRF
|
P101
|
Concrete of the walls, columns (cum)
|
39.18
|
₽ 7,026.10
|
₽ 275,265.60
|
|
GRF
|
P101
|
Formwork of the slabs (sqm)
|
1,484.00
|
₽ 1,436.15
|
₽ 2,131,250.00
|
|
GRF
|
P101
|
Formwork of the walls, columns (sqm)
|
263.56
|
₽ 1,443.47
|
₽ 380,439.60
|
|
GRF
|
P101
|
Geotextile of the greenroof (sqm)
|
1,484.00
|
₽ 1,286.15
|
₽ 1,908,650.00
|
|
GRF
|
P101
|
Gravel fill of the greenroof (cum)
|
148.40
|
₽ 1,629.38
|
₽ 241,800.00
|
|
GRF
|
P101
|
Lightning protection current of the greenroof (kg)
|
593.60
|
₽ 1,119.78
|
₽ 664,700.00
|
|
GRF
|
P101
|
Masterfibe of the greenroof (cum)
|
59.36
|
₽ 146,197.78
|
₽ 8,678,300.00
|
|
GRF
|
P101
|
Paving of the greenroof (sqm)
|
1,484.00
|
₽ 4,186.15
|
₽ 6,212,250.00
|
|
GRF
|
P101
|
Plant soil fill of the greenroof (cum)
|
371.00
|
₽ 1,122.91
|
₽ 416,600.00
|
|
GRF
|
P101
|
PLANTER Geo of the greenroof (sqm)
|
2,968.00
|
₽ 1,603.82
|
₽ 4,760,134.67
|
|
GRF
|
P101
|
Rebar of the slabs (kg)
|
53,424.00
|
₽ 574.01
|
₽ 30,665,850.00
|
|
GRF
|
P101
|
Rebar of the walls, columns (kg)
|
7,835.52
|
₽ 574.30
|
₽ 4,499,952.00
|
|
GRF
|
P101
|
Sand fill of the greenroof (cum)
|
148.40
|
₽ 1,129.38
|
₽ 167,600.00
|
|
GRF
|
P101
|
Screed of the greenroof (cum)
|
118.72
|
₽ 1,646.56
|
₽ 195,480.00
|
|
GRF
|
P101
|
Soil fill of the greenroof (cum)
|
296.80
|
₽ 1,119.78
|
₽ 332,350.00
|
|
GRF
|
P101
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
371.00
|
₽ 1,457.91
|
₽ 540,886.00
|
|
GRF
|
P101
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,484.00
|
₽ 1,609.15
|
₽ 2,387,982.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P102
|
|
95,222.05
|
₽ 972.14
|
₽ 92,569,211.63
|
|
GRF
|
P102
|
Asphalt concrete finishing of the greenroof (cum)
|
96.05
|
₽ 11,205.62
|
₽ 1,076,300.00
|
|
GRF
|
P102
|
Asphalt concrete of the greenroof (cum)
|
249.73
|
₽ 11,201.30
|
₽ 2,797,300.00
|
|
GRF
|
P102
|
CARBON SOLID 500 of the greenroof (cum)
|
192.10
|
₽ 1,800.94
|
₽ 345,960.00
|
|
GRF
|
P102
|
Clay pebbles of the greenroof (cum)
|
48.03
|
₽ 2,153.05
|
₽ 103,400.00
|
|
GRF
|
P102
|
Concrete of greenroof (cum)
|
307.36
|
₽ 6,952.14
|
₽ 2,136,810.00
|
|
GRF
|
P102
|
Concrete of the slabs (cum)
|
384.20
|
₽ 6,951.46
|
₽ 2,670,750.00
|
|
GRF
|
P102
|
Concrete of the walls, columns (cum)
|
50.71
|
₽ 7,008.59
|
₽ 355,436.40
|
|
GRF
|
P102
|
Formwork of the slabs (sqm)
|
1,921.00
|
₽ 1,436.34
|
₽ 2,759,200.00
|
|
GRF
|
P102
|
Formwork of the walls, columns (sqm)
|
341.17
|
₽ 1,444.57
|
₽ 492,842.40
|
|
GRF
|
P102
|
Geotextile of the greenroof (sqm)
|
1,921.00
|
₽ 1,286.34
|
₽ 2,471,050.00
|
|
GRF
|
P102
|
Gravel fill of the greenroof (cum)
|
192.10
|
₽ 1,623.37
|
₽ 311,850.00
|
|
GRF
|
P102
|
Lightning protection current of the greenroof (kg)
|
768.40
|
₽ 1,119.86
|
₽ 860,500.00
|
|
GRF
|
P102
|
Masterfibe of the greenroof (cum)
|
76.84
|
₽ 146,198.59
|
₽ 11,233,900.00
|
|
GRF
|
P102
|
Paving of the greenroof (sqm)
|
1,921.00
|
₽ 4,186.34
|
₽ 8,041,950.00
|
|
GRF
|
P102
|
Plant soil fill of the greenroof (cum)
|
480.25
|
₽ 1,121.50
|
₽ 538,600.00
|
|
GRF
|
P102
|
PLANTER Geo of the greenroof (sqm)
|
3,842.00
|
₽ 1,604.00
|
₽ 6,162,575.33
|
|
GRF
|
P102
|
Rebar of the slabs (kg)
|
69,156.00
|
₽ 574.04
|
₽ 39,698,250.00
|
|
GRF
|
P102
|
Rebar of the walls, columns (kg)
|
10,142.88
|
₽ 574.16
|
₽ 5,823,588.00
|
|
GRF
|
P102
|
Sand fill of the greenroof (cum)
|
192.10
|
₽ 1,123.37
|
₽ 215,800.00
|
|
GRF
|
P102
|
Screed of the greenroof (cum)
|
153.68
|
₽ 1,630.79
|
₽ 250,620.00
|
|
GRF
|
P102
|
Soil fill of the greenroof (cum)
|
384.20
|
₽ 1,121.03
|
₽ 430,700.00
|
|
GRF
|
P102
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
480.25
|
₽ 1,458.19
|
₽ 700,296.50
|
|
GRF
|
P102
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,921.00
|
₽ 1,609.34
|
₽ 3,091,533.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P103
|
|
113,463.44
|
₽ 971.97
|
₽ 110,282,754.70
|
|
GRF
|
P103
|
Asphalt concrete finishing of the greenroof (cum)
|
114.45
|
₽ 11,203.15
|
₽ 1,282,200.00
|
|
GRF
|
P103
|
Asphalt concrete of the greenroof (cum)
|
297.57
|
₽ 11,201.23
|
₽ 3,333,150.00
|
|
GRF
|
P103
|
CARBON SOLID 500 of the greenroof (cum)
|
228.90
|
₽ 1,786.76
|
₽ 408,990.00
|
|
GRF
|
P103
|
Clay pebbles of the greenroof (cum)
|
57.23
|
₽ 2,144.17
|
₽ 122,700.00
|
|
GRF
|
P103
|
Concrete of greenroof (cum)
|
366.24
|
₽ 6,953.47
|
₽ 2,546,640.00
|
|
GRF
|
P103
|
Concrete of the slabs (cum)
|
457.80
|
₽ 6,951.83
|
₽ 3,182,550.00
|
|
GRF
|
P103
|
Concrete of the walls, columns (cum)
|
60.43
|
₽ 6,965.59
|
₽ 420,927.60
|
|
GRF
|
P103
|
Formwork of the slabs (sqm)
|
2,289.00
|
₽ 1,435.12
|
₽ 3,285,000.00
|
|
GRF
|
P103
|
Formwork of the walls, columns (sqm)
|
406.53
|
₽ 1,438.48
|
₽ 584,781.60
|
|
GRF
|
P103
|
Geotextile of the greenroof (sqm)
|
2,289.00
|
₽ 1,285.12
|
₽ 2,941,650.00
|
|
GRF
|
P103
|
Gravel fill of the greenroof (cum)
|
228.90
|
₽ 1,627.79
|
₽ 372,600.00
|
|
GRF
|
P103
|
Lightning protection current of the greenroof (kg)
|
915.60
|
₽ 1,121.56
|
₽ 1,026,900.00
|
|
GRF
|
P103
|
Masterfibe of the greenroof (cum)
|
91.56
|
₽ 146,215.60
|
₽ 13,387,500.00
|
|
GRF
|
P103
|
Paving of the greenroof (sqm)
|
2,289.00
|
₽ 4,185.12
|
₽ 9,579,750.00
|
|
GRF
|
P103
|
Plant soil fill of the greenroof (cum)
|
572.25
|
₽ 1,121.10
|
₽ 641,550.00
|
|
GRF
|
P103
|
PLANTER Geo of the greenroof (sqm)
|
4,578.00
|
₽ 1,602.79
|
₽ 7,337,578.00
|
|
GRF
|
P103
|
Rebar of the slabs (kg)
|
82,404.00
|
₽ 574.03
|
₽ 47,302,650.00
|
|
GRF
|
P103
|
Rebar of the walls, columns (kg)
|
12,085.92
|
₽ 574.18
|
₽ 6,939,492.00
|
|
GRF
|
P103
|
Sand fill of the greenroof (cum)
|
228.90
|
₽ 1,127.79
|
₽ 258,150.00
|
|
GRF
|
P103
|
Screed of the greenroof (cum)
|
183.12
|
₽ 1,640.07
|
₽ 300,330.00
|
|
GRF
|
P103
|
Soil fill of the greenroof (cum)
|
457.80
|
₽ 1,121.56
|
₽ 513,450.00
|
|
GRF
|
P103
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
572.25
|
₽ 1,456.04
|
₽ 833,218.50
|
|
GRF
|
P103
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,289.00
|
₽ 1,608.12
|
₽ 3,680,997.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P104
|
|
90,413.86
|
₽ 972.10
|
₽ 87,891,585.20
|
|
GRF
|
P104
|
Asphalt concrete finishing of the greenroof (cum)
|
91.20
|
₽ 11,220.39
|
₽ 1,023,300.00
|
|
GRF
|
P104
|
Asphalt concrete of the greenroof (cum)
|
237.12
|
₽ 11,191.80
|
₽ 2,653,800.00
|
|
GRF
|
P104
|
CARBON SOLID 500 of the greenroof (cum)
|
182.40
|
₽ 1,799.84
|
₽ 328,290.00
|
|
GRF
|
P104
|
Clay pebbles of the greenroof (cum)
|
45.60
|
₽ 2,161.18
|
₽ 98,550.00
|
|
GRF
|
P104
|
Concrete of greenroof (cum)
|
291.84
|
₽ 6,956.00
|
₽ 2,030,040.00
|
|
GRF
|
P104
|
Concrete of the slabs (cum)
|
364.80
|
₽ 6,954.77
|
₽ 2,537,100.00
|
|
GRF
|
P104
|
Concrete of the walls, columns (cum)
|
48.15
|
₽ 6,965.66
|
₽ 335,421.60
|
|
GRF
|
P104
|
Formwork of the slabs (sqm)
|
1,824.00
|
₽ 1,435.94
|
₽ 2,619,150.00
|
|
GRF
|
P104
|
Formwork of the walls, columns (sqm)
|
323.94
|
₽ 1,440.49
|
₽ 466,635.60
|
|
GRF
|
P104
|
Geotextile of the greenroof (sqm)
|
1,824.00
|
₽ 1,285.94
|
₽ 2,345,550.00
|
|
GRF
|
P104
|
Gravel fill of the greenroof (cum)
|
182.40
|
₽ 1,625.00
|
₽ 296,400.00
|
|
GRF
|
P104
|
Lightning protection current of the greenroof (kg)
|
729.60
|
₽ 1,121.30
|
₽ 818,100.00
|
|
GRF
|
P104
|
Masterfibe of the greenroof (cum)
|
72.96
|
₽ 146,212.99
|
₽ 10,667,700.00
|
|
GRF
|
P104
|
Paving of the greenroof (sqm)
|
1,824.00
|
₽ 4,185.94
|
₽ 7,635,150.00
|
|
GRF
|
P104
|
Plant soil fill of the greenroof (cum)
|
456.00
|
₽ 1,122.04
|
₽ 511,650.00
|
|
GRF
|
P104
|
PLANTER Geo of the greenroof (sqm)
|
3,648.00
|
₽ 1,603.60
|
₽ 5,849,948.00
|
|
GRF
|
P104
|
Rebar of the slabs (kg)
|
65,664.00
|
₽ 574.02
|
₽ 37,692,750.00
|
|
GRF
|
P104
|
Rebar of the walls, columns (kg)
|
9,630.72
|
₽ 574.29
|
₽ 5,530,872.00
|
|
GRF
|
P104
|
Sand fill of the greenroof (cum)
|
182.40
|
₽ 1,125.00
|
₽ 205,200.00
|
|
GRF
|
P104
|
Screed of the greenroof (cum)
|
145.92
|
₽ 1,637.75
|
₽ 238,980.00
|
|
GRF
|
P104
|
Soil fill of the greenroof (cum)
|
364.80
|
₽ 1,122.53
|
₽ 409,500.00
|
|
GRF
|
P104
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
456.00
|
₽ 1,453.50
|
₽ 662,796.00
|
|
GRF
|
P104
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,824.00
|
₽ 1,608.94
|
₽ 2,934,702.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P105
|
|
73,560.40
|
₽ 972.16
|
₽ 71,512,319.87
|
|
GRF
|
P105
|
Asphalt concrete finishing of the greenroof (cum)
|
74.20
|
₽ 11,216.98
|
₽ 832,300.00
|
|
GRF
|
P105
|
Asphalt concrete of the greenroof (cum)
|
192.92
|
₽ 11,200.50
|
₽ 2,160,800.00
|
|
GRF
|
P105
|
CARBON SOLID 500 of the greenroof (cum)
|
148.40
|
₽ 1,791.71
|
₽ 265,890.00
|
|
GRF
|
P105
|
Clay pebbles of the greenroof (cum)
|
37.10
|
₽ 2,173.85
|
₽ 80,650.00
|
|
GRF
|
P105
|
Concrete of greenroof (cum)
|
237.44
|
₽ 6,948.24
|
₽ 1,649,790.00
|
|
GRF
|
P105
|
Concrete of the slabs (cum)
|
296.80
|
₽ 6,952.16
|
₽ 2,063,400.00
|
|
GRF
|
P105
|
Concrete of the walls, columns (cum)
|
39.18
|
₽ 7,026.10
|
₽ 275,265.60
|
|
GRF
|
P105
|
Formwork of the slabs (sqm)
|
1,484.00
|
₽ 1,436.15
|
₽ 2,131,250.00
|
|
GRF
|
P105
|
Formwork of the walls, columns (sqm)
|
263.56
|
₽ 1,443.47
|
₽ 380,439.60
|
|
GRF
|
P105
|
Geotextile of the greenroof (sqm)
|
1,484.00
|
₽ 1,286.15
|
₽ 1,908,650.00
|
|
GRF
|
P105
|
Gravel fill of the greenroof (cum)
|
148.40
|
₽ 1,629.38
|
₽ 241,800.00
|
|
GRF
|
P105
|
Lightning protection current of the greenroof (kg)
|
593.60
|
₽ 1,119.78
|
₽ 664,700.00
|
|
GRF
|
P105
|
Masterfibe of the greenroof (cum)
|
59.36
|
₽ 146,197.78
|
₽ 8,678,300.00
|
|
GRF
|
P105
|
Paving of the greenroof (sqm)
|
1,484.00
|
₽ 4,186.15
|
₽ 6,212,250.00
|
|
GRF
|
P105
|
Plant soil fill of the greenroof (cum)
|
371.00
|
₽ 1,122.91
|
₽ 416,600.00
|
|
GRF
|
P105
|
PLANTER Geo of the greenroof (sqm)
|
2,968.00
|
₽ 1,603.82
|
₽ 4,760,134.67
|
|
GRF
|
P105
|
Rebar of the slabs (kg)
|
53,424.00
|
₽ 574.01
|
₽ 30,665,850.00
|
|
GRF
|
P105
|
Rebar of the walls, columns (kg)
|
7,835.52
|
₽ 574.30
|
₽ 4,499,952.00
|
|
GRF
|
P105
|
Sand fill of the greenroof (cum)
|
148.40
|
₽ 1,129.38
|
₽ 167,600.00
|
|
GRF
|
P105
|
Screed of the greenroof (cum)
|
118.72
|
₽ 1,646.56
|
₽ 195,480.00
|
|
GRF
|
P105
|
Soil fill of the greenroof (cum)
|
296.80
|
₽ 1,119.78
|
₽ 332,350.00
|
|
GRF
|
P105
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
371.00
|
₽ 1,457.91
|
₽ 540,886.00
|
|
GRF
|
P105
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,484.00
|
₽ 1,609.15
|
₽ 2,387,982.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P106
|
|
84,069.02
|
₽ 972.10
|
₽ 81,723,244.13
|
|
GRF
|
P106
|
Asphalt concrete finishing of the greenroof (cum)
|
84.80
|
₽ 11,204.60
|
₽ 950,150.00
|
|
GRF
|
P106
|
Asphalt concrete of the greenroof (cum)
|
220.48
|
₽ 11,199.43
|
₽ 2,469,250.00
|
|
GRF
|
P106
|
CARBON SOLID 500 of the greenroof (cum)
|
169.60
|
₽ 1,787.79
|
₽ 303,210.00
|
|
GRF
|
P106
|
Clay pebbles of the greenroof (cum)
|
42.40
|
₽ 2,173.35
|
₽ 92,150.00
|
|
GRF
|
P106
|
Concrete of greenroof (cum)
|
271.36
|
₽ 6,954.08
|
₽ 1,887,060.00
|
|
GRF
|
P106
|
Concrete of the slabs (cum)
|
339.20
|
₽ 6,956.96
|
₽ 2,359,800.00
|
|
GRF
|
P106
|
Concrete of the walls, columns (cum)
|
44.77
|
₽ 6,978.24
|
₽ 312,446.40
|
|
GRF
|
P106
|
Formwork of the slabs (sqm)
|
1,696.00
|
₽ 1,435.67
|
₽ 2,434,900.00
|
|
GRF
|
P106
|
Formwork of the walls, columns (sqm)
|
301.21
|
₽ 1,445.68
|
₽ 435,452.40
|
|
GRF
|
P106
|
Geotextile of the greenroof (sqm)
|
1,696.00
|
₽ 1,285.67
|
₽ 2,180,500.00
|
|
GRF
|
P106
|
Gravel fill of the greenroof (cum)
|
169.60
|
₽ 1,623.82
|
₽ 275,400.00
|
|
GRF
|
P106
|
Lightning protection current of the greenroof (kg)
|
678.40
|
₽ 1,119.62
|
₽ 759,550.00
|
|
GRF
|
P106
|
Masterfibe of the greenroof (cum)
|
67.84
|
₽ 146,196.20
|
₽ 9,917,950.00
|
|
GRF
|
P106
|
Paving of the greenroof (sqm)
|
1,696.00
|
₽ 4,185.67
|
₽ 7,098,900.00
|
|
GRF
|
P106
|
Plant soil fill of the greenroof (cum)
|
424.00
|
₽ 1,124.88
|
₽ 476,950.00
|
|
GRF
|
P106
|
PLANTER Geo of the greenroof (sqm)
|
3,392.00
|
₽ 1,603.34
|
₽ 5,438,525.33
|
|
GRF
|
P106
|
Rebar of the slabs (kg)
|
61,056.00
|
₽ 574.04
|
₽ 35,048,850.00
|
|
GRF
|
P106
|
Rebar of the walls, columns (kg)
|
8,954.88
|
₽ 574.26
|
₽ 5,142,438.00
|
|
GRF
|
P106
|
Sand fill of the greenroof (cum)
|
169.60
|
₽ 1,123.82
|
₽ 190,600.00
|
|
GRF
|
P106
|
Screed of the greenroof (cum)
|
135.68
|
₽ 1,641.51
|
₽ 222,720.00
|
|
GRF
|
P106
|
Soil fill of the greenroof (cum)
|
339.20
|
₽ 1,123.82
|
₽ 381,200.00
|
|
GRF
|
P106
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
424.00
|
₽ 1,455.03
|
₽ 616,934.00
|
|
GRF
|
P106
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,696.00
|
₽ 1,608.67
|
₽ 2,728,308.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P107
|
|
78,913.85
|
₽ 972.19
|
₽ 76,719,398.27
|
|
GRF
|
P107
|
Asphalt concrete finishing of the greenroof (cum)
|
79.60
|
₽ 11,190.95
|
₽ 890,800.00
|
|
GRF
|
P107
|
Asphalt concrete of the greenroof (cum)
|
206.96
|
₽ 11,207.48
|
₽ 2,319,500.00
|
|
GRF
|
P107
|
CARBON SOLID 500 of the greenroof (cum)
|
159.20
|
₽ 1,790.95
|
₽ 285,120.00
|
|
GRF
|
P107
|
Clay pebbles of the greenroof (cum)
|
39.80
|
₽ 2,162.06
|
₽ 86,050.00
|
|
GRF
|
P107
|
Concrete of greenroof (cum)
|
254.72
|
₽ 6,955.76
|
₽ 1,771,770.00
|
|
GRF
|
P107
|
Concrete of the slabs (cum)
|
318.40
|
₽ 6,953.52
|
₽ 2,214,000.00
|
|
GRF
|
P107
|
Concrete of the walls, columns (cum)
|
42.03
|
₽ 6,999.31
|
₽ 294,172.80
|
|
GRF
|
P107
|
Formwork of the slabs (sqm)
|
1,592.00
|
₽ 1,436.43
|
₽ 2,286,800.00
|
|
GRF
|
P107
|
Formwork of the walls, columns (sqm)
|
282.74
|
₽ 1,443.15
|
₽ 408,034.80
|
|
GRF
|
P107
|
Geotextile of the greenroof (sqm)
|
1,592.00
|
₽ 1,286.43
|
₽ 2,048,000.00
|
|
GRF
|
P107
|
Gravel fill of the greenroof (cum)
|
159.20
|
₽ 1,626.26
|
₽ 258,900.00
|
|
GRF
|
P107
|
Lightning protection current of the greenroof (kg)
|
636.80
|
₽ 1,121.78
|
₽ 714,350.00
|
|
GRF
|
P107
|
Masterfibe of the greenroof (cum)
|
63.68
|
₽ 146,217.81
|
₽ 9,311,150.00
|
|
GRF
|
P107
|
Paving of the greenroof (sqm)
|
1,592.00
|
₽ 4,186.43
|
₽ 6,664,800.00
|
|
GRF
|
P107
|
Plant soil fill of the greenroof (cum)
|
398.00
|
₽ 1,119.10
|
₽ 445,400.00
|
|
GRF
|
P107
|
PLANTER Geo of the greenroof (sqm)
|
3,184.00
|
₽ 1,604.10
|
₽ 5,107,450.67
|
|
GRF
|
P107
|
Rebar of the slabs (kg)
|
57,312.00
|
₽ 574.03
|
₽ 32,898,750.00
|
|
GRF
|
P107
|
Rebar of the walls, columns (kg)
|
8,405.76
|
₽ 574.34
|
₽ 4,827,726.00
|
|
GRF
|
P107
|
Sand fill of the greenroof (cum)
|
159.20
|
₽ 1,126.26
|
₽ 179,300.00
|
|
GRF
|
P107
|
Screed of the greenroof (cum)
|
127.36
|
₽ 1,636.62
|
₽ 208,440.00
|
|
GRF
|
P107
|
Soil fill of the greenroof (cum)
|
318.40
|
₽ 1,126.26
|
₽ 358,600.00
|
|
GRF
|
P107
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
398.00
|
₽ 1,452.43
|
₽ 578,068.00
|
|
GRF
|
P107
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,592.00
|
₽ 1,609.43
|
₽ 2,562,216.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P108
|
|
97,105.67
|
₽ 971.86
|
₽ 94,372,945.70
|
|
GRF
|
P108
|
Asphalt concrete finishing of the greenroof (cum)
|
97.95
|
₽ 11,191.42
|
₽ 1,096,200.00
|
|
GRF
|
P108
|
Asphalt concrete of the greenroof (cum)
|
254.67
|
₽ 11,195.66
|
₽ 2,851,200.00
|
|
GRF
|
P108
|
CARBON SOLID 500 of the greenroof (cum)
|
195.90
|
₽ 1,791.42
|
₽ 350,940.00
|
|
GRF
|
P108
|
Clay pebbles of the greenroof (cum)
|
48.98
|
₽ 2,150.08
|
₽ 105,300.00
|
|
GRF
|
P108
|
Concrete of greenroof (cum)
|
313.44
|
₽ 6,957.12
|
₽ 2,180,640.00
|
|
GRF
|
P108
|
Concrete of the slabs (cum)
|
391.80
|
₽ 6,954.06
|
₽ 2,724,600.00
|
|
GRF
|
P108
|
Concrete of the walls, columns (cum)
|
51.72
|
₽ 7,006.43
|
₽ 362,355.60
|
|
GRF
|
P108
|
Formwork of the slabs (sqm)
|
1,959.00
|
₽ 1,435.15
|
₽ 2,811,450.00
|
|
GRF
|
P108
|
Formwork of the walls, columns (sqm)
|
347.92
|
₽ 1,436.92
|
₽ 499,929.60
|
|
GRF
|
P108
|
Geotextile of the greenroof (sqm)
|
1,959.00
|
₽ 1,285.15
|
₽ 2,517,600.00
|
|
GRF
|
P108
|
Gravel fill of the greenroof (cum)
|
195.90
|
₽ 1,620.98
|
₽ 317,550.00
|
|
GRF
|
P108
|
Lightning protection current of the greenroof (kg)
|
783.60
|
₽ 1,119.83
|
₽ 877,500.00
|
|
GRF
|
P108
|
Masterfibe of the greenroof (cum)
|
78.36
|
₽ 146,198.32
|
₽ 11,456,100.00
|
|
GRF
|
P108
|
Paving of the greenroof (sqm)
|
1,959.00
|
₽ 4,185.15
|
₽ 8,198,700.00
|
|
GRF
|
P108
|
Plant soil fill of the greenroof (cum)
|
489.75
|
₽ 1,119.14
|
₽ 548,100.00
|
|
GRF
|
P108
|
PLANTER Geo of the greenroof (sqm)
|
3,918.00
|
₽ 1,602.81
|
₽ 6,279,818.00
|
|
GRF
|
P108
|
Rebar of the slabs (kg)
|
70,524.00
|
₽ 574.01
|
₽ 40,481,250.00
|
|
GRF
|
P108
|
Rebar of the walls, columns (kg)
|
10,343.52
|
₽ 574.12
|
₽ 5,938,452.00
|
|
GRF
|
P108
|
Sand fill of the greenroof (cum)
|
195.90
|
₽ 1,120.98
|
₽ 219,600.00
|
|
GRF
|
P108
|
Screed of the greenroof (cum)
|
156.72
|
₽ 1,628.25
|
₽ 255,180.00
|
|
GRF
|
P108
|
Soil fill of the greenroof (cum)
|
391.80
|
₽ 1,120.98
|
₽ 439,200.00
|
|
GRF
|
P108
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
489.75
|
₽ 1,451.60
|
₽ 710,923.50
|
|
GRF
|
P108
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,959.00
|
₽ 1,608.15
|
₽ 3,150,357.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P109
|
|
94,577.65
|
₽ 971.98
|
₽ 91,927,268.40
|
|
GRF
|
P109
|
Asphalt concrete finishing of the greenroof (cum)
|
95.40
|
₽ 11,204.40
|
₽ 1,068,900.00
|
|
GRF
|
P109
|
Asphalt concrete of the greenroof (cum)
|
248.04
|
₽ 11,202.23
|
₽ 2,778,600.00
|
|
GRF
|
P109
|
CARBON SOLID 500 of the greenroof (cum)
|
190.80
|
₽ 1,799.69
|
₽ 343,380.00
|
|
GRF
|
P109
|
Clay pebbles of the greenroof (cum)
|
47.70
|
₽ 2,154.09
|
₽ 102,750.00
|
|
GRF
|
P109
|
Concrete of greenroof (cum)
|
305.28
|
₽ 6,955.68
|
₽ 2,123,430.00
|
|
GRF
|
P109
|
Concrete of the slabs (cum)
|
381.60
|
₽ 6,953.22
|
₽ 2,653,350.00
|
|
GRF
|
P109
|
Concrete of the walls, columns (cum)
|
50.37
|
₽ 7,015.46
|
₽ 353,377.20
|
|
GRF
|
P109
|
Formwork of the slabs (sqm)
|
1,908.00
|
₽ 1,435.30
|
₽ 2,738,550.00
|
|
GRF
|
P109
|
Formwork of the walls, columns (sqm)
|
338.86
|
₽ 1,436.33
|
₽ 486,715.20
|
|
GRF
|
P109
|
Geotextile of the greenroof (sqm)
|
1,908.00
|
₽ 1,285.30
|
₽ 2,452,350.00
|
|
GRF
|
P109
|
Gravel fill of the greenroof (cum)
|
190.80
|
₽ 1,624.21
|
₽ 309,900.00
|
|
GRF
|
P109
|
Lightning protection current of the greenroof (kg)
|
763.20
|
₽ 1,120.68
|
₽ 855,300.00
|
|
GRF
|
P109
|
Masterfibe of the greenroof (cum)
|
76.32
|
₽ 146,206.76
|
₽ 11,158,500.00
|
|
GRF
|
P109
|
Paving of the greenroof (sqm)
|
1,908.00
|
₽ 4,185.30
|
₽ 7,985,550.00
|
|
GRF
|
P109
|
Plant soil fill of the greenroof (cum)
|
477.00
|
₽ 1,120.44
|
₽ 534,450.00
|
|
GRF
|
P109
|
PLANTER Geo of the greenroof (sqm)
|
3,816.00
|
₽ 1,602.97
|
₽ 6,116,916.00
|
|
GRF
|
P109
|
Rebar of the slabs (kg)
|
68,688.00
|
₽ 574.03
|
₽ 39,429,000.00
|
|
GRF
|
P109
|
Rebar of the walls, columns (kg)
|
10,074.24
|
₽ 574.04
|
₽ 5,782,974.00
|
|
GRF
|
P109
|
Sand fill of the greenroof (cum)
|
190.80
|
₽ 1,124.21
|
₽ 214,500.00
|
|
GRF
|
P109
|
Screed of the greenroof (cum)
|
152.64
|
₽ 1,631.68
|
₽ 249,060.00
|
|
GRF
|
P109
|
Soil fill of the greenroof (cum)
|
381.60
|
₽ 1,121.86
|
₽ 428,100.00
|
|
GRF
|
P109
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
477.00
|
₽ 1,452.79
|
₽ 692,982.00
|
|
GRF
|
P109
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,908.00
|
₽ 1,608.30
|
₽ 3,068,634.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P110
|
|
104,788.87
|
₽ 972.10
|
₽ 101,865,068.87
|
|
GRF
|
P110
|
Asphalt concrete finishing of the greenroof (cum)
|
105.70
|
₽ 11,199.15
|
₽ 1,183,750.00
|
|
GRF
|
P110
|
Asphalt concrete of the greenroof (cum)
|
274.82
|
₽ 11,190.96
|
₽ 3,075,500.00
|
|
GRF
|
P110
|
CARBON SOLID 500 of the greenroof (cum)
|
211.40
|
₽ 1,799.15
|
₽ 380,340.00
|
|
GRF
|
P110
|
Clay pebbles of the greenroof (cum)
|
52.85
|
₽ 2,156.10
|
₽ 113,950.00
|
|
GRF
|
P110
|
Concrete of greenroof (cum)
|
338.24
|
₽ 6,957.01
|
₽ 2,353,140.00
|
|
GRF
|
P110
|
Concrete of the slabs (cum)
|
422.80
|
₽ 6,950.80
|
₽ 2,938,800.00
|
|
GRF
|
P110
|
Concrete of the walls, columns (cum)
|
55.81
|
₽ 6,981.01
|
₽ 389,607.60
|
|
GRF
|
P110
|
Formwork of the slabs (sqm)
|
2,114.00
|
₽ 1,435.81
|
₽ 3,035,300.00
|
|
GRF
|
P110
|
Formwork of the walls, columns (sqm)
|
375.45
|
₽ 1,439.78
|
₽ 540,561.60
|
|
GRF
|
P110
|
Geotextile of the greenroof (sqm)
|
2,114.00
|
₽ 1,285.81
|
₽ 2,718,200.00
|
|
GRF
|
P110
|
Gravel fill of the greenroof (cum)
|
211.40
|
₽ 1,634.11
|
₽ 345,450.00
|
|
GRF
|
P110
|
Lightning protection current of the greenroof (kg)
|
845.60
|
₽ 1,120.80
|
₽ 947,750.00
|
|
GRF
|
P110
|
Masterfibe of the greenroof (cum)
|
84.56
|
₽ 146,208.02
|
₽ 12,363,350.00
|
|
GRF
|
P110
|
Paving of the greenroof (sqm)
|
2,114.00
|
₽ 4,185.81
|
₽ 8,848,800.00
|
|
GRF
|
P110
|
Plant soil fill of the greenroof (cum)
|
528.50
|
₽ 1,122.61
|
₽ 593,300.00
|
|
GRF
|
P110
|
PLANTER Geo of the greenroof (sqm)
|
4,228.00
|
₽ 1,603.48
|
₽ 6,779,494.67
|
|
GRF
|
P110
|
Rebar of the slabs (kg)
|
76,104.00
|
₽ 574.04
|
₽ 43,686,450.00
|
|
GRF
|
P110
|
Rebar of the walls, columns (kg)
|
11,161.92
|
₽ 574.15
|
₽ 6,408,642.00
|
|
GRF
|
P110
|
Sand fill of the greenroof (cum)
|
211.40
|
₽ 1,134.11
|
₽ 239,750.00
|
|
GRF
|
P110
|
Screed of the greenroof (cum)
|
169.12
|
₽ 1,646.35
|
₽ 278,430.00
|
|
GRF
|
P110
|
Soil fill of the greenroof (cum)
|
422.80
|
₽ 1,125.24
|
₽ 475,750.00
|
|
GRF
|
P110
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
528.50
|
₽ 1,452.66
|
₽ 767,731.00
|
|
GRF
|
P110
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,114.00
|
₽ 1,608.81
|
₽ 3,401,022.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P111
|
|
91,851.36
|
₽ 972.11
|
₽ 89,290,058.57
|
|
GRF
|
P111
|
Asphalt concrete finishing of the greenroof (cum)
|
92.65
|
₽ 11,211.01
|
₽ 1,038,700.00
|
|
GRF
|
P111
|
Asphalt concrete of the greenroof (cum)
|
240.89
|
₽ 11,199.93
|
₽ 2,697,950.00
|
|
GRF
|
P111
|
CARBON SOLID 500 of the greenroof (cum)
|
185.30
|
₽ 1,795.63
|
₽ 332,730.00
|
|
GRF
|
P111
|
Clay pebbles of the greenroof (cum)
|
46.33
|
₽ 2,158.66
|
₽ 100,000.00
|
|
GRF
|
P111
|
Concrete of greenroof (cum)
|
296.48
|
₽ 6,953.18
|
₽ 2,061,480.00
|
|
GRF
|
P111
|
Concrete of the slabs (cum)
|
370.60
|
₽ 6,951.97
|
₽ 2,576,400.00
|
|
GRF
|
P111
|
Concrete of the walls, columns (cum)
|
48.92
|
₽ 6,968.94
|
₽ 340,915.20
|
|
GRF
|
P111
|
Formwork of the slabs (sqm)
|
1,853.00
|
₽ 1,436.08
|
₽ 2,661,050.00
|
|
GRF
|
P111
|
Formwork of the walls, columns (sqm)
|
329.09
|
₽ 1,438.27
|
₽ 473,323.20
|
|
GRF
|
P111
|
Geotextile of the greenroof (sqm)
|
1,853.00
|
₽ 1,286.08
|
₽ 2,383,100.00
|
|
GRF
|
P111
|
Gravel fill of the greenroof (cum)
|
185.30
|
₽ 1,623.04
|
₽ 300,750.00
|
|
GRF
|
P111
|
Lightning protection current of the greenroof (kg)
|
741.20
|
₽ 1,121.83
|
₽ 831,500.00
|
|
GRF
|
P111
|
Masterfibe of the greenroof (cum)
|
74.12
|
₽ 146,218.29
|
₽ 10,837,700.00
|
|
GRF
|
P111
|
Paving of the greenroof (sqm)
|
1,853.00
|
₽ 4,186.08
|
₽ 7,756,800.00
|
|
GRF
|
P111
|
Plant soil fill of the greenroof (cum)
|
463.25
|
₽ 1,122.07
|
₽ 519,800.00
|
|
GRF
|
P111
|
PLANTER Geo of the greenroof (sqm)
|
3,706.00
|
₽ 1,603.74
|
₽ 5,943,472.67
|
|
GRF
|
P111
|
Rebar of the slabs (kg)
|
66,708.00
|
₽ 574.04
|
₽ 38,293,050.00
|
|
GRF
|
P111
|
Rebar of the walls, columns (kg)
|
9,783.84
|
₽ 574.23
|
₽ 5,618,184.00
|
|
GRF
|
P111
|
Sand fill of the greenroof (cum)
|
185.30
|
₽ 1,123.04
|
₽ 208,100.00
|
|
GRF
|
P111
|
Screed of the greenroof (cum)
|
148.24
|
₽ 1,635.59
|
₽ 242,460.00
|
|
GRF
|
P111
|
Soil fill of the greenroof (cum)
|
370.60
|
₽ 1,123.04
|
₽ 416,200.00
|
|
GRF
|
P111
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
463.25
|
₽ 1,456.61
|
₽ 674,774.50
|
|
GRF
|
P111
|
Техноэласт ЭПП of the greenroof (sqm)
|
1,853.00
|
₽ 1,609.08
|
₽ 2,981,619.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P201
|
|
118,222.07
|
₽ 971.97
|
₽ 114,908,335.50
|
|
GRF
|
P201
|
Asphalt concrete finishing of the greenroof (cum)
|
119.25
|
₽ 11,192.45
|
₽ 1,334,700.00
|
|
GRF
|
P201
|
Asphalt concrete of the greenroof (cum)
|
310.05
|
₽ 11,196.90
|
₽ 3,471,600.00
|
|
GRF
|
P201
|
CARBON SOLID 500 of the greenroof (cum)
|
238.50
|
₽ 1,788.68
|
₽ 426,600.00
|
|
GRF
|
P201
|
Clay pebbles of the greenroof (cum)
|
59.62
|
₽ 2,138.36
|
₽ 127,500.00
|
|
GRF
|
P201
|
Concrete of greenroof (cum)
|
381.60
|
₽ 6,953.22
|
₽ 2,653,350.00
|
|
GRF
|
P201
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
GRF
|
P201
|
Concrete of the walls, columns (cum)
|
62.96
|
₽ 7,000.57
|
₽ 440,784.00
|
|
GRF
|
P201
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
GRF
|
P201
|
Formwork of the walls, columns (sqm)
|
423.58
|
₽ 1,440.22
|
₽ 610,044.00
|
|
GRF
|
P201
|
Geotextile of the greenroof (sqm)
|
2,385.00
|
₽ 1,285.60
|
₽ 3,066,150.00
|
|
GRF
|
P201
|
Gravel fill of the greenroof (cum)
|
238.50
|
₽ 1,626.42
|
₽ 387,900.00
|
|
GRF
|
P201
|
Lightning protection current of the greenroof (kg)
|
954.00
|
₽ 1,120.44
|
₽ 1,068,900.00
|
|
GRF
|
P201
|
Masterfibe of the greenroof (cum)
|
95.40
|
₽ 146,204.40
|
₽ 13,947,900.00
|
|
GRF
|
P201
|
Paving of the greenroof (sqm)
|
2,385.00
|
₽ 4,185.60
|
₽ 9,982,650.00
|
|
GRF
|
P201
|
Plant soil fill of the greenroof (cum)
|
596.25
|
₽ 1,119.25
|
₽ 667,350.00
|
|
GRF
|
P201
|
PLANTER Geo of the greenroof (sqm)
|
4,770.00
|
₽ 1,603.26
|
₽ 7,647,570.00
|
|
GRF
|
P201
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
GRF
|
P201
|
Rebar of the walls, columns (kg)
|
12,592.80
|
₽ 574.13
|
₽ 7,229,880.00
|
|
GRF
|
P201
|
Sand fill of the greenroof (cum)
|
238.50
|
₽ 1,126.42
|
₽ 268,650.00
|
|
GRF
|
P201
|
Screed of the greenroof (cum)
|
190.80
|
₽ 1,639.15
|
₽ 312,750.00
|
|
GRF
|
P201
|
Soil fill of the greenroof (cum)
|
477.00
|
₽ 1,120.44
|
₽ 534,450.00
|
|
GRF
|
P201
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
596.25
|
₽ 1,453.92
|
₽ 866,902.50
|
|
GRF
|
P201
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,385.00
|
₽ 1,608.60
|
₽ 3,836,505.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P202
|
|
118,222.07
|
₽ 971.97
|
₽ 114,908,335.50
|
|
GRF
|
P202
|
Asphalt concrete finishing of the greenroof (cum)
|
119.25
|
₽ 11,192.45
|
₽ 1,334,700.00
|
|
GRF
|
P202
|
Asphalt concrete of the greenroof (cum)
|
310.05
|
₽ 11,196.90
|
₽ 3,471,600.00
|
|
GRF
|
P202
|
CARBON SOLID 500 of the greenroof (cum)
|
238.50
|
₽ 1,788.68
|
₽ 426,600.00
|
|
GRF
|
P202
|
Clay pebbles of the greenroof (cum)
|
59.62
|
₽ 2,138.36
|
₽ 127,500.00
|
|
GRF
|
P202
|
Concrete of greenroof (cum)
|
381.60
|
₽ 6,953.22
|
₽ 2,653,350.00
|
|
GRF
|
P202
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
GRF
|
P202
|
Concrete of the walls, columns (cum)
|
62.96
|
₽ 7,000.57
|
₽ 440,784.00
|
|
GRF
|
P202
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
GRF
|
P202
|
Formwork of the walls, columns (sqm)
|
423.58
|
₽ 1,440.22
|
₽ 610,044.00
|
|
GRF
|
P202
|
Geotextile of the greenroof (sqm)
|
2,385.00
|
₽ 1,285.60
|
₽ 3,066,150.00
|
|
GRF
|
P202
|
Gravel fill of the greenroof (cum)
|
238.50
|
₽ 1,626.42
|
₽ 387,900.00
|
|
GRF
|
P202
|
Lightning protection current of the greenroof (kg)
|
954.00
|
₽ 1,120.44
|
₽ 1,068,900.00
|
|
GRF
|
P202
|
Masterfibe of the greenroof (cum)
|
95.40
|
₽ 146,204.40
|
₽ 13,947,900.00
|
|
GRF
|
P202
|
Paving of the greenroof (sqm)
|
2,385.00
|
₽ 4,185.60
|
₽ 9,982,650.00
|
|
GRF
|
P202
|
Plant soil fill of the greenroof (cum)
|
596.25
|
₽ 1,119.25
|
₽ 667,350.00
|
|
GRF
|
P202
|
PLANTER Geo of the greenroof (sqm)
|
4,770.00
|
₽ 1,603.26
|
₽ 7,647,570.00
|
|
GRF
|
P202
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
GRF
|
P202
|
Rebar of the walls, columns (kg)
|
12,592.80
|
₽ 574.13
|
₽ 7,229,880.00
|
|
GRF
|
P202
|
Sand fill of the greenroof (cum)
|
238.50
|
₽ 1,126.42
|
₽ 268,650.00
|
|
GRF
|
P202
|
Screed of the greenroof (cum)
|
190.80
|
₽ 1,639.15
|
₽ 312,750.00
|
|
GRF
|
P202
|
Soil fill of the greenroof (cum)
|
477.00
|
₽ 1,120.44
|
₽ 534,450.00
|
|
GRF
|
P202
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
596.25
|
₽ 1,453.92
|
₽ 866,902.50
|
|
GRF
|
P202
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,385.00
|
₽ 1,608.60
|
₽ 3,836,505.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P203
|
|
112,967.75
|
₽ 971.93
|
₽ 109,796,348.37
|
|
GRF
|
P203
|
Asphalt concrete finishing of the greenroof (cum)
|
113.95
|
₽ 11,200.53
|
₽ 1,276,300.00
|
|
GRF
|
P203
|
Asphalt concrete of the greenroof (cum)
|
296.27
|
₽ 11,190.81
|
₽ 3,315,500.00
|
|
GRF
|
P203
|
CARBON SOLID 500 of the greenroof (cum)
|
227.90
|
₽ 1,788.02
|
₽ 407,490.00
|
|
GRF
|
P203
|
Clay pebbles of the greenroof (cum)
|
56.98
|
₽ 2,144.80
|
₽ 122,200.00
|
|
GRF
|
P203
|
Concrete of greenroof (cum)
|
364.64
|
₽ 6,955.19
|
₽ 2,536,140.00
|
|
GRF
|
P203
|
Concrete of the slabs (cum)
|
455.80
|
₽ 6,952.06
|
₽ 3,168,750.00
|
|
GRF
|
P203
|
Concrete of the walls, columns (cum)
|
60.17
|
₽ 6,969.82
|
₽ 419,343.60
|
|
GRF
|
P203
|
Formwork of the slabs (sqm)
|
2,279.00
|
₽ 1,435.13
|
₽ 3,270,650.00
|
|
GRF
|
P203
|
Formwork of the walls, columns (sqm)
|
404.75
|
₽ 1,439.25
|
₽ 582,537.60
|
|
GRF
|
P203
|
Geotextile of the greenroof (sqm)
|
2,279.00
|
₽ 1,285.13
|
₽ 2,928,800.00
|
|
GRF
|
P203
|
Gravel fill of the greenroof (cum)
|
227.90
|
₽ 1,628.35
|
₽ 371,100.00
|
|
GRF
|
P203
|
Lightning protection current of the greenroof (kg)
|
911.60
|
₽ 1,122.09
|
₽ 1,022,900.00
|
|
GRF
|
P203
|
Masterfibe of the greenroof (cum)
|
91.16
|
₽ 146,220.93
|
₽ 13,329,500.00
|
|
GRF
|
P203
|
Paving of the greenroof (sqm)
|
2,279.00
|
₽ 4,185.13
|
₽ 9,537,900.00
|
|
GRF
|
P203
|
Plant soil fill of the greenroof (cum)
|
569.75
|
₽ 1,120.05
|
₽ 638,150.00
|
|
GRF
|
P203
|
PLANTER Geo of the greenroof (sqm)
|
4,558.00
|
₽ 1,602.79
|
₽ 7,305,524.67
|
|
GRF
|
P203
|
Rebar of the slabs (kg)
|
82,044.00
|
₽ 574.01
|
₽ 47,094,300.00
|
|
GRF
|
P203
|
Rebar of the walls, columns (kg)
|
12,033.12
|
₽ 574.22
|
₽ 6,909,612.00
|
|
GRF
|
P203
|
Sand fill of the greenroof (cum)
|
227.90
|
₽ 1,128.35
|
₽ 257,150.00
|
|
GRF
|
P203
|
Screed of the greenroof (cum)
|
182.32
|
₽ 1,640.69
|
₽ 299,130.00
|
|
GRF
|
P203
|
Soil fill of the greenroof (cum)
|
455.80
|
₽ 1,122.09
|
₽ 511,450.00
|
|
GRF
|
P203
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
569.75
|
₽ 1,451.52
|
₽ 827,003.50
|
|
GRF
|
P203
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,279.00
|
₽ 1,608.13
|
₽ 3,664,917.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P204
|
|
123,476.38
|
₽ 972.00
|
₽ 120,018,522.63
|
|
GRF
|
P204
|
Asphalt concrete finishing of the greenroof (cum)
|
124.55
|
₽ 11,200.72
|
₽ 1,395,050.00
|
|
GRF
|
P204
|
Asphalt concrete of the greenroof (cum)
|
323.83
|
₽ 11,193.68
|
₽ 3,624,850.00
|
|
GRF
|
P204
|
CARBON SOLID 500 of the greenroof (cum)
|
249.10
|
₽ 1,789.28
|
₽ 445,710.00
|
|
GRF
|
P204
|
Clay pebbles of the greenroof (cum)
|
62.28
|
₽ 2,146.93
|
₽ 133,700.00
|
|
GRF
|
P204
|
Concrete of greenroof (cum)
|
398.56
|
₽ 6,949.17
|
₽ 2,769,660.00
|
|
GRF
|
P204
|
Concrete of the slabs (cum)
|
498.20
|
₽ 6,949.62
|
₽ 3,462,300.00
|
|
GRF
|
P204
|
Concrete of the walls, columns (cum)
|
65.76
|
₽ 6,985.37
|
₽ 459,374.40
|
|
GRF
|
P204
|
Formwork of the slabs (sqm)
|
2,491.00
|
₽ 1,436.03
|
₽ 3,577,150.00
|
|
GRF
|
P204
|
Formwork of the walls, columns (sqm)
|
442.40
|
₽ 1,441.11
|
₽ 637,550.40
|
|
GRF
|
P204
|
Geotextile of the greenroof (sqm)
|
2,491.00
|
₽ 1,286.03
|
₽ 3,203,500.00
|
|
GRF
|
P204
|
Gravel fill of the greenroof (cum)
|
249.10
|
₽ 1,624.65
|
₽ 404,700.00
|
|
GRF
|
P204
|
Lightning protection current of the greenroof (kg)
|
996.40
|
₽ 1,118.93
|
₽ 1,114,900.00
|
|
GRF
|
P204
|
Masterfibe of the greenroof (cum)
|
99.64
|
₽ 146,189.28
|
₽ 14,566,300.00
|
|
GRF
|
P204
|
Paving of the greenroof (sqm)
|
2,491.00
|
₽ 4,186.03
|
₽ 10,427,400.00
|
|
GRF
|
P204
|
Plant soil fill of the greenroof (cum)
|
622.75
|
₽ 1,123.08
|
₽ 699,400.00
|
|
GRF
|
P204
|
PLANTER Geo of the greenroof (sqm)
|
4,982.00
|
₽ 1,603.70
|
₽ 7,989,615.33
|
|
GRF
|
P204
|
Rebar of the slabs (kg)
|
89,676.00
|
₽ 574.04
|
₽ 51,477,300.00
|
|
GRF
|
P204
|
Rebar of the walls, columns (kg)
|
13,152.48
|
₽ 574.20
|
₽ 7,552,098.00
|
|
GRF
|
P204
|
Sand fill of the greenroof (cum)
|
249.10
|
₽ 1,124.65
|
₽ 280,150.00
|
|
GRF
|
P204
|
Screed of the greenroof (cum)
|
199.28
|
₽ 1,637.75
|
₽ 326,370.00
|
|
GRF
|
P204
|
Soil fill of the greenroof (cum)
|
498.20
|
₽ 1,118.93
|
₽ 557,450.00
|
|
GRF
|
P204
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
622.75
|
₽ 1,454.68
|
₽ 905,901.50
|
|
GRF
|
P204
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,491.00
|
₽ 1,609.03
|
₽ 4,008,093.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P301
|
|
118,222.07
|
₽ 971.97
|
₽ 114,908,335.50
|
|
GRF
|
P301
|
Asphalt concrete finishing of the greenroof (cum)
|
119.25
|
₽ 11,192.45
|
₽ 1,334,700.00
|
|
GRF
|
P301
|
Asphalt concrete of the greenroof (cum)
|
310.05
|
₽ 11,196.90
|
₽ 3,471,600.00
|
|
GRF
|
P301
|
CARBON SOLID 500 of the greenroof (cum)
|
238.50
|
₽ 1,788.68
|
₽ 426,600.00
|
|
GRF
|
P301
|
Clay pebbles of the greenroof (cum)
|
59.62
|
₽ 2,138.36
|
₽ 127,500.00
|
|
GRF
|
P301
|
Concrete of greenroof (cum)
|
381.60
|
₽ 6,953.22
|
₽ 2,653,350.00
|
|
GRF
|
P301
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
GRF
|
P301
|
Concrete of the walls, columns (cum)
|
62.96
|
₽ 7,000.57
|
₽ 440,784.00
|
|
GRF
|
P301
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
GRF
|
P301
|
Formwork of the walls, columns (sqm)
|
423.58
|
₽ 1,440.22
|
₽ 610,044.00
|
|
GRF
|
P301
|
Geotextile of the greenroof (sqm)
|
2,385.00
|
₽ 1,285.60
|
₽ 3,066,150.00
|
|
GRF
|
P301
|
Gravel fill of the greenroof (cum)
|
238.50
|
₽ 1,626.42
|
₽ 387,900.00
|
|
GRF
|
P301
|
Lightning protection current of the greenroof (kg)
|
954.00
|
₽ 1,120.44
|
₽ 1,068,900.00
|
|
GRF
|
P301
|
Masterfibe of the greenroof (cum)
|
95.40
|
₽ 146,204.40
|
₽ 13,947,900.00
|
|
GRF
|
P301
|
Paving of the greenroof (sqm)
|
2,385.00
|
₽ 4,185.60
|
₽ 9,982,650.00
|
|
GRF
|
P301
|
Plant soil fill of the greenroof (cum)
|
596.25
|
₽ 1,119.25
|
₽ 667,350.00
|
|
GRF
|
P301
|
PLANTER Geo of the greenroof (sqm)
|
4,770.00
|
₽ 1,603.26
|
₽ 7,647,570.00
|
|
GRF
|
P301
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
GRF
|
P301
|
Rebar of the walls, columns (kg)
|
12,592.80
|
₽ 574.13
|
₽ 7,229,880.00
|
|
GRF
|
P301
|
Sand fill of the greenroof (cum)
|
238.50
|
₽ 1,126.42
|
₽ 268,650.00
|
|
GRF
|
P301
|
Screed of the greenroof (cum)
|
190.80
|
₽ 1,639.15
|
₽ 312,750.00
|
|
GRF
|
P301
|
Soil fill of the greenroof (cum)
|
477.00
|
₽ 1,120.44
|
₽ 534,450.00
|
|
GRF
|
P301
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
596.25
|
₽ 1,453.92
|
₽ 866,902.50
|
|
GRF
|
P301
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,385.00
|
₽ 1,608.60
|
₽ 3,836,505.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P302
|
|
118,222.07
|
₽ 971.97
|
₽ 114,908,335.50
|
|
GRF
|
P302
|
Asphalt concrete finishing of the greenroof (cum)
|
119.25
|
₽ 11,192.45
|
₽ 1,334,700.00
|
|
GRF
|
P302
|
Asphalt concrete of the greenroof (cum)
|
310.05
|
₽ 11,196.90
|
₽ 3,471,600.00
|
|
GRF
|
P302
|
CARBON SOLID 500 of the greenroof (cum)
|
238.50
|
₽ 1,788.68
|
₽ 426,600.00
|
|
GRF
|
P302
|
Clay pebbles of the greenroof (cum)
|
59.62
|
₽ 2,138.36
|
₽ 127,500.00
|
|
GRF
|
P302
|
Concrete of greenroof (cum)
|
381.60
|
₽ 6,953.22
|
₽ 2,653,350.00
|
|
GRF
|
P302
|
Concrete of the slabs (cum)
|
477.00
|
₽ 6,953.77
|
₽ 3,316,950.00
|
|
GRF
|
P302
|
Concrete of the walls, columns (cum)
|
62.96
|
₽ 7,000.57
|
₽ 440,784.00
|
|
GRF
|
P302
|
Formwork of the slabs (sqm)
|
2,385.00
|
₽ 1,435.60
|
₽ 3,423,900.00
|
|
GRF
|
P302
|
Formwork of the walls, columns (sqm)
|
423.58
|
₽ 1,440.22
|
₽ 610,044.00
|
|
GRF
|
P302
|
Geotextile of the greenroof (sqm)
|
2,385.00
|
₽ 1,285.60
|
₽ 3,066,150.00
|
|
GRF
|
P302
|
Gravel fill of the greenroof (cum)
|
238.50
|
₽ 1,626.42
|
₽ 387,900.00
|
|
GRF
|
P302
|
Lightning protection current of the greenroof (kg)
|
954.00
|
₽ 1,120.44
|
₽ 1,068,900.00
|
|
GRF
|
P302
|
Masterfibe of the greenroof (cum)
|
95.40
|
₽ 146,204.40
|
₽ 13,947,900.00
|
|
GRF
|
P302
|
Paving of the greenroof (sqm)
|
2,385.00
|
₽ 4,185.60
|
₽ 9,982,650.00
|
|
GRF
|
P302
|
Plant soil fill of the greenroof (cum)
|
596.25
|
₽ 1,119.25
|
₽ 667,350.00
|
|
GRF
|
P302
|
PLANTER Geo of the greenroof (sqm)
|
4,770.00
|
₽ 1,603.26
|
₽ 7,647,570.00
|
|
GRF
|
P302
|
Rebar of the slabs (kg)
|
85,860.00
|
₽ 574.02
|
₽ 49,285,350.00
|
|
GRF
|
P302
|
Rebar of the walls, columns (kg)
|
12,592.80
|
₽ 574.13
|
₽ 7,229,880.00
|
|
GRF
|
P302
|
Sand fill of the greenroof (cum)
|
238.50
|
₽ 1,126.42
|
₽ 268,650.00
|
|
GRF
|
P302
|
Screed of the greenroof (cum)
|
190.80
|
₽ 1,639.15
|
₽ 312,750.00
|
|
GRF
|
P302
|
Soil fill of the greenroof (cum)
|
477.00
|
₽ 1,120.44
|
₽ 534,450.00
|
|
GRF
|
P302
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
596.25
|
₽ 1,453.92
|
₽ 866,902.50
|
|
GRF
|
P302
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,385.00
|
₽ 1,608.60
|
₽ 3,836,505.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P303
|
|
112,967.75
|
₽ 971.93
|
₽ 109,796,348.37
|
|
GRF
|
P303
|
Asphalt concrete finishing of the greenroof (cum)
|
113.95
|
₽ 11,200.53
|
₽ 1,276,300.00
|
|
GRF
|
P303
|
Asphalt concrete of the greenroof (cum)
|
296.27
|
₽ 11,190.81
|
₽ 3,315,500.00
|
|
GRF
|
P303
|
CARBON SOLID 500 of the greenroof (cum)
|
227.90
|
₽ 1,788.02
|
₽ 407,490.00
|
|
GRF
|
P303
|
Clay pebbles of the greenroof (cum)
|
56.98
|
₽ 2,144.80
|
₽ 122,200.00
|
|
GRF
|
P303
|
Concrete of greenroof (cum)
|
364.64
|
₽ 6,955.19
|
₽ 2,536,140.00
|
|
GRF
|
P303
|
Concrete of the slabs (cum)
|
455.80
|
₽ 6,952.06
|
₽ 3,168,750.00
|
|
GRF
|
P303
|
Concrete of the walls, columns (cum)
|
60.17
|
₽ 6,969.82
|
₽ 419,343.60
|
|
GRF
|
P303
|
Formwork of the slabs (sqm)
|
2,279.00
|
₽ 1,435.13
|
₽ 3,270,650.00
|
|
GRF
|
P303
|
Formwork of the walls, columns (sqm)
|
404.75
|
₽ 1,439.25
|
₽ 582,537.60
|
|
GRF
|
P303
|
Geotextile of the greenroof (sqm)
|
2,279.00
|
₽ 1,285.13
|
₽ 2,928,800.00
|
|
GRF
|
P303
|
Gravel fill of the greenroof (cum)
|
227.90
|
₽ 1,628.35
|
₽ 371,100.00
|
|
GRF
|
P303
|
Lightning protection current of the greenroof (kg)
|
911.60
|
₽ 1,122.09
|
₽ 1,022,900.00
|
|
GRF
|
P303
|
Masterfibe of the greenroof (cum)
|
91.16
|
₽ 146,220.93
|
₽ 13,329,500.00
|
|
GRF
|
P303
|
Paving of the greenroof (sqm)
|
2,279.00
|
₽ 4,185.13
|
₽ 9,537,900.00
|
|
GRF
|
P303
|
Plant soil fill of the greenroof (cum)
|
569.75
|
₽ 1,120.05
|
₽ 638,150.00
|
|
GRF
|
P303
|
PLANTER Geo of the greenroof (sqm)
|
4,558.00
|
₽ 1,602.79
|
₽ 7,305,524.67
|
|
GRF
|
P303
|
Rebar of the slabs (kg)
|
82,044.00
|
₽ 574.01
|
₽ 47,094,300.00
|
|
GRF
|
P303
|
Rebar of the walls, columns (kg)
|
12,033.12
|
₽ 574.22
|
₽ 6,909,612.00
|
|
GRF
|
P303
|
Sand fill of the greenroof (cum)
|
227.90
|
₽ 1,128.35
|
₽ 257,150.00
|
|
GRF
|
P303
|
Screed of the greenroof (cum)
|
182.32
|
₽ 1,640.69
|
₽ 299,130.00
|
|
GRF
|
P303
|
Soil fill of the greenroof (cum)
|
455.80
|
₽ 1,122.09
|
₽ 511,450.00
|
|
GRF
|
P303
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
569.75
|
₽ 1,451.52
|
₽ 827,003.50
|
|
GRF
|
P303
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,279.00
|
₽ 1,608.13
|
₽ 3,664,917.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
GRF
|
P304
|
|
123,476.38
|
₽ 972.00
|
₽ 120,018,522.63
|
|
GRF
|
P304
|
Asphalt concrete finishing of the greenroof (cum)
|
124.55
|
₽ 11,200.72
|
₽ 1,395,050.00
|
|
GRF
|
P304
|
Asphalt concrete of the greenroof (cum)
|
323.83
|
₽ 11,193.68
|
₽ 3,624,850.00
|
|
GRF
|
P304
|
CARBON SOLID 500 of the greenroof (cum)
|
249.10
|
₽ 1,789.28
|
₽ 445,710.00
|
|
GRF
|
P304
|
Clay pebbles of the greenroof (cum)
|
62.28
|
₽ 2,146.93
|
₽ 133,700.00
|
|
GRF
|
P304
|
Concrete of greenroof (cum)
|
398.56
|
₽ 6,949.17
|
₽ 2,769,660.00
|
|
GRF
|
P304
|
Concrete of the slabs (cum)
|
498.20
|
₽ 6,949.62
|
₽ 3,462,300.00
|
|
GRF
|
P304
|
Concrete of the walls, columns (cum)
|
65.76
|
₽ 6,985.37
|
₽ 459,374.40
|
|
GRF
|
P304
|
Formwork of the slabs (sqm)
|
2,491.00
|
₽ 1,436.03
|
₽ 3,577,150.00
|
|
GRF
|
P304
|
Formwork of the walls, columns (sqm)
|
442.40
|
₽ 1,441.11
|
₽ 637,550.40
|
|
GRF
|
P304
|
Geotextile of the greenroof (sqm)
|
2,491.00
|
₽ 1,286.03
|
₽ 3,203,500.00
|
|
GRF
|
P304
|
Gravel fill of the greenroof (cum)
|
249.10
|
₽ 1,624.65
|
₽ 404,700.00
|
|
GRF
|
P304
|
Lightning protection current of the greenroof (kg)
|
996.40
|
₽ 1,118.93
|
₽ 1,114,900.00
|
|
GRF
|
P304
|
Masterfibe of the greenroof (cum)
|
99.64
|
₽ 146,189.28
|
₽ 14,566,300.00
|
|
GRF
|
P304
|
Paving of the greenroof (sqm)
|
2,491.00
|
₽ 4,186.03
|
₽ 10,427,400.00
|
|
GRF
|
P304
|
Plant soil fill of the greenroof (cum)
|
622.75
|
₽ 1,123.08
|
₽ 699,400.00
|
|
GRF
|
P304
|
PLANTER Geo of the greenroof (sqm)
|
4,982.00
|
₽ 1,603.70
|
₽ 7,989,615.33
|
|
GRF
|
P304
|
Rebar of the slabs (kg)
|
89,676.00
|
₽ 574.04
|
₽ 51,477,300.00
|
|
GRF
|
P304
|
Rebar of the walls, columns (kg)
|
13,152.48
|
₽ 574.20
|
₽ 7,552,098.00
|
|
GRF
|
P304
|
Sand fill of the greenroof (cum)
|
249.10
|
₽ 1,124.65
|
₽ 280,150.00
|
|
GRF
|
P304
|
Screed of the greenroof (cum)
|
199.28
|
₽ 1,637.75
|
₽ 326,370.00
|
|
GRF
|
P304
|
Soil fill of the greenroof (cum)
|
498.20
|
₽ 1,118.93
|
₽ 557,450.00
|
|
GRF
|
P304
|
ТехноНИКОЛЬ №01 of the greenroof (kg)
|
622.75
|
₽ 1,454.68
|
₽ 905,901.50
|
|
GRF
|
P304
|
Техноэласт ЭПП of the greenroof (sqm)
|
2,491.00
|
₽ 1,609.03
|
₽ 4,008,093.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
|
|
262,757.09
|
₽ 8,951.88
|
₽ 2,352,170,904.00
|
|
PT
|
Benua Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Benua Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Benua Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Tihoretskiy Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Tihoretskiy Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Tihoretskiy Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Kurchatov Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Kurchatov Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Kurchatov Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Politekh Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Politekh Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Politekh Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Atom Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Atom Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Atom Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
RTK Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
RTK Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
RTK Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P101
|
|
1,175.33
|
₽ 8,955.65
|
₽ 10,525,824.00
|
|
PT
|
P101
|
AAC (Wet) concrete (cum)
|
587.66
|
₽ 8,955.65
|
₽ 5,262,912.00
|
|
PT
|
P101
|
AAC concrete (cum)
|
587.66
|
₽ 8,955.65
|
₽ 5,262,912.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P102
|
|
1,521.43
|
₽ 8,953.97
|
₽ 13,622,856.00
|
|
PT
|
P102
|
AAC (Wet) concrete (cum)
|
760.72
|
₽ 8,953.97
|
₽ 6,811,428.00
|
|
PT
|
P102
|
AAC concrete (cum)
|
760.72
|
₽ 8,953.97
|
₽ 6,811,428.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P103
|
|
1,812.89
|
₽ 8,953.51
|
₽ 16,231,704.00
|
|
PT
|
P103
|
AAC (Wet) concrete (cum)
|
906.44
|
₽ 8,953.51
|
₽ 8,115,852.00
|
|
PT
|
P103
|
AAC concrete (cum)
|
906.44
|
₽ 8,953.51
|
₽ 8,115,852.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P104
|
|
1,444.61
|
₽ 8,949.05
|
₽ 12,927,864.00
|
|
PT
|
P104
|
AAC (Wet) concrete (cum)
|
722.30
|
₽ 8,949.05
|
₽ 6,463,932.00
|
|
PT
|
P104
|
AAC concrete (cum)
|
722.30
|
₽ 8,949.05
|
₽ 6,463,932.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P105
|
|
1,175.33
|
₽ 8,955.65
|
₽ 10,525,824.00
|
|
PT
|
P105
|
AAC (Wet) concrete (cum)
|
587.66
|
₽ 8,955.65
|
₽ 5,262,912.00
|
|
PT
|
P105
|
AAC concrete (cum)
|
587.66
|
₽ 8,955.65
|
₽ 5,262,912.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P106
|
|
1,343.23
|
₽ 8,950.10
|
₽ 12,022,056.00
|
|
PT
|
P106
|
AAC (Wet) concrete (cum)
|
671.62
|
₽ 8,950.10
|
₽ 6,011,028.00
|
|
PT
|
P106
|
AAC concrete (cum)
|
671.62
|
₽ 8,950.10
|
₽ 6,011,028.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P107
|
|
1,260.86
|
₽ 8,957.44
|
₽ 11,294,112.00
|
|
PT
|
P107
|
AAC (Wet) concrete (cum)
|
630.43
|
₽ 8,957.44
|
₽ 5,647,056.00
|
|
PT
|
P107
|
AAC concrete (cum)
|
630.43
|
₽ 8,957.44
|
₽ 5,647,056.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P108
|
|
1,551.53
|
₽ 8,956.73
|
₽ 13,896,624.00
|
|
PT
|
P108
|
AAC (Wet) concrete (cum)
|
775.76
|
₽ 8,956.73
|
₽ 6,948,312.00
|
|
PT
|
P108
|
AAC concrete (cum)
|
775.76
|
₽ 8,956.73
|
₽ 6,948,312.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P109
|
|
1,511.14
|
₽ 8,955.70
|
₽ 13,533,288.00
|
|
PT
|
P109
|
AAC (Wet) concrete (cum)
|
755.57
|
₽ 8,955.70
|
₽ 6,766,644.00
|
|
PT
|
P109
|
AAC concrete (cum)
|
755.57
|
₽ 8,955.70
|
₽ 6,766,644.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P110
|
|
1,674.29
|
₽ 8,951.81
|
₽ 14,987,904.00
|
|
PT
|
P110
|
AAC (Wet) concrete (cum)
|
837.14
|
₽ 8,951.81
|
₽ 7,493,952.00
|
|
PT
|
P110
|
AAC concrete (cum)
|
837.14
|
₽ 8,951.81
|
₽ 7,493,952.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P111
|
|
1,467.58
|
₽ 8,954.23
|
₽ 13,141,008.00
|
|
PT
|
P111
|
AAC (Wet) concrete (cum)
|
733.79
|
₽ 8,954.23
|
₽ 6,570,504.00
|
|
PT
|
P111
|
AAC concrete (cum)
|
733.79
|
₽ 8,954.23
|
₽ 6,570,504.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Akadem Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Akadem Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Akadem Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Nauki Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Nauki Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Nauki Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P201
|
|
1,888.92
|
₽ 8,949.75
|
₽ 16,905,360.00
|
|
PT
|
P201
|
AAC (Wet) concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
PT
|
P201
|
AAC concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P202
|
|
1,888.92
|
₽ 8,949.75
|
₽ 16,905,360.00
|
|
PT
|
P202
|
AAC (Wet) concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
PT
|
P202
|
AAC concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P203
|
|
1,804.97
|
₽ 8,953.70
|
₽ 16,161,144.00
|
|
PT
|
P203
|
AAC (Wet) concrete (cum)
|
902.48
|
₽ 8,953.70
|
₽ 8,080,572.00
|
|
PT
|
P203
|
AAC concrete (cum)
|
902.48
|
₽ 8,953.70
|
₽ 8,080,572.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P204
|
|
1,972.87
|
₽ 8,951.91
|
₽ 17,660,976.00
|
|
PT
|
P204
|
AAC (Wet) concrete (cum)
|
986.44
|
₽ 8,951.91
|
₽ 8,830,488.00
|
|
PT
|
P204
|
AAC concrete (cum)
|
986.44
|
₽ 8,951.91
|
₽ 8,830,488.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
CHapaev Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
CHapaev Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
CHapaev Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
Budenniy Tower
|
|
23,170.75
|
₽ 8,951.79
|
₽ 207,419,616.00
|
|
PT
|
Budenniy Tower
|
AAC (Wet) concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
PT
|
Budenniy Tower
|
AAC concrete (cum)
|
11,585.38
|
₽ 8,951.79
|
₽ 103,709,808.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P301
|
|
1,888.92
|
₽ 8,949.75
|
₽ 16,905,360.00
|
|
PT
|
P301
|
AAC (Wet) concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
PT
|
P301
|
AAC concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P302
|
|
1,888.92
|
₽ 8,949.75
|
₽ 16,905,360.00
|
|
PT
|
P302
|
AAC (Wet) concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
PT
|
P302
|
AAC concrete (cum)
|
944.46
|
₽ 8,949.75
|
₽ 8,452,680.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P303
|
|
1,804.97
|
₽ 8,953.70
|
₽ 16,161,144.00
|
|
PT
|
P303
|
AAC (Wet) concrete (cum)
|
902.48
|
₽ 8,953.70
|
₽ 8,080,572.00
|
|
PT
|
P303
|
AAC concrete (cum)
|
902.48
|
₽ 8,953.70
|
₽ 8,080,572.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PT
|
P304
|
|
1,972.87
|
₽ 8,951.91
|
₽ 17,660,976.00
|
|
PT
|
P304
|
AAC (Wet) concrete (cum)
|
986.44
|
₽ 8,951.91
|
₽ 8,830,488.00
|
|
PT
|
P304
|
AAC concrete (cum)
|
986.44
|
₽ 8,951.91
|
₽ 8,830,488.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
|
|
583,584.06
|
₽ 717.53
|
₽ 418,739,651.20
|
|
RF
|
Benua Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Benua Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Benua Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Benua Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Benua Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Benua Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Benua Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Benua Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Benua Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Benua Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Benua Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Benua Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Benua Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Benua Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Benua Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Benua Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Tihoretskiy Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Tihoretskiy Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Tihoretskiy Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Tihoretskiy Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Tihoretskiy Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Tihoretskiy Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Tihoretskiy Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Tihoretskiy Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Tihoretskiy Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Tihoretskiy Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Tihoretskiy Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Tihoretskiy Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Tihoretskiy Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Tihoretskiy Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Tihoretskiy Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Tihoretskiy Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Kurchatov Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Kurchatov Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Kurchatov Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Kurchatov Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Kurchatov Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Kurchatov Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Kurchatov Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Kurchatov Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Kurchatov Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Kurchatov Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Kurchatov Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Kurchatov Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Kurchatov Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Kurchatov Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Kurchatov Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Kurchatov Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Politekh Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Politekh Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Politekh Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Politekh Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Politekh Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Politekh Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Politekh Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Politekh Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Politekh Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Politekh Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Politekh Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Politekh Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Politekh Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Politekh Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Politekh Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Politekh Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Atom Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Atom Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Atom Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Atom Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Atom Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Atom Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Atom Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Atom Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Atom Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Atom Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Atom Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Atom Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Atom Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Atom Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Atom Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Atom Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
RTK Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
RTK Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
RTK Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
RTK Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
RTK Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
RTK Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
RTK Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
RTK Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
RTK Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
RTK Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
RTK Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
RTK Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
RTK Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
RTK Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
RTK Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
RTK Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Akadem Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Akadem Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Akadem Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Akadem Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Akadem Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Akadem Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Akadem Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Akadem Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Akadem Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Akadem Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Akadem Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Akadem Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Akadem Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Akadem Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Akadem Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Akadem Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Nauki Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Nauki Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Nauki Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Nauki Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Nauki Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Nauki Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Nauki Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Nauki Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Nauki Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Nauki Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Nauki Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Nauki Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Nauki Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Nauki Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Nauki Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Nauki Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
CHapaev Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
CHapaev Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
CHapaev Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
CHapaev Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
CHapaev Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
CHapaev Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
CHapaev Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
CHapaev Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
CHapaev Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
CHapaev Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
CHapaev Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
CHapaev Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
CHapaev Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
CHapaev Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
CHapaev Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
CHapaev Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
RF
|
Budenniy Tower
|
|
58,358.41
|
₽ 717.53
|
₽ 41,873,965.12
|
|
RF
|
Budenniy Tower
|
CARBON PROF 300 of the roof (cum)
|
195.04
|
₽ 1,769.68
|
₽ 345,157.92
|
|
RF
|
Budenniy Tower
|
Clay pebbles of the roof (cum)
|
60.95
|
₽ 2,150.12
|
₽ 131,050.00
|
|
RF
|
Budenniy Tower
|
Concrete of the slabs (cum)
|
243.80
|
₽ 6,957.34
|
₽ 1,696,200.00
|
|
RF
|
Budenniy Tower
|
Concrete of the walls, columns (cum)
|
32.18
|
₽ 6,992.80
|
₽ 225,039.60
|
|
RF
|
Budenniy Tower
|
Formwork of the slabs (sqm)
|
1,219.00
|
₽ 1,435.23
|
₽ 1,749,550.00
|
|
RF
|
Budenniy Tower
|
Formwork of the walls, columns (sqm)
|
216.49
|
₽ 1,441.72
|
₽ 312,123.60
|
|
RF
|
Budenniy Tower
|
Lightning protection of the roof (kg)
|
487.60
|
₽ 1,119.67
|
₽ 545,950.00
|
|
RF
|
Budenniy Tower
|
Polyethylene 200 mkm of the roof (sqm)
|
1,219.00
|
₽ 1,215.23
|
₽ 1,481,370.00
|
|
RF
|
Budenniy Tower
|
Rebar of the slabs (kg)
|
43,884.00
|
₽ 574.05
|
₽ 25,191,600.00
|
|
RF
|
Budenniy Tower
|
Rebar of the walls, columns (kg)
|
6,436.32
|
₽ 574.31
|
₽ 3,696,432.00
|
|
RF
|
Budenniy Tower
|
Screed of the roof (cum)
|
97.52
|
₽ 1,659.97
|
₽ 161,880.00
|
|
RF
|
Budenniy Tower
|
Биполь ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Budenniy Tower
|
ТехноНИКОЛЬ №01 of the roof (kg)
|
609.50
|
₽ 1,456.65
|
₽ 887,827.00
|
|
RF
|
Budenniy Tower
|
Техноэласт ЭКП of the roof (sqm)
|
1,219.00
|
₽ 1,431.23
|
₽ 1,744,674.00
|
|
RF
|
Budenniy Tower
|
Техноэласт ЭПП of the roof (sqm)
|
1,219.00
|
₽ 1,608.23
|
₽ 1,960,437.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
|
|
376,377.96
|
₽ 5,447.95
|
₽ 2,050,488,750.00
|
|
FC
|
Benua Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Benua Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Benua Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Benua Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Benua Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Benua Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Benua Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Tihoretskiy Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Tihoretskiy Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Tihoretskiy Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Tihoretskiy Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Tihoretskiy Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Tihoretskiy Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Tihoretskiy Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Kurchatov Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Kurchatov Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Kurchatov Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Kurchatov Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Kurchatov Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Kurchatov Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Kurchatov Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Politekh Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Politekh Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Politekh Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Politekh Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Politekh Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Politekh Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Politekh Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Atom Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Atom Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Atom Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Atom Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Atom Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Atom Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Atom Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
RTK Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
RTK Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
RTK Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
RTK Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
RTK Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
RTK Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
RTK Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P101
|
|
199.92
|
₽ 5,084.03
|
₽ 1,016,400.00
|
|
FC
|
P101
|
AAC concrete of the facade (cum)
|
16.80
|
₽ 9,089.29
|
₽ 152,700.00
|
|
FC
|
P101
|
Finishing of the facade (sqm)
|
84.00
|
₽ 2,705.36
|
₽ 227,250.00
|
|
FC
|
P101
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
6.72
|
₽ 27,075.89
|
₽ 181,950.00
|
|
FC
|
P101
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
8.40
|
₽ 27,053.57
|
₽ 227,250.00
|
|
FC
|
P101
|
Steel subsystem of the facade (sqm)
|
84.00
|
₽ 2,705.36
|
₽ 227,250.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P102
|
|
635.46
|
₽ 5,050.04
|
₽ 3,209,100.00
|
|
FC
|
P102
|
AAC concrete of the facade (cum)
|
53.40
|
₽ 8,991.57
|
₽ 480,150.00
|
|
FC
|
P102
|
Finishing of the facade (sqm)
|
267.00
|
₽ 2,688.20
|
₽ 717,750.00
|
|
FC
|
P102
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
21.36
|
₽ 26,952.25
|
₽ 575,700.00
|
|
FC
|
P102
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
26.70
|
₽ 26,882.02
|
₽ 717,750.00
|
|
FC
|
P102
|
Steel subsystem of the facade (sqm)
|
267.00
|
₽ 2,688.20
|
₽ 717,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P103
|
|
478.38
|
₽ 5,067.10
|
₽ 2,424,000.00
|
|
FC
|
P103
|
AAC concrete of the facade (cum)
|
40.20
|
₽ 9,022.39
|
₽ 362,700.00
|
|
FC
|
P103
|
Finishing of the facade (sqm)
|
201.00
|
₽ 2,697.76
|
₽ 542,250.00
|
|
FC
|
P103
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
16.08
|
₽ 27,024.25
|
₽ 434,550.00
|
|
FC
|
P103
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
20.10
|
₽ 26,977.61
|
₽ 542,250.00
|
|
FC
|
P103
|
Steel subsystem of the facade (sqm)
|
201.00
|
₽ 2,697.76
|
₽ 542,250.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P105
|
|
164.22
|
₽ 5,077.64
|
₽ 833,850.00
|
|
FC
|
P105
|
AAC concrete of the facade (cum)
|
13.80
|
₽ 9,195.65
|
₽ 126,900.00
|
|
FC
|
P105
|
Finishing of the facade (sqm)
|
69.00
|
₽ 2,689.13
|
₽ 185,550.00
|
|
FC
|
P105
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
5.52
|
₽ 27,228.26
|
₽ 150,300.00
|
|
FC
|
P105
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
6.90
|
₽ 26,891.30
|
₽ 185,550.00
|
|
FC
|
P105
|
Steel subsystem of the facade (sqm)
|
69.00
|
₽ 2,689.13
|
₽ 185,550.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P106
|
|
28.56
|
₽ 5,378.15
|
₽ 153,600.00
|
|
FC
|
P106
|
AAC concrete of the facade (cum)
|
2.40
|
₽ 9,937.50
|
₽ 23,850.00
|
|
FC
|
P106
|
Finishing of the facade (sqm)
|
12.00
|
₽ 2,875.00
|
₽ 34,500.00
|
|
FC
|
P106
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
0.96
|
₽ 27,343.75
|
₽ 26,250.00
|
|
FC
|
P106
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1.20
|
₽ 28,750.00
|
₽ 34,500.00
|
|
FC
|
P106
|
Steel subsystem of the facade (sqm)
|
12.00
|
₽ 2,875.00
|
₽ 34,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P107
|
|
421.26
|
₽ 5,054.12
|
₽ 2,129,100.00
|
|
FC
|
P107
|
AAC concrete of the facade (cum)
|
35.40
|
₽ 8,978.81
|
₽ 317,850.00
|
|
FC
|
P107
|
Finishing of the facade (sqm)
|
177.00
|
₽ 2,689.83
|
₽ 476,100.00
|
|
FC
|
P107
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
14.16
|
₽ 27,044.49
|
₽ 382,950.00
|
|
FC
|
P107
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
17.70
|
₽ 26,898.31
|
₽ 476,100.00
|
|
FC
|
P107
|
Steel subsystem of the facade (sqm)
|
177.00
|
₽ 2,689.83
|
₽ 476,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P108
|
|
214.20
|
₽ 5,059.52
|
₽ 1,083,750.00
|
|
FC
|
P108
|
AAC concrete of the facade (cum)
|
18.00
|
₽ 9,066.67
|
₽ 163,200.00
|
|
FC
|
P108
|
Finishing of the facade (sqm)
|
90.00
|
₽ 2,685.00
|
₽ 241,650.00
|
|
FC
|
P108
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
7.20
|
₽ 27,166.67
|
₽ 195,600.00
|
|
FC
|
P108
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
9.00
|
₽ 26,850.00
|
₽ 241,650.00
|
|
FC
|
P108
|
Steel subsystem of the facade (sqm)
|
90.00
|
₽ 2,685.00
|
₽ 241,650.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P109
|
|
257.04
|
₽ 5,057.19
|
₽ 1,299,900.00
|
|
FC
|
P109
|
AAC concrete of the facade (cum)
|
21.60
|
₽ 9,013.89
|
₽ 194,700.00
|
|
FC
|
P109
|
Finishing of the facade (sqm)
|
108.00
|
₽ 2,690.28
|
₽ 290,550.00
|
|
FC
|
P109
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
8.64
|
₽ 27,031.25
|
₽ 233,550.00
|
|
FC
|
P109
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
10.80
|
₽ 26,902.78
|
₽ 290,550.00
|
|
FC
|
P109
|
Steel subsystem of the facade (sqm)
|
108.00
|
₽ 2,690.28
|
₽ 290,550.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P110
|
|
349.86
|
₽ 5,055.74
|
₽ 1,768,800.00
|
|
FC
|
P110
|
AAC concrete of the facade (cum)
|
29.40
|
₽ 9,025.51
|
₽ 265,350.00
|
|
FC
|
P110
|
Finishing of the facade (sqm)
|
147.00
|
₽ 2,690.82
|
₽ 395,550.00
|
|
FC
|
P110
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
11.76
|
₽ 26,938.78
|
₽ 316,800.00
|
|
FC
|
P110
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
14.70
|
₽ 26,908.16
|
₽ 395,550.00
|
|
FC
|
P110
|
Steel subsystem of the facade (sqm)
|
147.00
|
₽ 2,690.82
|
₽ 395,550.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P111
|
|
499.80
|
₽ 5,044.42
|
₽ 2,521,200.00
|
|
FC
|
P111
|
AAC concrete of the facade (cum)
|
42.00
|
₽ 9,000.00
|
₽ 378,000.00
|
|
FC
|
P111
|
Finishing of the facade (sqm)
|
210.00
|
₽ 2,685.00
|
₽ 563,850.00
|
|
FC
|
P111
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
16.80
|
₽ 26,883.93
|
₽ 451,650.00
|
|
FC
|
P111
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
21.00
|
₽ 26,850.00
|
₽ 563,850.00
|
|
FC
|
P111
|
Steel subsystem of the facade (sqm)
|
210.00
|
₽ 2,685.00
|
₽ 563,850.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Akadem Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Akadem Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Akadem Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Akadem Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Akadem Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Akadem Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Akadem Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Nauki Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Nauki Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Nauki Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Nauki Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Nauki Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Nauki Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Nauki Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P201
|
|
699.72
|
₽ 5,051.66
|
₽ 3,534,750.00
|
|
FC
|
P201
|
AAC concrete of the facade (cum)
|
58.80
|
₽ 8,977.04
|
₽ 527,850.00
|
|
FC
|
P201
|
Finishing of the facade (sqm)
|
294.00
|
₽ 2,690.82
|
₽ 791,100.00
|
|
FC
|
P201
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
23.52
|
₽ 26,938.78
|
₽ 633,600.00
|
|
FC
|
P201
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
29.40
|
₽ 26,908.16
|
₽ 791,100.00
|
|
FC
|
P201
|
Steel subsystem of the facade (sqm)
|
294.00
|
₽ 2,690.82
|
₽ 791,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P202
|
|
321.30
|
₽ 5,062.56
|
₽ 1,626,600.00
|
|
FC
|
P202
|
AAC concrete of the facade (cum)
|
27.00
|
₽ 9,050.00
|
₽ 244,350.00
|
|
FC
|
P202
|
Finishing of the facade (sqm)
|
135.00
|
₽ 2,695.56
|
₽ 363,900.00
|
|
FC
|
P202
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
10.80
|
₽ 26,902.78
|
₽ 290,550.00
|
|
FC
|
P202
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
13.50
|
₽ 26,955.56
|
₽ 363,900.00
|
|
FC
|
P202
|
Steel subsystem of the facade (sqm)
|
135.00
|
₽ 2,695.56
|
₽ 363,900.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P203
|
|
378.42
|
₽ 5,049.94
|
₽ 1,911,000.00
|
|
FC
|
P203
|
AAC concrete of the facade (cum)
|
31.80
|
₽ 9,004.72
|
₽ 286,350.00
|
|
FC
|
P203
|
Finishing of the facade (sqm)
|
159.00
|
₽ 2,686.79
|
₽ 427,200.00
|
|
FC
|
P203
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
12.72
|
₽ 26,969.34
|
₽ 343,050.00
|
|
FC
|
P203
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
15.90
|
₽ 26,867.92
|
₽ 427,200.00
|
|
FC
|
P203
|
Steel subsystem of the facade (sqm)
|
159.00
|
₽ 2,686.79
|
₽ 427,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P204
|
|
714.00
|
₽ 5,039.71
|
₽ 3,598,350.00
|
|
FC
|
P204
|
AAC concrete of the facade (cum)
|
60.00
|
₽ 8,957.50
|
₽ 537,450.00
|
|
FC
|
P204
|
Finishing of the facade (sqm)
|
300.00
|
₽ 2,685.00
|
₽ 805,500.00
|
|
FC
|
P204
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
24.00
|
₽ 26,850.00
|
₽ 644,400.00
|
|
FC
|
P204
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
30.00
|
₽ 26,850.00
|
₽ 805,500.00
|
|
FC
|
P204
|
Steel subsystem of the facade (sqm)
|
300.00
|
₽ 2,685.00
|
₽ 805,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
CHapaev Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
CHapaev Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
CHapaev Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
CHapaev Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
CHapaev Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
CHapaev Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
CHapaev Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
Budenniy Tower
|
|
36,899.52
|
₽ 5,455.83
|
₽ 201,317,550.00
|
|
FC
|
Budenniy Tower
|
AAC concrete of the facade (cum)
|
3,100.80
|
₽ 8,970.39
|
₽ 27,815,400.00
|
|
FC
|
Budenniy Tower
|
Finishing of the facade (sqm)
|
5,472.00
|
₽ 2,698.96
|
₽ 14,768,700.00
|
|
FC
|
Budenniy Tower
|
Glazing of the facade (sqm)
|
10,032.00
|
₽ 4,190.62
|
₽ 42,040,350.00
|
|
FC
|
Budenniy Tower
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
1,240.32
|
₽ 26,895.56
|
₽ 33,359,100.00
|
|
FC
|
Budenniy Tower
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
1,550.40
|
₽ 26,875.00
|
₽ 41,667,000.00
|
|
FC
|
Budenniy Tower
|
Steel subsystem of the facade (sqm)
|
15,504.00
|
₽ 2,687.50
|
₽ 41,667,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P301
|
|
321.30
|
₽ 5,062.56
|
₽ 1,626,600.00
|
|
FC
|
P301
|
AAC concrete of the facade (cum)
|
27.00
|
₽ 9,050.00
|
₽ 244,350.00
|
|
FC
|
P301
|
Finishing of the facade (sqm)
|
135.00
|
₽ 2,695.56
|
₽ 363,900.00
|
|
FC
|
P301
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
10.80
|
₽ 26,902.78
|
₽ 290,550.00
|
|
FC
|
P301
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
13.50
|
₽ 26,955.56
|
₽ 363,900.00
|
|
FC
|
P301
|
Steel subsystem of the facade (sqm)
|
135.00
|
₽ 2,695.56
|
₽ 363,900.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P302
|
|
678.30
|
₽ 5,048.43
|
₽ 3,424,350.00
|
|
FC
|
P302
|
AAC concrete of the facade (cum)
|
57.00
|
₽ 8,976.32
|
₽ 511,650.00
|
|
FC
|
P302
|
Finishing of the facade (sqm)
|
285.00
|
₽ 2,690.00
|
₽ 766,650.00
|
|
FC
|
P302
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
22.80
|
₽ 26,875.00
|
₽ 612,750.00
|
|
FC
|
P302
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
28.50
|
₽ 26,900.00
|
₽ 766,650.00
|
|
FC
|
P302
|
Steel subsystem of the facade (sqm)
|
285.00
|
₽ 2,690.00
|
₽ 766,650.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P303
|
|
307.02
|
₽ 5,060.09
|
₽ 1,553,550.00
|
|
FC
|
P303
|
AAC concrete of the facade (cum)
|
25.80
|
₽ 9,063.95
|
₽ 233,850.00
|
|
FC
|
P303
|
Finishing of the facade (sqm)
|
129.00
|
₽ 2,687.21
|
₽ 346,650.00
|
|
FC
|
P303
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
10.32
|
₽ 27,107.56
|
₽ 279,750.00
|
|
FC
|
P303
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
12.90
|
₽ 26,872.09
|
₽ 346,650.00
|
|
FC
|
P303
|
Steel subsystem of the facade (sqm)
|
129.00
|
₽ 2,687.21
|
₽ 346,650.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FC
|
P304
|
|
714.00
|
₽ 5,039.71
|
₽ 3,598,350.00
|
|
FC
|
P304
|
AAC concrete of the facade (cum)
|
60.00
|
₽ 8,957.50
|
₽ 537,450.00
|
|
FC
|
P304
|
Finishing of the facade (sqm)
|
300.00
|
₽ 2,685.00
|
₽ 805,500.00
|
|
FC
|
P304
|
Rockwool ВЕНТИ БАТТС of the facade (cum)
|
24.00
|
₽ 26,850.00
|
₽ 644,400.00
|
|
FC
|
P304
|
Rockwool ВЕНТИ БАТТС Н of the facade (cum)
|
30.00
|
₽ 26,850.00
|
₽ 805,500.00
|
|
FC
|
P304
|
Steel subsystem of the facade (sqm)
|
300.00
|
₽ 2,685.00
|
₽ 805,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
|
|
1,771,255.80
|
₽ 2,088.55
|
₽ 3,699,358,500.00
|
|
FN
|
Benua Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Benua Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Benua Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Benua Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Benua Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Benua Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Benua Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Tihoretskiy Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Tihoretskiy Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Tihoretskiy Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Tihoretskiy Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Tihoretskiy Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Tihoretskiy Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Tihoretskiy Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Kurchatov Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Kurchatov Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Kurchatov Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Kurchatov Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Kurchatov Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Kurchatov Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Kurchatov Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Politekh Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Politekh Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Politekh Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Politekh Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Politekh Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Politekh Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Politekh Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Atom Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Atom Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Atom Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Atom Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Atom Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Atom Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Atom Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
RTK Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
RTK Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
RTK Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
RTK Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
RTK Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
RTK Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
RTK Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P101
|
|
15,136.80
|
₽ 1,900.73
|
₽ 28,770,900.00
|
|
FN
|
P101
|
Bump stop (kg)
|
2,968.00
|
₽ 1,486.15
|
₽ 4,410,900.00
|
|
FN
|
P101
|
Finishing of the ceiling (sqm)
|
2,968.00
|
₽ 1,686.15
|
₽ 5,004,500.00
|
|
FN
|
P101
|
Finishing of the floor (sqm)
|
2,968.00
|
₽ 3,186.15
|
₽ 9,456,500.00
|
|
FN
|
P101
|
Finishing of the walls (sqm)
|
2,968.00
|
₽ 1,686.15
|
₽ 5,004,500.00
|
|
FN
|
P101
|
Road markings (sqm)
|
2,968.00
|
₽ 1,486.15
|
₽ 4,410,900.00
|
|
FN
|
P101
|
Screed of the floor (cum)
|
296.80
|
₽ 1,629.38
|
₽ 483,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P102
|
|
19,594.20
|
₽ 1,900.79
|
₽ 37,244,400.00
|
|
FN
|
P102
|
Bump stop (kg)
|
3,842.00
|
₽ 1,486.34
|
₽ 5,710,500.00
|
|
FN
|
P102
|
Finishing of the ceiling (sqm)
|
3,842.00
|
₽ 1,686.34
|
₽ 6,478,900.00
|
|
FN
|
P102
|
Finishing of the floor (sqm)
|
3,842.00
|
₽ 3,186.34
|
₽ 12,241,900.00
|
|
FN
|
P102
|
Finishing of the walls (sqm)
|
3,842.00
|
₽ 1,686.34
|
₽ 6,478,900.00
|
|
FN
|
P102
|
Road markings (sqm)
|
3,842.00
|
₽ 1,486.34
|
₽ 5,710,500.00
|
|
FN
|
P102
|
Screed of the floor (cum)
|
384.20
|
₽ 1,623.37
|
₽ 623,700.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P103
|
|
23,347.80
|
₽ 1,899.69
|
₽ 44,353,500.00
|
|
FN
|
P103
|
Bump stop (kg)
|
4,578.00
|
₽ 1,485.12
|
₽ 6,798,900.00
|
|
FN
|
P103
|
Finishing of the ceiling (sqm)
|
4,578.00
|
₽ 1,685.12
|
₽ 7,714,500.00
|
|
FN
|
P103
|
Finishing of the floor (sqm)
|
4,578.00
|
₽ 3,185.12
|
₽ 14,581,500.00
|
|
FN
|
P103
|
Finishing of the walls (sqm)
|
4,578.00
|
₽ 1,685.12
|
₽ 7,714,500.00
|
|
FN
|
P103
|
Road markings (sqm)
|
4,578.00
|
₽ 1,485.12
|
₽ 6,798,900.00
|
|
FN
|
P103
|
Screed of the floor (cum)
|
457.80
|
₽ 1,627.79
|
₽ 745,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P104
|
|
18,604.80
|
₽ 1,900.43
|
₽ 35,357,100.00
|
|
FN
|
P104
|
Bump stop (kg)
|
3,648.00
|
₽ 1,485.94
|
₽ 5,420,700.00
|
|
FN
|
P104
|
Finishing of the ceiling (sqm)
|
3,648.00
|
₽ 1,685.94
|
₽ 6,150,300.00
|
|
FN
|
P104
|
Finishing of the floor (sqm)
|
3,648.00
|
₽ 3,185.94
|
₽ 11,622,300.00
|
|
FN
|
P104
|
Finishing of the walls (sqm)
|
3,648.00
|
₽ 1,685.94
|
₽ 6,150,300.00
|
|
FN
|
P104
|
Road markings (sqm)
|
3,648.00
|
₽ 1,485.94
|
₽ 5,420,700.00
|
|
FN
|
P104
|
Screed of the floor (cum)
|
364.80
|
₽ 1,625.00
|
₽ 592,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P105
|
|
15,136.80
|
₽ 1,900.73
|
₽ 28,770,900.00
|
|
FN
|
P105
|
Bump stop (kg)
|
2,968.00
|
₽ 1,486.15
|
₽ 4,410,900.00
|
|
FN
|
P105
|
Finishing of the ceiling (sqm)
|
2,968.00
|
₽ 1,686.15
|
₽ 5,004,500.00
|
|
FN
|
P105
|
Finishing of the floor (sqm)
|
2,968.00
|
₽ 3,186.15
|
₽ 9,456,500.00
|
|
FN
|
P105
|
Finishing of the walls (sqm)
|
2,968.00
|
₽ 1,686.15
|
₽ 5,004,500.00
|
|
FN
|
P105
|
Road markings (sqm)
|
2,968.00
|
₽ 1,486.15
|
₽ 4,410,900.00
|
|
FN
|
P105
|
Screed of the floor (cum)
|
296.80
|
₽ 1,629.38
|
₽ 483,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P106
|
|
17,299.20
|
₽ 1,900.15
|
₽ 32,871,000.00
|
|
FN
|
P106
|
Bump stop (kg)
|
3,392.00
|
₽ 1,485.67
|
₽ 5,039,400.00
|
|
FN
|
P106
|
Finishing of the ceiling (sqm)
|
3,392.00
|
₽ 1,685.67
|
₽ 5,717,800.00
|
|
FN
|
P106
|
Finishing of the floor (sqm)
|
3,392.00
|
₽ 3,185.67
|
₽ 10,805,800.00
|
|
FN
|
P106
|
Finishing of the walls (sqm)
|
3,392.00
|
₽ 1,685.67
|
₽ 5,717,800.00
|
|
FN
|
P106
|
Road markings (sqm)
|
3,392.00
|
₽ 1,485.67
|
₽ 5,039,400.00
|
|
FN
|
P106
|
Screed of the floor (cum)
|
339.20
|
₽ 1,623.82
|
₽ 550,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P107
|
|
16,238.40
|
₽ 1,900.94
|
₽ 30,868,200.00
|
|
FN
|
P107
|
Bump stop (kg)
|
3,184.00
|
₽ 1,486.43
|
₽ 4,732,800.00
|
|
FN
|
P107
|
Finishing of the ceiling (sqm)
|
3,184.00
|
₽ 1,686.43
|
₽ 5,369,600.00
|
|
FN
|
P107
|
Finishing of the floor (sqm)
|
3,184.00
|
₽ 3,186.43
|
₽ 10,145,600.00
|
|
FN
|
P107
|
Finishing of the walls (sqm)
|
3,184.00
|
₽ 1,686.43
|
₽ 5,369,600.00
|
|
FN
|
P107
|
Road markings (sqm)
|
3,184.00
|
₽ 1,486.43
|
₽ 4,732,800.00
|
|
FN
|
P107
|
Screed of the floor (cum)
|
318.40
|
₽ 1,626.26
|
₽ 517,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P108
|
|
19,981.80
|
₽ 1,899.57
|
₽ 37,956,900.00
|
|
FN
|
P108
|
Bump stop (kg)
|
3,918.00
|
₽ 1,485.15
|
₽ 5,818,800.00
|
|
FN
|
P108
|
Finishing of the ceiling (sqm)
|
3,918.00
|
₽ 1,685.15
|
₽ 6,602,400.00
|
|
FN
|
P108
|
Finishing of the floor (sqm)
|
3,918.00
|
₽ 3,185.15
|
₽ 12,479,400.00
|
|
FN
|
P108
|
Finishing of the walls (sqm)
|
3,918.00
|
₽ 1,685.15
|
₽ 6,602,400.00
|
|
FN
|
P108
|
Road markings (sqm)
|
3,918.00
|
₽ 1,485.15
|
₽ 5,818,800.00
|
|
FN
|
P108
|
Screed of the floor (cum)
|
391.80
|
₽ 1,620.98
|
₽ 635,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P109
|
|
19,461.60
|
₽ 1,899.79
|
₽ 36,972,900.00
|
|
FN
|
P109
|
Bump stop (kg)
|
3,816.00
|
₽ 1,485.30
|
₽ 5,667,900.00
|
|
FN
|
P109
|
Finishing of the ceiling (sqm)
|
3,816.00
|
₽ 1,685.30
|
₽ 6,431,100.00
|
|
FN
|
P109
|
Finishing of the floor (sqm)
|
3,816.00
|
₽ 3,185.30
|
₽ 12,155,100.00
|
|
FN
|
P109
|
Finishing of the walls (sqm)
|
3,816.00
|
₽ 1,685.30
|
₽ 6,431,100.00
|
|
FN
|
P109
|
Road markings (sqm)
|
3,816.00
|
₽ 1,485.30
|
₽ 5,667,900.00
|
|
FN
|
P109
|
Screed of the floor (cum)
|
381.60
|
₽ 1,624.21
|
₽ 619,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P110
|
|
21,562.80
|
₽ 1,900.48
|
₽ 40,979,700.00
|
|
FN
|
P110
|
Bump stop (kg)
|
4,228.00
|
₽ 1,485.81
|
₽ 6,282,000.00
|
|
FN
|
P110
|
Finishing of the ceiling (sqm)
|
4,228.00
|
₽ 1,685.81
|
₽ 7,127,600.00
|
|
FN
|
P110
|
Finishing of the floor (sqm)
|
4,228.00
|
₽ 3,185.81
|
₽ 13,469,600.00
|
|
FN
|
P110
|
Finishing of the walls (sqm)
|
4,228.00
|
₽ 1,685.81
|
₽ 7,127,600.00
|
|
FN
|
P110
|
Road markings (sqm)
|
4,228.00
|
₽ 1,485.81
|
₽ 6,282,000.00
|
|
FN
|
P110
|
Screed of the floor (cum)
|
422.80
|
₽ 1,634.11
|
₽ 690,900.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P111
|
|
18,900.60
|
₽ 1,900.53
|
₽ 35,921,100.00
|
|
FN
|
P111
|
Bump stop (kg)
|
3,706.00
|
₽ 1,486.08
|
₽ 5,507,400.00
|
|
FN
|
P111
|
Finishing of the ceiling (sqm)
|
3,706.00
|
₽ 1,686.08
|
₽ 6,248,600.00
|
|
FN
|
P111
|
Finishing of the floor (sqm)
|
3,706.00
|
₽ 3,186.08
|
₽ 11,807,600.00
|
|
FN
|
P111
|
Finishing of the walls (sqm)
|
3,706.00
|
₽ 1,686.08
|
₽ 6,248,600.00
|
|
FN
|
P111
|
Road markings (sqm)
|
3,706.00
|
₽ 1,486.08
|
₽ 5,507,400.00
|
|
FN
|
P111
|
Screed of the floor (cum)
|
370.60
|
₽ 1,623.04
|
₽ 601,500.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Akadem Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Akadem Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Akadem Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Akadem Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Akadem Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Akadem Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Akadem Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Nauki Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Nauki Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Nauki Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Nauki Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Nauki Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Nauki Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Nauki Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P201
|
|
24,327.00
|
₽ 1,900.12
|
₽ 46,224,300.00
|
|
FN
|
P201
|
Bump stop (kg)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P201
|
Finishing of the ceiling (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P201
|
Finishing of the floor (sqm)
|
4,770.00
|
₽ 3,185.60
|
₽ 15,195,300.00
|
|
FN
|
P201
|
Finishing of the walls (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P201
|
Road markings (sqm)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P201
|
Screed of the floor (cum)
|
477.00
|
₽ 1,626.42
|
₽ 775,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P202
|
|
24,327.00
|
₽ 1,900.12
|
₽ 46,224,300.00
|
|
FN
|
P202
|
Bump stop (kg)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P202
|
Finishing of the ceiling (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P202
|
Finishing of the floor (sqm)
|
4,770.00
|
₽ 3,185.60
|
₽ 15,195,300.00
|
|
FN
|
P202
|
Finishing of the walls (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P202
|
Road markings (sqm)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P202
|
Screed of the floor (cum)
|
477.00
|
₽ 1,626.42
|
₽ 775,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P203
|
|
23,245.80
|
₽ 1,899.70
|
₽ 44,160,000.00
|
|
FN
|
P203
|
Bump stop (kg)
|
4,558.00
|
₽ 1,485.13
|
₽ 6,769,200.00
|
|
FN
|
P203
|
Finishing of the ceiling (sqm)
|
4,558.00
|
₽ 1,685.13
|
₽ 7,680,800.00
|
|
FN
|
P203
|
Finishing of the floor (sqm)
|
4,558.00
|
₽ 3,185.13
|
₽ 14,517,800.00
|
|
FN
|
P203
|
Finishing of the walls (sqm)
|
4,558.00
|
₽ 1,685.13
|
₽ 7,680,800.00
|
|
FN
|
P203
|
Road markings (sqm)
|
4,558.00
|
₽ 1,485.13
|
₽ 6,769,200.00
|
|
FN
|
P203
|
Screed of the floor (cum)
|
455.80
|
₽ 1,628.35
|
₽ 742,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P204
|
|
25,408.20
|
₽ 1,900.51
|
₽ 48,288,600.00
|
|
FN
|
P204
|
Bump stop (kg)
|
4,982.00
|
₽ 1,486.03
|
₽ 7,403,400.00
|
|
FN
|
P204
|
Finishing of the ceiling (sqm)
|
4,982.00
|
₽ 1,686.03
|
₽ 8,399,800.00
|
|
FN
|
P204
|
Finishing of the floor (sqm)
|
4,982.00
|
₽ 3,186.03
|
₽ 15,872,800.00
|
|
FN
|
P204
|
Finishing of the walls (sqm)
|
4,982.00
|
₽ 1,686.03
|
₽ 8,399,800.00
|
|
FN
|
P204
|
Road markings (sqm)
|
4,982.00
|
₽ 1,486.03
|
₽ 7,403,400.00
|
|
FN
|
P204
|
Screed of the floor (cum)
|
498.20
|
₽ 1,624.65
|
₽ 809,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
CHapaev Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
CHapaev Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
CHapaev Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
CHapaev Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
CHapaev Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
CHapaev Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
CHapaev Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
Budenniy Tower
|
|
137,137.50
|
₽ 2,143.47
|
₽ 293,949,750.00
|
|
FN
|
Budenniy Tower
|
Bump stop (kg)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Budenniy Tower
|
Finishing of the ceiling (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Budenniy Tower
|
Finishing of the floor (sqm)
|
42,665.00
|
₽ 3,185.23
|
₽ 135,898,000.00
|
|
FN
|
Budenniy Tower
|
Finishing of the walls (sqm)
|
42,665.00
|
₽ 1,685.23
|
₽ 71,900,500.00
|
|
FN
|
Budenniy Tower
|
Road markings (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
FN
|
Budenniy Tower
|
Screed of the floor (cum)
|
4,266.50
|
₽ 1,642.74
|
₽ 7,008,750.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P301
|
|
24,327.00
|
₽ 1,900.12
|
₽ 46,224,300.00
|
|
FN
|
P301
|
Bump stop (kg)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P301
|
Finishing of the ceiling (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P301
|
Finishing of the floor (sqm)
|
4,770.00
|
₽ 3,185.60
|
₽ 15,195,300.00
|
|
FN
|
P301
|
Finishing of the walls (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P301
|
Road markings (sqm)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P301
|
Screed of the floor (cum)
|
477.00
|
₽ 1,626.42
|
₽ 775,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P302
|
|
24,327.00
|
₽ 1,900.12
|
₽ 46,224,300.00
|
|
FN
|
P302
|
Bump stop (kg)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P302
|
Finishing of the ceiling (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P302
|
Finishing of the floor (sqm)
|
4,770.00
|
₽ 3,185.60
|
₽ 15,195,300.00
|
|
FN
|
P302
|
Finishing of the walls (sqm)
|
4,770.00
|
₽ 1,685.60
|
₽ 8,040,300.00
|
|
FN
|
P302
|
Road markings (sqm)
|
4,770.00
|
₽ 1,485.60
|
₽ 7,086,300.00
|
|
FN
|
P302
|
Screed of the floor (cum)
|
477.00
|
₽ 1,626.42
|
₽ 775,800.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P303
|
|
23,245.80
|
₽ 1,899.70
|
₽ 44,160,000.00
|
|
FN
|
P303
|
Bump stop (kg)
|
4,558.00
|
₽ 1,485.13
|
₽ 6,769,200.00
|
|
FN
|
P303
|
Finishing of the ceiling (sqm)
|
4,558.00
|
₽ 1,685.13
|
₽ 7,680,800.00
|
|
FN
|
P303
|
Finishing of the floor (sqm)
|
4,558.00
|
₽ 3,185.13
|
₽ 14,517,800.00
|
|
FN
|
P303
|
Finishing of the walls (sqm)
|
4,558.00
|
₽ 1,685.13
|
₽ 7,680,800.00
|
|
FN
|
P303
|
Road markings (sqm)
|
4,558.00
|
₽ 1,485.13
|
₽ 6,769,200.00
|
|
FN
|
P303
|
Screed of the floor (cum)
|
455.80
|
₽ 1,628.35
|
₽ 742,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
FN
|
P304
|
|
25,408.20
|
₽ 1,900.51
|
₽ 48,288,600.00
|
|
FN
|
P304
|
Bump stop (kg)
|
4,982.00
|
₽ 1,486.03
|
₽ 7,403,400.00
|
|
FN
|
P304
|
Finishing of the ceiling (sqm)
|
4,982.00
|
₽ 1,686.03
|
₽ 8,399,800.00
|
|
FN
|
P304
|
Finishing of the floor (sqm)
|
4,982.00
|
₽ 3,186.03
|
₽ 15,872,800.00
|
|
FN
|
P304
|
Finishing of the walls (sqm)
|
4,982.00
|
₽ 1,686.03
|
₽ 8,399,800.00
|
|
FN
|
P304
|
Road markings (sqm)
|
4,982.00
|
₽ 1,486.03
|
₽ 7,403,400.00
|
|
FN
|
P304
|
Screed of the floor (cum)
|
498.20
|
₽ 1,624.65
|
₽ 809,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
|
|
2,824,772.00
|
₽ 1,536.44
|
₽ 4,340,096,000.00
|
|
PM
|
Benua Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Benua Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Benua Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Benua Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Benua Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Benua Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Benua Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Benua Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Benua Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Benua Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Benua Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Benua Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Benua Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Benua Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Benua Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Benua Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Benua Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Tihoretskiy Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Tihoretskiy Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Tihoretskiy Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Tihoretskiy Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Tihoretskiy Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Tihoretskiy Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Tihoretskiy Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Tihoretskiy Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Tihoretskiy Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Tihoretskiy Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Tihoretskiy Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Tihoretskiy Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Tihoretskiy Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Tihoretskiy Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Tihoretskiy Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Tihoretskiy Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Tihoretskiy Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Kurchatov Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Kurchatov Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Kurchatov Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Kurchatov Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Kurchatov Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Kurchatov Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Kurchatov Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Kurchatov Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Kurchatov Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Kurchatov Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Kurchatov Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Kurchatov Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Kurchatov Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Kurchatov Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Kurchatov Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Kurchatov Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Kurchatov Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Politekh Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Politekh Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Politekh Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Politekh Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Politekh Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Politekh Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Politekh Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Politekh Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Politekh Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Politekh Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Politekh Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Politekh Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Politekh Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Politekh Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Politekh Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Politekh Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Politekh Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Atom Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Atom Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Atom Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Atom Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Atom Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Atom Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Atom Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Atom Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Atom Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Atom Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Atom Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Atom Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Atom Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Atom Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Atom Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Atom Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Atom Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
RTK Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
RTK Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
RTK Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
RTK Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
RTK Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
RTK Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
RTK Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
RTK Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
RTK Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
RTK Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
RTK Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
RTK Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
RTK Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
RTK Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
RTK Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
RTK Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
RTK Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P101
|
|
11,872.00
|
₽ 1,286.15
|
₽ 15,269,200.00
|
|
PM
|
P101
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
PM
|
P101
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
PM
|
P101
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
PM
|
P101
|
Storm Water Drainage Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P102
|
|
15,368.00
|
₽ 1,286.34
|
₽ 19,768,400.00
|
|
PM
|
P102
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
PM
|
P102
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
PM
|
P102
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
PM
|
P102
|
Storm Water Drainage Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P103
|
|
18,312.00
|
₽ 1,285.12
|
₽ 23,533,200.00
|
|
PM
|
P103
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
PM
|
P103
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
PM
|
P103
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
PM
|
P103
|
Storm Water Drainage Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P104
|
|
14,592.00
|
₽ 1,285.94
|
₽ 18,764,400.00
|
|
PM
|
P104
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
PM
|
P104
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
PM
|
P104
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
PM
|
P104
|
Storm Water Drainage Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P105
|
|
11,872.00
|
₽ 1,286.15
|
₽ 15,269,200.00
|
|
PM
|
P105
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
PM
|
P105
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
PM
|
P105
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
PM
|
P105
|
Storm Water Drainage Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P106
|
|
13,568.00
|
₽ 1,285.67
|
₽ 17,444,000.00
|
|
PM
|
P106
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
PM
|
P106
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
PM
|
P106
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
PM
|
P106
|
Storm Water Drainage Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P107
|
|
12,736.00
|
₽ 1,286.43
|
₽ 16,384,000.00
|
|
PM
|
P107
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
PM
|
P107
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
PM
|
P107
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
PM
|
P107
|
Storm Water Drainage Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P108
|
|
15,672.00
|
₽ 1,285.15
|
₽ 20,140,800.00
|
|
PM
|
P108
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
PM
|
P108
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
PM
|
P108
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
PM
|
P108
|
Storm Water Drainage Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P109
|
|
15,264.00
|
₽ 1,285.30
|
₽ 19,618,800.00
|
|
PM
|
P109
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
PM
|
P109
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
PM
|
P109
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
PM
|
P109
|
Storm Water Drainage Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P110
|
|
16,912.00
|
₽ 1,285.81
|
₽ 21,745,600.00
|
|
PM
|
P110
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
PM
|
P110
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
PM
|
P110
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
PM
|
P110
|
Storm Water Drainage Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P111
|
|
14,824.00
|
₽ 1,286.08
|
₽ 19,064,800.00
|
|
PM
|
P111
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
PM
|
P111
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
PM
|
P111
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
PM
|
P111
|
Storm Water Drainage Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Akadem Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Akadem Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Akadem Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Akadem Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Akadem Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Akadem Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Akadem Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Akadem Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Akadem Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Akadem Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Akadem Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Akadem Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Akadem Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Akadem Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Akadem Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Akadem Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Akadem Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Nauki Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Nauki Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Nauki Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Nauki Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Nauki Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Nauki Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Nauki Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Nauki Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Nauki Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Nauki Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Nauki Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Nauki Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Nauki Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Nauki Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Nauki Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Nauki Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Nauki Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P201
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
PM
|
P201
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P201
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P201
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P201
|
Storm Water Drainage Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P202
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
PM
|
P202
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P202
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P202
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P202
|
Storm Water Drainage Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P203
|
|
18,232.00
|
₽ 1,285.13
|
₽ 23,430,400.00
|
|
PM
|
P203
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
PM
|
P203
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
PM
|
P203
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
PM
|
P203
|
Storm Water Drainage Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P204
|
|
19,928.00
|
₽ 1,286.03
|
₽ 25,628,000.00
|
|
PM
|
P204
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
PM
|
P204
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
PM
|
P204
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
PM
|
P204
|
Storm Water Drainage Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
CHapaev Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
CHapaev Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
CHapaev Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
CHapaev Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
CHapaev Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
CHapaev Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
CHapaev Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
CHapaev Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
CHapaev Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
CHapaev Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
CHapaev Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
CHapaev Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
CHapaev Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
CHapaev Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
CHapaev Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
CHapaev Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
CHapaev Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
Budenniy Tower
|
|
251,114.00
|
₽ 1,567.76
|
₽ 393,686,000.00
|
|
PM
|
Budenniy Tower
|
Automatic fire extinguishing. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Budenniy Tower
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Budenniy Tower
|
Automatic fire extinguishing. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Budenniy Tower
|
Drainage sewer system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Budenniy Tower
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Budenniy Tower
|
Drainage sewer system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Budenniy Tower
|
Internal fire water supply. Fire pump stationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Budenniy Tower
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Budenniy Tower
|
Internal fire water supply. Fire pump stationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Budenniy Tower
|
Sewage System (household)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Budenniy Tower
|
Sewage System (industrial)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Budenniy Tower
|
Storm Water Drainage Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Budenniy Tower
|
Storm Water Drainage Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
PM
|
Budenniy Tower
|
Storm Water Drainage Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
PM
|
Budenniy Tower
|
Water Supply Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
PM
|
Budenniy Tower
|
Water Supply Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P301
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
PM
|
P301
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P301
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P301
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P301
|
Storm Water Drainage Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P302
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
PM
|
P302
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P302
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P302
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
PM
|
P302
|
Storm Water Drainage Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P303
|
|
18,232.00
|
₽ 1,285.13
|
₽ 23,430,400.00
|
|
PM
|
P303
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
PM
|
P303
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
PM
|
P303
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
PM
|
P303
|
Storm Water Drainage Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
PM
|
P304
|
|
19,928.00
|
₽ 1,286.03
|
₽ 25,628,000.00
|
|
PM
|
P304
|
Automatic fire extinguishing. Fire pump stationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
PM
|
P304
|
Drainage sewer system, antismoke ventilationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
PM
|
P304
|
Internal fire water supply. Fire pump stationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
PM
|
P304
|
Storm Water Drainage Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
|
|
1,309,598.00
|
₽ 1,556.13
|
₽ 2,037,905,000.00
|
|
MC
|
Benua Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Benua Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Benua Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Benua Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Benua Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Benua Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Benua Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Benua Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Tihoretskiy Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Tihoretskiy Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Tihoretskiy Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Tihoretskiy Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Tihoretskiy Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Tihoretskiy Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Tihoretskiy Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Tihoretskiy Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Kurchatov Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Kurchatov Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Kurchatov Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Kurchatov Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Kurchatov Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Kurchatov Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Kurchatov Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Kurchatov Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Politekh Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Politekh Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Politekh Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Politekh Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Politekh Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Politekh Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Politekh Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Politekh Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Atom Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Atom Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Atom Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Atom Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Atom Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Atom Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Atom Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Atom Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
RTK Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
RTK Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
RTK Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
RTK Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
RTK Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
RTK Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
RTK Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
RTK Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P101
|
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
MC
|
P101
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P102
|
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
MC
|
P102
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P103
|
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
MC
|
P103
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P104
|
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
MC
|
P104
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P105
|
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
MC
|
P105
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P106
|
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
MC
|
P106
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P107
|
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
MC
|
P107
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P108
|
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
MC
|
P108
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P109
|
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
MC
|
P109
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P110
|
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
MC
|
P110
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P111
|
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
MC
|
P111
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Akadem Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Akadem Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Akadem Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Akadem Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Akadem Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Akadem Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Akadem Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Akadem Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Nauki Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Nauki Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Nauki Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Nauki Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Nauki Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Nauki Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Nauki Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Nauki Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P201
|
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
MC
|
P201
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P202
|
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
MC
|
P202
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P203
|
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
MC
|
P203
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P204
|
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
MC
|
P204
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
CHapaev Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
CHapaev Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
CHapaev Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
CHapaev Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
CHapaev Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
CHapaev Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
CHapaev Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
CHapaev Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
Budenniy Tower
|
|
123,119.00
|
₽ 1,573.35
|
₽ 193,709,600.00
|
|
MC
|
Budenniy Tower
|
Air conditioning systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Budenniy Tower
|
Air conditioning systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Budenniy Tower
|
Cooling system, refrigeration equipmentof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Budenniy Tower
|
Cooling system, refrigeration equipmentof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
MC
|
Budenniy Tower
|
Ventilation system, antismoke ventilationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
MC
|
Budenniy Tower
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
MC
|
Budenniy Tower
|
Ventilation system, antismoke ventilationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P301
|
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
MC
|
P301
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P302
|
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
MC
|
P302
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P303
|
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
MC
|
P303
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
MC
|
P304
|
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
MC
|
P304
|
Ventilation system, antismoke ventilationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
|
|
2,800,392.00
|
₽ 1,536.89
|
₽ 4,303,886,000.00
|
|
EL
|
Benua Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Benua Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Benua Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Benua Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Benua Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Benua Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Benua Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Benua Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Benua Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Benua Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Benua Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Benua Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Benua Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Benua Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Benua Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Benua Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Tihoretskiy Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Tihoretskiy Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Tihoretskiy Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Tihoretskiy Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Tihoretskiy Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Tihoretskiy Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Tihoretskiy Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Tihoretskiy Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Tihoretskiy Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Tihoretskiy Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Tihoretskiy Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Tihoretskiy Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Tihoretskiy Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Tihoretskiy Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Tihoretskiy Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Tihoretskiy Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Kurchatov Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Kurchatov Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Kurchatov Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Kurchatov Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Kurchatov Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Kurchatov Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Kurchatov Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Kurchatov Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Kurchatov Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Kurchatov Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Kurchatov Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Kurchatov Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Kurchatov Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Kurchatov Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Kurchatov Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Kurchatov Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Politekh Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Politekh Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Politekh Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Politekh Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Politekh Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Politekh Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Politekh Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Politekh Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Politekh Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Politekh Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Politekh Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Politekh Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Politekh Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Politekh Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Politekh Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Politekh Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Atom Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Atom Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Atom Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Atom Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Atom Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Atom Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Atom Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Atom Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Atom Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Atom Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Atom Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Atom Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Atom Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Atom Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Atom Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Atom Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
RTK Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
RTK Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
RTK Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
RTK Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
RTK Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
RTK Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
RTK Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
RTK Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
RTK Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
RTK Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
RTK Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
RTK Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
RTK Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
RTK Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
RTK Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
RTK Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P101
|
|
11,872.00
|
₽ 1,286.15
|
₽ 15,269,200.00
|
|
EL
|
P101
|
Earthing Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
EL
|
P101
|
Emergency, evacuation lightingof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
EL
|
P101
|
Lighting Fixturesof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
EL
|
P101
|
Lightning Protection Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P102
|
|
15,368.00
|
₽ 1,286.34
|
₽ 19,768,400.00
|
|
EL
|
P102
|
Earthing Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
EL
|
P102
|
Emergency, evacuation lightingof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
EL
|
P102
|
Lighting Fixturesof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
EL
|
P102
|
Lightning Protection Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P103
|
|
18,312.00
|
₽ 1,285.12
|
₽ 23,533,200.00
|
|
EL
|
P103
|
Earthing Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
EL
|
P103
|
Emergency, evacuation lightingof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
EL
|
P103
|
Lighting Fixturesof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
EL
|
P103
|
Lightning Protection Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P104
|
|
14,592.00
|
₽ 1,285.94
|
₽ 18,764,400.00
|
|
EL
|
P104
|
Earthing Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
EL
|
P104
|
Emergency, evacuation lightingof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
EL
|
P104
|
Lighting Fixturesof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
EL
|
P104
|
Lightning Protection Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P105
|
|
11,872.00
|
₽ 1,286.15
|
₽ 15,269,200.00
|
|
EL
|
P105
|
Earthing Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
EL
|
P105
|
Emergency, evacuation lightingof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
EL
|
P105
|
Lighting Fixturesof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
EL
|
P105
|
Lightning Protection Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P106
|
|
13,568.00
|
₽ 1,285.67
|
₽ 17,444,000.00
|
|
EL
|
P106
|
Earthing Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
EL
|
P106
|
Emergency, evacuation lightingof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
EL
|
P106
|
Lighting Fixturesof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
EL
|
P106
|
Lightning Protection Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P107
|
|
12,736.00
|
₽ 1,286.43
|
₽ 16,384,000.00
|
|
EL
|
P107
|
Earthing Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
EL
|
P107
|
Emergency, evacuation lightingof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
EL
|
P107
|
Lighting Fixturesof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
EL
|
P107
|
Lightning Protection Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P108
|
|
15,672.00
|
₽ 1,285.15
|
₽ 20,140,800.00
|
|
EL
|
P108
|
Earthing Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
EL
|
P108
|
Emergency, evacuation lightingof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
EL
|
P108
|
Lighting Fixturesof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
EL
|
P108
|
Lightning Protection Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P109
|
|
15,264.00
|
₽ 1,285.30
|
₽ 19,618,800.00
|
|
EL
|
P109
|
Earthing Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
EL
|
P109
|
Emergency, evacuation lightingof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
EL
|
P109
|
Lighting Fixturesof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
EL
|
P109
|
Lightning Protection Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P110
|
|
16,912.00
|
₽ 1,285.81
|
₽ 21,745,600.00
|
|
EL
|
P110
|
Earthing Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
EL
|
P110
|
Emergency, evacuation lightingof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
EL
|
P110
|
Lighting Fixturesof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
EL
|
P110
|
Lightning Protection Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P111
|
|
14,824.00
|
₽ 1,286.08
|
₽ 19,064,800.00
|
|
EL
|
P111
|
Earthing Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
EL
|
P111
|
Emergency, evacuation lightingof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
EL
|
P111
|
Lighting Fixturesof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
EL
|
P111
|
Lightning Protection Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Akadem Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Akadem Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Akadem Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Akadem Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Akadem Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Akadem Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Akadem Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Akadem Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Akadem Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Akadem Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Akadem Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Akadem Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Akadem Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Akadem Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Akadem Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Akadem Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Nauki Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Nauki Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Nauki Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Nauki Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Nauki Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Nauki Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Nauki Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Nauki Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Nauki Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Nauki Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Nauki Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Nauki Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Nauki Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Nauki Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Nauki Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Nauki Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P201
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
EL
|
P201
|
Earthing Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P201
|
Emergency, evacuation lightingof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P201
|
Lighting Fixturesof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P201
|
Lightning Protection Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P202
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
EL
|
P202
|
Earthing Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P202
|
Emergency, evacuation lightingof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P202
|
Lighting Fixturesof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P202
|
Lightning Protection Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P203
|
|
18,232.00
|
₽ 1,285.13
|
₽ 23,430,400.00
|
|
EL
|
P203
|
Earthing Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
EL
|
P203
|
Emergency, evacuation lightingof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
EL
|
P203
|
Lighting Fixturesof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
EL
|
P203
|
Lightning Protection Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P204
|
|
19,928.00
|
₽ 1,286.03
|
₽ 25,628,000.00
|
|
EL
|
P204
|
Earthing Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
EL
|
P204
|
Emergency, evacuation lightingof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
EL
|
P204
|
Lighting Fixturesof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
EL
|
P204
|
Lightning Protection Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
CHapaev Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
CHapaev Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
CHapaev Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
CHapaev Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
CHapaev Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
CHapaev Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
CHapaev Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
CHapaev Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
CHapaev Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
CHapaev Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
CHapaev Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
CHapaev Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
CHapaev Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
CHapaev Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
CHapaev Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
CHapaev Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
Budenniy Tower
|
|
248,676.00
|
₽ 1,568.57
|
₽ 390,065,000.00
|
|
EL
|
Budenniy Tower
|
Earthing Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Budenniy Tower
|
Earthing Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Budenniy Tower
|
Earthing Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Budenniy Tower
|
Emergency, evacuation lightingof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Budenniy Tower
|
Emergency, evacuation lightingof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Budenniy Tower
|
Emergency, evacuation lightingof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Budenniy Tower
|
Lighting Fixturesof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Budenniy Tower
|
Lighting Fixturesof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Budenniy Tower
|
Lighting Fixturesof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Budenniy Tower
|
Lightning Protection Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Budenniy Tower
|
Lightning Protection Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
EL
|
Budenniy Tower
|
Lightning Protection Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Budenniy Tower
|
Power Installationsof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
EL
|
Budenniy Tower
|
Power Installationsof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
EL
|
Budenniy Tower
|
Structured Cabling Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P301
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
EL
|
P301
|
Earthing Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P301
|
Emergency, evacuation lightingof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P301
|
Lighting Fixturesof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P301
|
Lightning Protection Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P302
|
|
19,080.00
|
₽ 1,285.60
|
₽ 24,529,200.00
|
|
EL
|
P302
|
Earthing Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P302
|
Emergency, evacuation lightingof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P302
|
Lighting Fixturesof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
EL
|
P302
|
Lightning Protection Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P303
|
|
18,232.00
|
₽ 1,285.13
|
₽ 23,430,400.00
|
|
EL
|
P303
|
Earthing Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
EL
|
P303
|
Emergency, evacuation lightingof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
EL
|
P303
|
Lighting Fixturesof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
EL
|
P303
|
Lightning Protection Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
EL
|
P304
|
|
19,928.00
|
₽ 1,286.03
|
₽ 25,628,000.00
|
|
EL
|
P304
|
Earthing Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
EL
|
P304
|
Emergency, evacuation lightingof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
EL
|
P304
|
Lighting Fixturesof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
EL
|
P304
|
Lightning Protection Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
|
|
5,128,988.00
|
₽ 1,514.90
|
₽ 7,769,903,000.00
|
|
IN
|
Benua Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Benua Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Benua Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Benua Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Benua Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Tihoretskiy Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Tihoretskiy Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Tihoretskiy Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Tihoretskiy Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Tihoretskiy Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Kurchatov Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Kurchatov Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Kurchatov Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Kurchatov Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Kurchatov Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Politekh Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Politekh Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Politekh Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Politekh Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Politekh Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Atom Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Atom Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Atom Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Atom Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Atom Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
RTK Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
RTK Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
RTK Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
RTK Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
RTK Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P101
|
|
32,648.00
|
₽ 1,286.15
|
₽ 41,990,300.00
|
|
IN
|
P101
|
Access Control Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
BMS (Building Management System)of the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
CCTV Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Internet access system and IP televisionof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Protective Deratization System of the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Public Announcement Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Security alarm systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Structured Cabling Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P101
|
Telecommunication Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P102
|
|
42,262.00
|
₽ 1,286.34
|
₽ 54,363,100.00
|
|
IN
|
P102
|
Access Control Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
BMS (Building Management System)of the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
CCTV Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Internet access system and IP televisionof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Protective Deratization System of the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Public Announcement Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Security alarm systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Structured Cabling Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
IN
|
P102
|
Telecommunication Systemof the parking (sqm)
|
3,842.00
|
₽ 1,286.34
|
₽ 4,942,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P103
|
|
50,358.00
|
₽ 1,285.12
|
₽ 64,716,300.00
|
|
IN
|
P103
|
Access Control Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
BMS (Building Management System)of the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
CCTV Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Internet access system and IP televisionof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Protective Deratization System of the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Public Announcement Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Security alarm systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Structured Cabling Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
IN
|
P103
|
Telecommunication Systemof the parking (sqm)
|
4,578.00
|
₽ 1,285.12
|
₽ 5,883,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P104
|
|
40,128.00
|
₽ 1,285.94
|
₽ 51,602,100.00
|
|
IN
|
P104
|
Access Control Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
BMS (Building Management System)of the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
CCTV Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Internet access system and IP televisionof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Protective Deratization System of the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Public Announcement Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Security alarm systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Structured Cabling Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
IN
|
P104
|
Telecommunication Systemof the parking (sqm)
|
3,648.00
|
₽ 1,285.94
|
₽ 4,691,100.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P105
|
|
32,648.00
|
₽ 1,286.15
|
₽ 41,990,300.00
|
|
IN
|
P105
|
Access Control Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
BMS (Building Management System)of the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
CCTV Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Internet access system and IP televisionof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Protective Deratization System of the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Public Announcement Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Security alarm systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Structured Cabling Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
IN
|
P105
|
Telecommunication Systemof the parking (sqm)
|
2,968.00
|
₽ 1,286.15
|
₽ 3,817,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P106
|
|
37,312.00
|
₽ 1,285.67
|
₽ 47,971,000.00
|
|
IN
|
P106
|
Access Control Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
BMS (Building Management System)of the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
CCTV Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Internet access system and IP televisionof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Protective Deratization System of the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Public Announcement Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Security alarm systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Structured Cabling Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
IN
|
P106
|
Telecommunication Systemof the parking (sqm)
|
3,392.00
|
₽ 1,285.67
|
₽ 4,361,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P107
|
|
35,024.00
|
₽ 1,286.43
|
₽ 45,056,000.00
|
|
IN
|
P107
|
Access Control Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
BMS (Building Management System)of the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
CCTV Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Internet access system and IP televisionof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Protective Deratization System of the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Public Announcement Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Security alarm systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Structured Cabling Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
IN
|
P107
|
Telecommunication Systemof the parking (sqm)
|
3,184.00
|
₽ 1,286.43
|
₽ 4,096,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P108
|
|
43,098.00
|
₽ 1,285.15
|
₽ 55,387,200.00
|
|
IN
|
P108
|
Access Control Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
BMS (Building Management System)of the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
CCTV Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Internet access system and IP televisionof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Protective Deratization System of the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Public Announcement Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Security alarm systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Structured Cabling Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
IN
|
P108
|
Telecommunication Systemof the parking (sqm)
|
3,918.00
|
₽ 1,285.15
|
₽ 5,035,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P109
|
|
41,976.00
|
₽ 1,285.30
|
₽ 53,951,700.00
|
|
IN
|
P109
|
Access Control Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
BMS (Building Management System)of the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
CCTV Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Internet access system and IP televisionof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Protective Deratization System of the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Public Announcement Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Security alarm systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Structured Cabling Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
IN
|
P109
|
Telecommunication Systemof the parking (sqm)
|
3,816.00
|
₽ 1,285.30
|
₽ 4,904,700.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P110
|
|
46,508.00
|
₽ 1,285.81
|
₽ 59,800,400.00
|
|
IN
|
P110
|
Access Control Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
BMS (Building Management System)of the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
CCTV Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Internet access system and IP televisionof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Protective Deratization System of the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Public Announcement Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Security alarm systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Structured Cabling Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
IN
|
P110
|
Telecommunication Systemof the parking (sqm)
|
4,228.00
|
₽ 1,285.81
|
₽ 5,436,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P111
|
|
40,766.00
|
₽ 1,286.08
|
₽ 52,428,200.00
|
|
IN
|
P111
|
Access Control Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
BMS (Building Management System)of the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
CCTV Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Fire and Security Alarm Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Internet access system and IP televisionof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Protective Deratization System of the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Public Announcement Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Security alarm systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Structured Cabling Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
IN
|
P111
|
Telecommunication Systemof the parking (sqm)
|
3,706.00
|
₽ 1,286.08
|
₽ 4,766,200.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Akadem Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Akadem Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Akadem Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Akadem Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Akadem Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Nauki Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Nauki Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Nauki Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Nauki Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Nauki Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P201
|
|
52,470.00
|
₽ 1,285.60
|
₽ 67,455,300.00
|
|
IN
|
P201
|
Access Control Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
BMS (Building Management System)of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
CCTV Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Internet access system and IP televisionof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Protective Deratization System of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Public Announcement Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Security alarm systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Structured Cabling Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P201
|
Telecommunication Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P202
|
|
52,470.00
|
₽ 1,285.60
|
₽ 67,455,300.00
|
|
IN
|
P202
|
Access Control Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
BMS (Building Management System)of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
CCTV Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Internet access system and IP televisionof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Protective Deratization System of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Public Announcement Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Security alarm systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Structured Cabling Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P202
|
Telecommunication Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P203
|
|
50,138.00
|
₽ 1,285.13
|
₽ 64,433,600.00
|
|
IN
|
P203
|
Access Control Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
BMS (Building Management System)of the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
CCTV Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Internet access system and IP televisionof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Protective Deratization System of the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Public Announcement Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Security alarm systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Structured Cabling Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P203
|
Telecommunication Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P204
|
|
54,802.00
|
₽ 1,286.03
|
₽ 70,477,000.00
|
|
IN
|
P204
|
Access Control Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
BMS (Building Management System)of the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
CCTV Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Internet access system and IP televisionof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Protective Deratization System of the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Public Announcement Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Security alarm systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Structured Cabling Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P204
|
Telecommunication Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
CHapaev Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
CHapaev Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
CHapaev Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
CHapaev Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
CHapaev Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
Budenniy Tower
|
|
426,650.00
|
₽ 1,561.23
|
₽ 666,100,400.00
|
|
IN
|
Budenniy Tower
|
Access Control Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Access Control Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
BMS (Building Management System)of the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
BMS (Building Management System)of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
BMS (Building Management System)of the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
CCTV Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
CCTV Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
CCTV Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Fire and Security Alarm Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Fire and Security Alarm Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Fire and Security Alarm Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Intercom Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Internet access system and IP televisionof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Internet access system and IP televisionof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Internet access system and IP televisionof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Protective Deratization System of the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Public Announcement Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Public Announcement Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Public Announcement Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Radio Broadcast System and Emergency Notificationof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Radio Broadcast System and Emergency Notificationof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Security alarm systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Security alarm systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Security alarm systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
IN
|
Budenniy Tower
|
Structured Cabling Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Structured Cabling Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Telecommunication Systemof the commercial (sqm)
|
2,438.00
|
₽ 1,485.23
|
₽ 3,621,000.00
|
|
IN
|
Budenniy Tower
|
Telecommunication Systemof the parking (sqm)
|
2,438.00
|
₽ 1,285.23
|
₽ 3,133,400.00
|
|
IN
|
Budenniy Tower
|
Telecommunication Systemof the resident (sqm)
|
37,789.00
|
₽ 1,585.23
|
₽ 59,904,400.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P301
|
|
52,470.00
|
₽ 1,285.60
|
₽ 67,455,300.00
|
|
IN
|
P301
|
Access Control Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
BMS (Building Management System)of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
CCTV Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Internet access system and IP televisionof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Protective Deratization System of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Public Announcement Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Security alarm systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Structured Cabling Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P301
|
Telecommunication Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P302
|
|
52,470.00
|
₽ 1,285.60
|
₽ 67,455,300.00
|
|
IN
|
P302
|
Access Control Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
BMS (Building Management System)of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
CCTV Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Internet access system and IP televisionof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Protective Deratization System of the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Public Announcement Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Security alarm systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Structured Cabling Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
IN
|
P302
|
Telecommunication Systemof the parking (sqm)
|
4,770.00
|
₽ 1,285.60
|
₽ 6,132,300.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P303
|
|
50,138.00
|
₽ 1,285.13
|
₽ 64,433,600.00
|
|
IN
|
P303
|
Access Control Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
BMS (Building Management System)of the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
CCTV Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Internet access system and IP televisionof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Protective Deratization System of the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Public Announcement Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Security alarm systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Structured Cabling Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
IN
|
P303
|
Telecommunication Systemof the parking (sqm)
|
4,558.00
|
₽ 1,285.13
|
₽ 5,857,600.00
|
|
|
|
|
nan
|
₽ nan
|
₽ nan
|
|
IN
|
P304
|
|
54,802.00
|
₽ 1,286.03
|
₽ 70,477,000.00
|
|
IN
|
P304
|
Access Control Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
BMS (Building Management System)of the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
CCTV Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Fire and Security Alarm Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Internet access system and IP televisionof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Protective Deratization System of the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Public Announcement Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Radio Broadcast System and Emergency Notificationof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Security alarm systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Structured Cabling Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|
|
IN
|
P304
|
Telecommunication Systemof the parking (sqm)
|
4,982.00
|
₽ 1,286.03
|
₽ 6,407,000.00
|